4924 N LLANO DR 91364

Certificate Information: 4924 N LLANO DR 91364

Application / Permit
21010-20000-03380
Plan Check / Job No.
B21VN08771
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 3-STORY SFD W/ ATTACHED 2-CAR GARAGE (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 8/11/2023
Issuing Office
Valley
Current Status
Issued on 8/11/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/7/2021 APPLICANT
Assigned to Plan Check Engineer 8/12/2021 NILOOFAR MEHRAIN
Corrections Issued 8/17/2021 NILOOFAR MEHRAIN
Quality Review Completed 8/27/2021 STEVEN KIM
Building Plans Picked Up 9/1/2021 APPLICANT
Applicant returned to address corrections 11/18/2022 NILOOFAR MEHRAIN
Applicant returned to address corrections 12/14/2022 NILOOFAR MEHRAIN
Applicant returned to address corrections 4/13/2023 NILOOFAR MEHRAIN
Applicant returned to address corrections 5/19/2023 NILOOFAR MEHRAIN
Applicant returned to address corrections 6/30/2023 NILOOFAR MEHRAIN
Plan Check Approved 8/3/2023 NILOOFAR MEHRAIN
Issued 8/11/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 12/1/2021 DAGOVERTO GUERRERO
BHO/Hillside ordinance Cleared 12/1/2021 DAGOVERTO GUERRERO
BHO/Hillside ordinance Cleared 12/1/2021 DAGOVERTO GUERRERO
BHO/Hillside ordinance Cleared 12/1/2021 DAGOVERTO GUERRERO
BHO/Hillside ordinance Cleared 12/1/2021 DAGOVERTO GUERRERO
BHO/Hillside ordinance Cleared 12/1/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 12/1/2021 DAGOVERTO GUERRERO
Permit Cleared 12/1/2021 DAGOVERTO GUERRERO
Trees in Parkway Cleared 4/6/2022 ADALBERTO VERA
Hydrant and Access approval Cleared 4/20/2022 KURT CORRAL
Low Impact Development Cleared 10/3/2022 ERNEST TSE
Roof/Waste drainage to street Cleared 10/4/2022 DAGOVERTO GUERRERO
Miscellaneous Cleared 10/24/2022 NELSON RODRIGUEZ
Miscellaneous Cleared 10/24/2022 NELSON RODRIGUEZ
Miscellaneous Cleared 10/24/2022 NELSON RODRIGUEZ
Miscellaneous Cleared 10/24/2022 NELSON RODRIGUEZ
Miscellaneous Cleared 10/24/2022 NELSON RODRIGUEZ
Specific Plan Cleared 10/24/2022 NELSON RODRIGUEZ
ZA Case Cleared 10/24/2022 NELSON RODRIGUEZ
ZA Case Cleared 10/24/2022 NELSON RODRIGUEZ
ZI Cleared 10/24/2022 NELSON RODRIGUEZ
Sewer availability Cleared 10/28/2022 DAGOVERTO GUERRERO
Building over 36-ft Cleared 12/14/2022 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 12/14/2022 CALOSHA APPROVED
GPI Written Notices Cleared 12/14/2022 NILOOFAR MEHRAIN
Grading Pre-Inspection Cleared 12/14/2022 NILOOFAR MEHRAIN

Contact Information

Architect Di, Zitti, Fernando; Lic. No.: C24587 21731 VENTURA BLVD #110      WOODLAND HILLS, CA 91364
Contractor K S Construction And Design Inc; Lic. No.: 952277-B 22141 VENTURA BL SUITE 304      WOODLAND HILLS, CA 91364
Engineer Miller,, Karen Lynn; Lic. No.: GE2257 6634 VALJEAN AVENUE      VAN NUYS, CA 91406
Geologist Ruberti,, Rudolph F; Lic. No.: EG1708 6634 VALJEAN AVE      VAN NUYS, CA 91406

