2521 S LONG BEACH AVE 90058
Certificate Information: 2521 S LONG BEACH AVE 90058
- Application / Permit
- 21010-20000-03421
- Plan Check / Job No.
- B21VN08883
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (11) Homeless Shelter
- Work Description
- EMERGENCY HOMELESS SHELTER (PER LAMC SEC. 12.81) AND LAFD DIRECTIVE 45, SECTION II. USE OF EXISTING SPACE. 60 BEDS TOTAL.
- Permit Issued
- Issued on 11/23/2021
- Issuing Office
- Current Status
- CofO Issued on 2/9/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/15/2021 | KEVIN MORALES |
| Corrections Issued | 7/20/2021 | KEVIN MORALES |
| Quality Review Completed | 7/20/2021 | EUGENE BARBEAU |
| Plan Check Approved | 11/1/2021 | KEVIN MORALES |
| No Progress | 11/1/2021 | KEVIN MORALES |
| Plan Check Approved | 11/23/2021 | KEVIN MORALES |
| Issued | 11/23/2021 | APPLICANT |
| CofO in Progress | 2/9/2023 | ERNESTO CORRAL |
| Permit Finaled | 2/9/2023 | ERNESTO CORRAL |
| CofO Issued | 2/9/2023 | ERNESTO CORRAL |
| Permit Finaled | 2/9/2023 | ERNESTO CORRAL |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/23/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 8/27/2021 | CECILIO NAVARRO |
| Hydrant and Access approval | Cleared | 8/30/2021 | KURT CORRAL |
| Fire Marshal Fire Life Safety | Cleared | 9/14/2021 | MENOA AGHAJANI |
| DAS Clearance | Cleared | 11/23/2021 | Rodolfo Arias |
Contact Information
| Contractor | Shipp D; Lic. No.: 969514-B | 1160 N COAST HWY LAGUNA BEACH, CA 92651 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wood Frame | 3/11/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Deputy Drilled-In Anchors | 3/17/2022 | Conditional Approval | DARRYL ARNOLD |
| Light Gage Steel Frame | 4/13/2022 | Approved | RUSSELL BONVOULOIR |
| Light Gage Steel Frame | 7/13/2022 | Approved | MARK FERRARI |
| Light Gage Steel Frame | 7/18/2022 | Partial Approval | RAFAEL ESPINOZA |
| Interior/Exterior Lathing | 8/4/2022 | Approved | RUSSELL BONVOULOIR |
| T-Bar Ceiling | 9/12/2022 | Approved | RUSSELL BONVOULOIR |
| Final | 2/2/2023 | Conditional Approval | ALAN MORELOS |
| SGSOV-Seismic Gas S/O Valve | 2/2/2023 | SGSOV Approved | ALAN MORELOS |
| Smoke Detectors | 2/2/2023 | Approved | ALAN MORELOS |
| Final | 2/8/2023 | Conditional Approval | ALAN MORELOS |
| Final | 2/9/2023 | Conditional Approval | ALAN MORELOS |