941 N ORLANDO AVE 90069
Certificate Information: 941 N ORLANDO AVE 90069
- Application / Permit
- 21010-20000-03411
- Plan Check / Job No.
- B21VN08840
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 69'-0" X 48'-0" 2-STORY SFD W/ATT TWO CAR GARAGE AND 41'-2" X 25'-6" ROOF DECK. SPRINKLERED THROUGHOUT.
- Permit Issued
- Issued on 12/13/2021
- Issuing Office
- Current Status
- CofO Issued on 11/3/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/15/2021 | ARTIN ZARUKIAN |
| Corrections Issued | 7/17/2021 | ARTIN ZARUKIAN |
| Quality Review Completed | 7/26/2021 | STEVEN KIM |
| Applicant returned to address corrections | 11/4/2021 | ARTIN ZARUKIAN |
| Applicant returned to address corrections | 12/1/2021 | ARTIN ZARUKIAN |
| Plan Check Approved | 12/13/2021 | ARTIN ZARUKIAN |
| Issued | 12/13/2021 | APPLICANT |
| Building Plans Picked Up | 12/15/2021 | APPLICANT |
| CofO in Progress | 10/13/2022 | MICHAEL LEWIS |
| Permit Finaled | 11/3/2022 | RONALD MYRICK |
| CofO Issued | 11/3/2022 | RONALD MYRICK |
| Permit Finaled | 11/3/2022 | RONALD MYRICK |
Permit Application Clearance Information
| Permit | Cleared | 8/4/2021 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 8/10/2021 | THOMAS LANG |
| Sewer availability | Cleared | 9/2/2021 | THOMAS LANG |
| Hydrant and Access approval | Cleared | 9/22/2021 | KURT CORRAL |
| Roof/Waste drainage to street | Cleared | 10/12/2021 | THOMAS LANG |
| Address approval | Cleared | 11/8/2021 | JEANETTE VONG |
| Low Impact Development | Cleared | 11/8/2021 | IDA MEISAMI-FARD |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 12/16/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 1/10/2022 | Partial Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 1/18/2022 | Approved | CHRIS CHRISTENSEN |
| Wood Frame | 2/2/2022 | Partial Approval | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 2/14/2022 | Conditional Approval | CHRIS CHRISTENSEN |
| Deputy Wood Construction | 3/4/2022 | Conditional Approval | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 3/4/2022 | Partial Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 3/25/2022 | Corrections Issued | JOSEPH MCGARRY |
| HVAC-Rough | 3/25/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| PLUMBING-Rough | 3/25/2022 | Conditional Approval | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 3/29/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Gas Test | 3/29/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| Green Building Rough | 3/29/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 3/29/2022 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 3/30/2022 | Approved | ALIZAH MAYAGOITIA |
| Rough-Elec/Plmb/HVAC | 3/30/2022 | Approved | ALIZAH MAYAGOITIA |
| Shower Pan | 3/30/2022 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 4/8/2022 | Approved | ARTHUR SARGSYAN |
| Drywall Nailing | 4/15/2022 | Approved | JUSTIN CURTIS |
| Green Building Rough | 4/15/2022 | Approved | JUSTIN CURTIS |
| Interior/Exterior Lathing | 4/15/2022 | Not Ready for Inspection | JUSTIN CURTIS |
| Interior/Exterior Lathing | 4/18/2022 | Not Ready for Inspection | ADAM ESCOTO |
| Interior/Exterior Lathing | 4/20/2022 | Approved | ADAM ESCOTO |
| ELECTRICAL-Final | 8/25/2022 | Partial Inspection | MICHAEL LEWIS |
| Green Building Final | 8/29/2022 | Partial Approval | MICHAEL LEWIS |
| Service/Power Release | 8/29/2022 | Approved | MICHAEL LEWIS |
| HVAC-Final | 9/9/2022 | Partial Inspection | MICHAEL LEWIS |
| PLUMBING-Final | 9/9/2022 | Approved | MICHAEL LEWIS |
| Final | 9/12/2022 | Corrections Issued | MICHAEL LEWIS |
| Green Building Final | 9/12/2022 | Corrections Issued | MICHAEL LEWIS |
| HVAC-Final | 9/12/2022 | Conditional Approval | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 9/12/2022 | SGSOV Approved | MICHAEL LEWIS |
| Smoke Detectors | 9/12/2022 | Approved | MICHAEL LEWIS |
| Service/Power Release | 9/20/2022 | Partial Inspection | MICHAEL LEWIS |
| ELECTRICAL-Final | 9/29/2022 | Approved | MICHAEL LEWIS |
| Final | 9/29/2022 | Corrections Issued | MICHAEL LEWIS |
| Green Building Final | 9/29/2022 | Approved | MICHAEL LEWIS |
| HVAC-Final | 9/29/2022 | Approved | MICHAEL LEWIS |
| Final | 10/12/2022 | OK to Issue CofO | MICHAEL LEWIS |