854 E WARREN AVE 90291

Certificate Information: 854 E WARREN AVE 90291

Application / Permit
21010-20000-03363
Plan Check / Job No.
B21VN08760
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 30'-0" X 63'-0" TWO STORY FULLY SPRINKLERED SFD W/ATT GARAGE.
Permit Issued
Issued on 1/20/2022
Issuing Office
Current Status
CofO Issued on 9/23/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/7/2021 APPLICANT
Assigned to Plan Check Engineer 7/8/2021 ARTIN ZARUKIAN
Corrections Issued 7/10/2021 ARTIN ZARUKIAN
Quality Review Completed 7/16/2021 STEVEN KIM
Applicant returned to address corrections 8/7/2021 ARTIN ZARUKIAN
Applicant returned to address corrections 12/18/2021 ARTIN ZARUKIAN
Plan Check Approved 1/20/2022 ARTIN ZARUKIAN
Issued 1/20/2022 APPLICANT
Building Plans Picked Up 1/24/2022 APPLICANT
CofO in Progress 9/19/2022 DAVID FEILER
Permit Finaled 9/23/2022 DANIEL ORRANTE
CofO Issued 9/23/2022 DANIEL ORRANTE
Permit Finaled 9/23/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 7/21/2021 CATHERINE ADROVER
Permit Cleared 7/21/2021 CATHERINE ADROVER
ZI Cleared 7/21/2021 LOUIS ORTEGA
Eng Process Fee Ord 176,300 Cleared 7/26/2021 CATHERINE ADROVER
Sewer availability Cleared 8/10/2021 CATHERINE ADROVER
Specific Plan Cleared 8/30/2021 KEVIN ARUCAN
Trees in Parkway Cleared 9/2/2021 JOHN KIM
Low Impact Development Cleared 9/24/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 9/28/2021 DINAH GARIN
Hydrant and Access approval Cleared 11/24/2021 RUEL COLE

Contact Information

Contractor Owner-Builder       ,
Engineer Zolfaghari,, Saeed; Lic. No.: C86761 6201 BEE AVE      AGOURA HILLS, CA 91301

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/9/2022 Corrections Issued DAVID FEILER
Sewer 2/9/2022 Partial Inspection DAVID FEILER
Underground Mechanical 2/9/2022 Not Ready for Inspection DAVID FEILER
ELECTRICAL-Rough 2/11/2022 Partial Approval DAVID FEILER
Gas Test 2/11/2022 Partial Inspection DAVID FEILER
Sewer 2/11/2022 Approved DAVID FEILER
Underground Mechanical 2/11/2022 Partial Approval DAVID FEILER
Excavation/Setback/Form/Re-Bar 2/22/2022 Corrections Issued ANDREW NAVE
Footing/Foundation/Slab 2/22/2022 Not Ready for Inspection ANDREW NAVE
Excavation/Setback/Form/Re-Bar 2/25/2022 Approved JOHNNY MIRANDA
Footing/Foundation/Slab 2/25/2022 Approved JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 3/8/2022 Not Ready for Inspection DAVID FEILER
Structural Steel Frame 3/8/2022 Partial Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 3/16/2022 Partial Approval DAVID FEILER
Deputy Wood Construction 4/19/2022 No Access for Inspection DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 4/22/2022 Corrections Issued DAVID FEILER
Wood Frame 4/22/2022 Not Ready for Inspection DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 5/5/2022 Approved DAVID FEILER
BUILDING-Rough-Frame 5/26/2022 Not Ready for Inspection JESUS RODRIGUEZ
ELECTRICAL-Rough 5/26/2022 Not Ready for Inspection JESUS RODRIGUEZ
Green Building Rough 5/26/2022 Not Ready for Inspection JESUS RODRIGUEZ
HVAC-Rough 5/26/2022 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Rough 5/26/2022 Conditional Approval JESUS RODRIGUEZ
Verify Sprinkler Sign Off 5/26/2022 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 5/27/2022 Approved JESUS RODRIGUEZ
ELECTRICAL-Rough 5/27/2022 Approved JESUS RODRIGUEZ
Green Building Rough 5/27/2022 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 5/31/2022 Approved JESUS RODRIGUEZ
PLUMBING-Rough 5/31/2022 Approved JESUS RODRIGUEZ
Shower Pan 5/31/2022 Approved JESUS RODRIGUEZ
Insulation 6/13/2022 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 6/13/2022 Approved JESUS RODRIGUEZ
Shower Pan 6/13/2022 Approved JESUS RODRIGUEZ
Drywall Nailing 6/22/2022 Not Ready for Inspection DAVID FEILER
Drywall Nailing 6/23/2022 Approved DAVID FEILER
ELECTRICAL-Final 9/2/2022 Corrections Issued DAVID FEILER
Gas Test 9/2/2022 Approved DAVID FEILER
HVAC-Final 9/2/2022 Corrections Issued DAVID FEILER
PLUMBING-Final 9/2/2022 Approved DAVID FEILER
ELECTRICAL-Final 9/7/2022 Approved DAVID FEILER
HVAC-Final 9/7/2022 Approved DAVID FEILER
Final 9/16/2022 OK to Issue CofO DAVID FEILER
Green Building Final 9/16/2022 Approved DAVID FEILER
SGSOV-Seismic Gas S/O Valve 9/16/2022 SGSOV Approved DAVID FEILER
Service/Power Release 9/16/2022 Approved DAVID FEILER
Smoke Detectors 9/16/2022 Approved DAVID FEILER