16923 W GAULT ST 91406

Certificate Information: 16923 W GAULT ST 91406

Application / Permit
21010-20000-03360
Plan Check / Job No.
B21VN08759
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED (44'-0"x29'6"), 1200 SQFT ADU PER LAMC 12.22 A.33 (c)(d) The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.
Permit Issued
Issued on 4/28/2022
Issuing Office
Current Status
CofO Issued on 6/4/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/29/2021 APPLICANT
Assigned to Plan Check Engineer 9/2/2021 PETER MOSESIAN
Corrections Issued 9/3/2021 PETER MOSESIAN
Quality Review Completed 9/17/2021 OMID HEDAYAT
Building Plans Picked Up 9/20/2021 APPLICANT
Plan Check Approved 4/22/2022 PETER MOSESIAN
Issued 4/28/2022 APPLICANT
CofO in Progress 3/4/2024 VINCENT HANLEY
Permit Finaled 6/4/2024 JOHN JANSON
CofO Issued 6/4/2024 JOHN JANSON
Permit Finaled 6/4/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 12/17/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 12/21/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 12/21/2021 DAGOVERTO GUERRERO
Construction near power lines Cleared 3/23/2022 NADER ISKANDER
Hydrant and Access approval Cleared 3/28/2022 CINDY JOSSELYN
Roof/Waste drainage to street Cleared 4/25/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 10/6/2022 Approved SEAN HAUPT
Footing/Foundation/Slab 10/11/2022 Approved DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 10/31/2022 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 11/15/2022 Approved SEAN HAUPT
Rough-Elec/Plmb/HVAC 11/15/2022 Approved SEAN HAUPT
BUILDING-Rough-Frame 11/16/2022 Not Ready for Inspection SEAN HAUPT
Green Building Rough 11/16/2022 Approved SEAN HAUPT
Insulation 11/16/2022 Approved SEAN HAUPT
Interior/Exterior Lathing 11/16/2022 Approved SEAN HAUPT
Verify Sprinkler Sign Off 11/16/2022 Approved SEAN HAUPT
Drywall Nailing 11/22/2022 No Access for Inspection KRISTEN CAUSEY
Green Building Rough 11/22/2022 No Access for Inspection KRISTEN CAUSEY
Shower Pan 11/22/2022 No Access for Inspection KRISTEN CAUSEY
BUILDING-Rough-Frame 5/2/2023 Approved JON MCHUGH
Drywall Nailing 5/2/2023 Partial Approval JON MCHUGH
Final 5/2/2023 Corrections Issued JON MCHUGH
Green Building Final 5/2/2023 Corrections Issued JON MCHUGH
Green Building Rough 5/2/2023 Approved JON MCHUGH
SGSOV-Seismic Gas S/O Valve 5/2/2023 SGSOV Approved JON MCHUGH
Service/Power Release 5/2/2023 Not Ready for Inspection JON MCHUGH
Smoke Detectors 5/2/2023 Approved JON MCHUGH
Special/Order Compliance 5/2/2023 Approved JON MCHUGH
Drywall Nailing 5/4/2023 Not Ready for Inspection JON MCHUGH
Final 5/4/2023 Corrections Issued JON MCHUGH
Green Building Final 5/4/2023 Not Ready for Inspection JON MCHUGH
Service/Power Release 5/4/2023 Not Ready for Inspection JON MCHUGH
Special/Order Compliance 5/4/2023 Not Ready for Inspection JON MCHUGH
Drywall Nailing 5/19/2023 Approved HORACE FULTZ
Final 5/19/2023 Not Ready for Inspection HORACE FULTZ
Green Building Final 5/19/2023 Approved HORACE FULTZ
Service/Power Release 5/19/2023 Not Ready for Inspection HORACE FULTZ
ELECTRICAL-Final 3/1/2024 Approved VINCENT HANLEY
Final 3/1/2024 OK to Issue CofO VINCENT HANLEY
HVAC-Final 3/1/2024 Approved VINCENT HANLEY
PLUMBING-Final 3/1/2024 Approved VINCENT HANLEY
Service/Power Release 3/1/2024 Approved VINCENT HANLEY