8167 N ST CLAIR AVE 91605
Certificate Information: 8167 N ST CLAIR AVE 91605
- Application / Permit
- 21010-20000-03410
- Plan Check / Job No.
- B21VN08838
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Carport
- Work Description
- NEW 19' X 45'- 4" DETACHED STORAGE/CARPORT AND BATHROOM WITH EXTERIOR ACCESS ONLY. ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 1/7/2022
- Issuing Office
- Current Status
- CofO Issued on 1/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/15/2021 | GURUNATH NESARAJAH |
| Corrections Issued | 7/18/2021 | GURUNATH NESARAJAH |
| Plan Check Approved | 1/7/2022 | OMAR GARNICA |
| Issued | 1/7/2022 | APPLICANT |
| Building Plans Picked Up | 1/7/2022 | APPLICANT |
| CofO in Progress | 12/28/2022 | JENNIFER RABUCHIN |
| Permit Finaled | 1/14/2023 | MICHAEL SMITH |
| CofO Issued | 1/14/2023 | MICHAEL SMITH |
| Permit Finaled | 1/14/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/28/2021 | DAGOVERTO GUERRERO |
| Construction near power lines | Cleared | 10/21/2021 | RIDWAN HARDY |
| Construction within easement | Cleared | 10/21/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 12/14/2021 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 12/15/2021 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/21/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Underground Mechanical | 3/21/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Excavation/Setback/Form/Re-Bar | 3/30/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 3/30/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Wood Frame | 4/28/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 5/3/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 5/3/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Deputy Wood Construction | 5/9/2022 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 5/19/2022 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 5/19/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Gas Test | 5/19/2022 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 5/19/2022 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 5/19/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Sewer | 5/19/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Shower Pan | 5/19/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Underground Mechanical | 5/19/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 6/27/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 7/14/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 7/14/2022 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 11/21/2022 | Approved | JENNIFER RABUCHIN |
| Final | 11/21/2022 | OK to Issue CofO | JENNIFER RABUCHIN |
| Green Building Final | 11/21/2022 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 11/21/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 11/21/2022 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 11/21/2022 | SGSOV Approved | JENNIFER RABUCHIN |
| Service/Power Release | 11/21/2022 | Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 11/21/2022 | Approved | JENNIFER RABUCHIN |