1031 S BUNDY DR 90049
Certificate Information: 1031 S BUNDY DR 90049
- Application / Permit
- 21010-20000-03414
- Plan Check / Job No.
- B21VN08845
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- NEW (25'-3" x 20') DETACHED 2-CAR GARAGE. WORK PER ENGINEER.
- Permit Issued
- Issued on 5/24/2022
- Issuing Office
- Current Status
- CofO Issued on 4/9/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/29/2021 | TROY DEGUZMAN |
| Corrections Issued | 7/30/2021 | TROY DEGUZMAN |
| Quality Review Completed | 8/18/2021 | OMID HEDAYAT |
| Applicant returned to address corrections | 12/3/2021 | TROY DEGUZMAN |
| Plan Check Approved | 4/6/2022 | TROY DEGUZMAN |
| Building Plans Picked Up | 5/20/2022 | APPLICANT |
| Issued | 5/24/2022 | APPLICANT |
| CofO in Progress | 3/27/2026 | MICHAEL ALLEN |
| Permit Finaled | 4/9/2026 | RICHARD STEINBACH |
| CofO Issued | 4/9/2026 | RICHARD STEINBACH |
| Permit Finaled | 4/9/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 12/2/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 12/13/2021 | MARCO SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/6/2022 | HISASHI KOBAYAKAWA |
| Roof/Waste drainage to street | Cleared | 2/22/2022 | HISASHI KOBAYAKAWA |
| Green Code | Cleared | 4/5/2022 | TROY DEGUZMAN |
Contact Information
| Contractor | Sterling Consulting And Construction Services Inc; Lic. No.: 1075574-B | 9 TAFFETA LANE LADERA RANCH, CA 92694 |
| Engineer | Mah,, Edwin Poy-Dor; Lic. No.: C27141 | 1740 APPIAN WAY MONTEBELLO, CA 90640 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/28/2022 | Partial Approval | JOHN KIDWELL |
| METHANE-Barrier | 9/28/2022 | Partial Approval | JOHN KIDWELL |
| METHANE-Subgrade | 9/28/2022 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 10/3/2022 | Partial Approval | ASHLEY THOMPSON |
| METHANE-Barrier | 10/3/2022 | Approved | ASHLEY THOMPSON |
| METHANE-Subgrade | 10/3/2022 | Approved | ASHLEY THOMPSON |
| Deputy Reinf. Concrete | 10/13/2022 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 10/14/2022 | Approved | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 11/21/2022 | Not Ready for Inspection | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/21/2022 | Conditional Approval | ASHLEY THOMPSON |
| Green Building Rough | 11/21/2022 | Not Ready for Inspection | ASHLEY THOMPSON |
| METHANE-Rough | 11/21/2022 | Approved | ASHLEY THOMPSON |
| Special/Order Compliance | 11/21/2022 | Partial Inspection | MICHAEL PELHAM |
| Special/Order Compliance | 1/17/2023 | Corrections Issued | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 1/30/2023 | Corrections Issued | DAVID FEILER |
| Interior/Exterior Lathing | 1/30/2023 | Corrections Issued | DAVID FEILER |
| BUILDING-Rough-Frame | 2/14/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| ELECTRICAL-Rough | 2/14/2023 | Approved | CLAYTON GRAHAM |
| Green Building Rough | 2/14/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| PLUMBING-Rough | 2/14/2023 | Corrections Issued | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 2/23/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| HVAC-Rough | 2/23/2023 | Approved | CLAYTON GRAHAM |
| PLUMBING-Rough | 2/23/2023 | Approved | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 2/27/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 3/2/2023 | Partial Approval | CLAYTON GRAHAM |
| Drywall Nailing | 3/9/2023 | Corrections Issued | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 3/9/2023 | Partial Approval | CLAYTON GRAHAM |
| Drywall Nailing | 3/10/2023 | Approved | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 3/31/2023 | Corrections Issued | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 10/12/2023 | Approved | MICHAEL PELHAM |
| Green Building Rough | 10/12/2023 | Approved | MICHAEL PELHAM |
| HVAC-Rough | 10/12/2023 | Approved | MICHAEL PELHAM |
| Insulation | 10/12/2023 | Not Ready for Inspection | MICHAEL PELHAM |
| Interior/Exterior Lathing | 10/12/2023 | Partial Approval | MICHAEL PELHAM |
| Final | 2/20/2025 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 2/20/2025 | Approved | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 2/20/2025 | SGSOV Approved | KIRK SANDERS |
| Service/Power Release | 2/20/2025 | Approved | KIRK SANDERS |
| Smoke Detectors | 2/20/2025 | Approved | KIRK SANDERS |
| Final | 6/24/2025 | Partial Approval | KIRK SANDERS |
| Final | 7/21/2025 | Corrections Issued | ARAM AVEDISIAN |
| Final | 3/26/2026 | OK to Issue CofO | MICHAEL ALLEN |