5111 E WADENA ST 90032
Certificate Information: 5111 E WADENA ST 90032
- Application / Permit
- 21010-20000-03369
- Plan Check / Job No.
- B21VN08765
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED 42'-11" X 26'-9" 1-STORY ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). LAMC 12.22 A.33(c)1, (d)1, and (g) ALL WORK PER ENGINEERING NFPA 13D REQUIRED THROUGHOUT PER FIRE CLEARANCE
- Permit Issued
- Issued on 9/7/2022
- Issuing Office
- Valley
- Current Status
- Issued on 9/7/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/19/2021 | COLIN LOREDO |
| Corrections Issued | 8/24/2021 | COLIN LOREDO |
| Quality Review Completed | 9/2/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 9/14/2021 | APPLICANT |
| Applicant returned to address corrections | 8/23/2022 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 9/2/2022 | SEWADA ZADOORAN MILAGARDI |
| Issued | 9/7/2022 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/27/2021 | STEVE MELGAR |
| Sewer availability | Cleared | 10/27/2021 | STEVE MELGAR |
| Address approval | Cleared | 11/16/2021 | STEVE MELGAR |
| Construction near power lines | Cleared | 1/28/2022 | RIDWAN HARDY |
| Low Impact Development | Cleared | 5/20/2022 | KHAING AYE |
| Roof/Waste drainage to street | Cleared | 5/25/2022 | STEVE MELGAR |
| Hydrant and Access approval | Cleared | 8/13/2022 | RUEL COLE |
| GPI Written Notices | Cleared | 9/2/2022 | SEWADA ZADOORAN MILAGARDI |
| Grading Pre-Inspection | Cleared | 9/2/2022 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 12/30/2022 | No Access for Inspection | AMY COLIN |
| Footing/Foundation/Slab | 1/3/2023 | Corrections Issued | AMY COLIN |
| Footing/Foundation/Slab | 1/23/2023 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 2/14/2023 | Partial Inspection | OSVALDO PARAMO |
| Green Building Rough | 2/14/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 2/14/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 7/5/2023 | Partial Inspection | RUBEN SALAS |
| Wood Frame | 7/5/2023 | Partial Inspection | RUBEN SALAS |
| BUILDING-Rough-Frame | 8/11/2023 | Corrections Issued | AMY COLIN |
| ELECTRICAL-Rough | 8/11/2023 | Corrections Issued | AMY COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 8/11/2023 | Not Ready for Inspection | AMY COLIN |
| Green Building Rough | 8/11/2023 | Not Ready for Inspection | AMY COLIN |
| HVAC-Rough | 8/11/2023 | Partial Approval | AMY COLIN |
| PLUMBING-Rough | 8/11/2023 | Corrections Issued | AMY COLIN |
| Verify Sprinkler Sign Off | 8/11/2023 | Corrections Issued | AMY COLIN |
| Wood Frame | 8/11/2023 | Approved | AMY COLIN |
| BUILDING-Rough-Frame | 9/7/2023 | Not Ready for Inspection | AMY COLIN |
| ELECTRICAL-Rough | 9/7/2023 | Approved | AMY COLIN |
| Green Building Rough | 9/7/2023 | Approved | AMY COLIN |
| HVAC-Rough | 9/7/2023 | Approved | AMY COLIN |
| PLUMBING-Rough | 9/7/2023 | Not Ready for Inspection | AMY COLIN |
| Rough-Elec/Plmb/HVAC | 9/7/2023 | Partial Approval | AMY COLIN |
| Verify Sprinkler Sign Off | 9/7/2023 | Not Ready for Inspection | AMY COLIN |
| ELECTRICAL-Rough | 9/25/2023 | Approved | AMY COLIN |
| HVAC-Rough | 9/25/2023 | Approved | AMY COLIN |
| Insulation | 9/25/2023 | Corrections Issued | AMY COLIN |
| Interior/Exterior Lathing | 9/25/2023 | Partial Approval | AMY COLIN |
| PLUMBING-Rough | 9/25/2023 | Approved | AMY COLIN |
| Drywall Nailing | 10/13/2023 | Approved | AMY COLIN |
| PLUMBING-Rough | 10/20/2023 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 10/27/2023 | Approved | JOSH MEISTER |
| BUILDING-Rough-Frame | 11/4/2024 | No Access for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Final | 11/4/2024 | No Access for Inspection | LILIANA PORTILLO |
| Final | 11/4/2024 | No Access for Inspection | LILIANA PORTILLO |
| Green Building Final | 11/4/2024 | No Access for Inspection | LILIANA PORTILLO |
| HVAC-Final | 11/4/2024 | No Access for Inspection | LILIANA PORTILLO |
| PLUMBING-Final | 11/4/2024 | No Access for Inspection | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 11/4/2024 | SGSOV Not Ready | LILIANA PORTILLO |
| Service/Power Release | 11/4/2024 | No Access for Inspection | LILIANA PORTILLO |
| Smoke Detectors | 11/4/2024 | No Access for Inspection | LILIANA PORTILLO |
| Verify Sprinkler Sign Off | 11/4/2024 | No Access for Inspection | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 3/18/2026 | No Access for Inspection | LILIANA PORTILLO |
| Final | 3/18/2026 | No Access for Inspection | LILIANA PORTILLO |
| Green Building Final | 3/18/2026 | No Access for Inspection | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 3/18/2026 | SGSOV Not Ready | LILIANA PORTILLO |
| Service/Power Release | 3/18/2026 | No Access for Inspection | LILIANA PORTILLO |
| Smoke Detectors | 3/18/2026 | No Access for Inspection | LILIANA PORTILLO |
| Verify Sprinkler Sign Off | 3/18/2026 | No Access for Inspection | LILIANA PORTILLO |