19601 W STRATHERN ST 91335
Certificate Information: 19601 W STRATHERN ST 91335
- Application / Permit
- 21010-20000-03385
- Plan Check / Job No.
- B21VN08785
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 1-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)(d) & WFPP
- Permit Issued
- Issued on 1/6/2022
- Issuing Office
- Current Status
- CofO Issued on 9/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/12/2021 | NILOOFAR MEHRAIN |
| Corrections Issued | 8/17/2021 | NILOOFAR MEHRAIN |
| Quality Review Completed | 8/19/2021 | STEVEN KIM |
| Building Plans Picked Up | 8/23/2021 | APPLICANT |
| Plan Check Approved | 12/29/2021 | NILOOFAR MEHRAIN |
| Issued | 1/6/2022 | APPLICANT |
| CofO in Progress | 8/29/2023 | JEFFREY BULL |
| Permit Finaled | 9/6/2023 | JOHN JANSON |
| CofO Issued | 9/6/2023 | JOHN JANSON |
| Permit Finaled | 9/6/2023 | JOHN JANSON |
Permit Application Clearance Information
| Construction near power lines | Cleared | 10/8/2021 | RIDWAN HARDY |
| Construction within easement | Cleared | 10/8/2021 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 10/10/2021 | GILBERT URREA |
| Low Impact Development | Cleared | 10/21/2021 | JORGE MEJIA LEMUS |
| Address approval | Cleared | 10/26/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 10/26/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 10/26/2021 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 10/29/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/23/2022 | Not Ready for Inspection | VINCENT HANLEY |
| Underground Mechanical | 3/23/2022 | Partial Approval | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 3/31/2022 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 3/31/2022 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2022 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 9/19/2022 | Approved | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2022 | Approved | JEFFREY BULL |
| PLUMBING-Rough | 9/19/2022 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 10/5/2022 | Partial Approval | VINCENT HANLEY |
| Green Building Rough | 10/5/2022 | Approved | VINCENT HANLEY |
| HVAC-Rough | 10/5/2022 | Approved | VINCENT HANLEY |
| Insulation | 10/5/2022 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 10/5/2022 | Approved | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 10/5/2022 | Not Ready for Inspection | VINCENT HANLEY |
| Drywall Nailing | 10/28/2022 | Approved | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 5/3/2023 | Approved | JEFFREY BULL |
| ELECTRICAL-Final | 5/3/2023 | Approved | JEFFREY BULL |
| Final | 5/3/2023 | Corrections Issued | JEFFREY BULL |
| Green Building Final | 5/3/2023 | Approved | JEFFREY BULL |
| HVAC-Final | 5/3/2023 | Approved | JEFFREY BULL |
| PLUMBING-Final | 5/3/2023 | Approved | JEFFREY BULL |
| Pre-Inspection | 5/3/2023 | Partial Inspection | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 5/3/2023 | SGSOV Not Ready | JEFFREY BULL |
| Service/Power Release | 5/3/2023 | Not Ready for Inspection | JEFFREY BULL |
| Smoke Detectors | 5/3/2023 | Approved | JEFFREY BULL |
| Final | 5/26/2023 | Not Ready for Inspection | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 5/26/2023 | SGSOV Approved | JEFFREY BULL |
| Service/Power Release | 5/26/2023 | Approved | JEFFREY BULL |
| Final | 8/29/2023 | OK to Issue CofO | JEFFREY BULL |