821 1/2 N KODAK DR 90026

Certificate Information: 821 1/2 N KODAK DR 90026

Application / Permit
21010-20000-03366
Plan Check / Job No.
B21VN08764
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW TWO-STORY 20'-8" X 30'-8" ACCESSORY DWELLING UNIT PER WITH ROOF TOP DECK PER LAMC 12.22 A.33(c) and (d) ALL WORK PER ENGINEERING. “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.”
Permit Issued
Issued on 1/31/2022
Issuing Office
Current Status
CofO Issued on 12/24/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/7/2021 APPLICANT
Assigned to Plan Check Engineer 8/12/2021 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 8/18/2021 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 8/25/2021 OMID HEDAYAT
Applicant returned to address corrections 8/30/2021 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 12/16/2021 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 12/23/2021 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 1/13/2022 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 1/26/2022 SEWADA ZADOORAN MILAGARDI
Issued 1/31/2022 APPLICANT
CofO in Progress 11/18/2022 FREDDIE RIVERA
Permit Finaled 12/24/2022 DEROLD HAUFF
CofO Issued 12/24/2022 DEROLD HAUFF
Permit Finaled 12/24/2022 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 9/22/2021 BRIAN MILLER
Address approval Cleared 9/25/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 9/28/2021 CECILIO NAVARRO
Sewer availability Cleared 9/28/2021 CECILIO NAVARRO
BHO/Hillside ordinance Cleared 10/7/2021 CECILIO NAVARRO
BHO/Hillside ordinance Cleared 10/7/2021 CECILIO NAVARRO
BHO/Hillside ordinance Cleared 10/7/2021 CECILIO NAVARRO
BHO/Hillside ordinance Cleared 10/7/2021 CECILIO NAVARRO
BHO/Hillside ordinance Cleared 10/7/2021 CECILIO NAVARRO
Highway dedication Cleared 10/7/2021 CECILIO NAVARRO
GPI Written Notices Cleared 10/28/2021 SEWADA ZADOORAN MILAGARDI
Hydrant and Access approval Cleared 11/24/2021 MATTHEW CRAIG
Roof/Waste drainage to street Cleared 12/13/2021 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,
Engineer Standley,, Craig Erick; Lic. No.: C87675 5330 ZELZAH AVE UNIT 7      ENCINO, CA 91316

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/4/2022 Approved STUART CHAPMAN
Footing/Foundation/Slab 2/4/2022 Approved STUART CHAPMAN
Pre-Inspection 2/4/2022 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 2/17/2022 Partial Approval AMY COLIN
Green Building Rough 2/17/2022 Not Ready for Inspection AMY COLIN
Verify Sprinkler Sign Off 2/17/2022 Approved AMY COLIN
BUILDING-Rough-Frame 5/12/2022 Partial Inspection FREDDIE RIVERA
ELECTRICAL-Rough 5/12/2022 Corrections Issued FREDDIE RIVERA
Green Building Rough 5/12/2022 Partial Inspection FREDDIE RIVERA
HVAC-Rough 5/12/2022 Partial Inspection FREDDIE RIVERA
PLUMBING-Rough 5/12/2022 Partial Inspection FREDDIE RIVERA
ELECTRICAL-Rough 5/16/2022 Approved FREDDIE RIVERA
HVAC-Rough 5/16/2022 Approved FREDDIE RIVERA
PLUMBING-Rough 5/16/2022 Approved FREDDIE RIVERA
Sewer 5/16/2022 Approved FREDDIE RIVERA
Underground Mechanical 5/16/2022 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 5/17/2022 Corrections Issued FREDDIE RIVERA
Green Building Rough 5/17/2022 Approved FREDDIE RIVERA
Interior/Exterior Lathing 6/7/2022 Partial Approval ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 6/13/2022 Approved FREDDIE RIVERA
Insulation 6/13/2022 Approved FREDDIE RIVERA
Drywall Nailing 6/28/2022 Approved FREDDIE RIVERA
Interior/Exterior Lathing 6/28/2022 Approved FREDDIE RIVERA
ELECTRICAL-Final 8/31/2022 Corrections Issued FREDDIE RIVERA
Final 8/31/2022 Corrections Issued FREDDIE RIVERA
Green Building Final 8/31/2022 Corrections Issued FREDDIE RIVERA
HVAC-Final 8/31/2022 Partial Inspection FREDDIE RIVERA
PLUMBING-Final 8/31/2022 Corrections Issued FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 8/31/2022 SGSOV Approved FREDDIE RIVERA
Service/Power Release 8/31/2022 Approved FREDDIE RIVERA
Smoke Detectors 8/31/2022 Approved FREDDIE RIVERA
ELECTRICAL-Final 9/22/2022 Approved FREDDIE RIVERA
Final 9/22/2022 Corrections Issued FREDDIE RIVERA
Green Building Final 9/22/2022 Approved FREDDIE RIVERA
HVAC-Final 9/22/2022 Approved FREDDIE RIVERA
PLUMBING-Final 9/22/2022 Approved FREDDIE RIVERA
Final 11/18/2022 OK to Issue CofO FREDDIE RIVERA