Inspector Information

JOHN HAYES, (818) 774-4302 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/13/2023 Not Ready for Inspection PETER FOLLING
Deputy Grading 12/5/2023 Partial Approval JOHN KIDWELL
Pre-Inspection 12/5/2023 Partial Inspection JOHN KIDWELL
Deputy Grading 12/8/2023 Partial Approval JOHN KIDWELL
Deputy Grading 12/19/2023 Partial Approval JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 1/16/2024 Partial Approval JOHN KIDWELL
Piling/Pier/Caisson 1/16/2024 Partial Approval JOHN KIDWELL
Piling/Pier/Caisson 4/19/2024 Partial Approval MORRIS JACKSON
Special/Order Compliance 4/19/2024 Partial Inspection JOHN KIDWELL
Deputy Reinf. Concrete 4/22/2024 Conditional Approval MORRIS JACKSON
Excavation/Setback/Form/Re-Bar 7/8/2024 Partial Approval JOHN HAYES
Footing/Foundation/Slab 7/8/2024 Partial Approval JOHN HAYES
Piling/Pier/Caisson 7/8/2024 Partial Approval JOHN HAYES
Excavation/Setback/Form/Re-Bar 7/12/2024 Partial Approval JOHN HAYES
Piling/Pier/Caisson 7/12/2024 Partial Approval JOHN HAYES
Masonry Wall/Backfill 9/6/2024 Corrections Issued JOHN HAYES
Deputy Reinf. Concrete 9/27/2024 Conditional Approval JOHN HAYES
Excavation/Setback/Form/Re-Bar 9/27/2024 Partial Approval JOHN HAYES
Footing/Foundation/Slab 9/27/2024 Partial Approval JOHN HAYES
PLUMBING-Rough 9/27/2024 Not Ready for Inspection JOHN HAYES
Piling/Pier/Caisson 9/27/2024 Partial Approval JOHN HAYES
Deputy Reinf. Concrete 10/2/2024 Conditional Approval JOHN HAYES
Underground Mechanical 10/30/2024 Partial Approval JOHN HAYES
Underground Mechanical 11/1/2024 Partial Approval JOHN HAYES
Footing/Foundation/Slab 11/14/2024 Partial Approval JOHN HAYES
Footing/Foundation/Slab 11/18/2024 Partial Approval JOHN HAYES
Deputy Drilled-In Anchors 12/6/2024 Conditional Approval HENRY KIM
Deputy Reinf. Concrete 12/6/2024 Conditional Approval HENRY KIM
Excavation/Setback/Form/Re-Bar 12/6/2024 Partial Approval JOHN HAYES
Footing/Foundation/Slab 12/6/2024 Partial Approval JOHN HAYES
Excavation/Setback/Form/Re-Bar 12/24/2024 Partial Approval JOHN HAYES
Footing/Foundation/Slab 12/24/2024 Partial Approval JOHN HAYES
PLUMBING-Rough 12/24/2024 Partial Approval JOHN HAYES
Underground Mechanical 12/24/2024 Partial Approval JOHN HAYES
Excavation/Setback/Form/Re-Bar 1/16/2025 Partial Approval JOHN HAYES
Reinforced Concrete Frame 1/16/2025 Partial Approval JOHN HAYES
Reinforced Masonry Frame 1/16/2025 Partial Approval JOHN HAYES
Deputy Drilled-In Anchors 1/17/2025 Approved JOHN HAYES
Excavation/Setback/Form/Re-Bar 1/17/2025 Partial Approval JOHN HAYES
Footing/Foundation/Slab 1/17/2025 Partial Approval JOHN HAYES
Reinforced Concrete Frame 1/17/2025 Partial Approval JOHN HAYES
Deputy Drilled-In Anchors 1/23/2025 Partial Approval SEAN WIRCH
Excavation/Setback/Form/Re-Bar 1/27/2025 Not Ready for Inspection JOHN HAYES
Reinforced Concrete Frame 1/27/2025 Not Ready for Inspection JOHN HAYES
Reinforced Masonry Frame 1/27/2025 Not Ready for Inspection JOHN HAYES
Excavation/Setback/Form/Re-Bar 1/29/2025 Partial Approval JOHN HAYES
Reinforced Concrete Frame 1/29/2025 Partial Approval JOHN HAYES
Reinforced Masonry Frame 1/29/2025 Partial Approval JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 2/19/2025 Partial Approval JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 3/5/2025 Partial Approval JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 3/18/2025 Partial Approval JOHN HAYES
Deputy Wood Construction 4/8/2025 Approved JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 4/8/2025 Partial Approval JOHN HAYES
Excavation/Setback/Form/Re-Bar 4/16/2025 Partial Approval JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 4/21/2025 Corrections Issued JOHN HAYES
Pre-Inspection 4/21/2025 Not Ready for Inspection JOHN HAYES
Wood Frame 4/21/2025 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 4/23/2025 Partial Approval JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 4/23/2025 Partial Approval JOHN HAYES
Green Building Rough 4/23/2025 Not Ready for Inspection JOHN HAYES
Pre-Inspection 4/23/2025 Partial Approval JOHN HAYES
Verify Sprinkler Sign Off 4/23/2025 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 6/23/2025 Approved JOHN HAYES
HVAC-Rough 7/10/2025 Corrections Issued JOHN HAYES
Rough-Elec/Plmb/HVAC 8/1/2025 Partial Approval JOHN HAYES
BUILDING-Rough-Frame 8/22/2025 Approved JOHN HAYES
Green Building Rough 8/22/2025 Approved JOHN HAYES
Interior/Exterior Lathing 8/22/2025 Partial Approval JOHN HAYES
Verify Sprinkler Sign Off 8/22/2025 Approved JOHN HAYES
Wood Frame 8/22/2025 Approved JOHN HAYES
Insulation 8/29/2025 Corrections Issued SCOTT SOBEL
HVAC-Rough 9/3/2025 Approved JOHN HAYES
Insulation 9/3/2025 Approved JOHN HAYES
Drywall Nailing 10/2/2025 Approved JOHN HAYES
Shower Pan 10/22/2025 Approved JOHN HAYES
Interior/Exterior Lathing 11/26/2025 Approved HENRY KIM
Sewer 4/3/2026 Partial Approval JON MCHUGH