2870 W AVENUE 33 90065
Certificate Information: 2870 W AVENUE 33 90065
- Application / Permit
- 21010-20000-03359
- Plan Check / Job No.
- B21VN08758
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 20' X 30' DETACHED ACCESSORY DWELLING UNIT WITH 9'-10" X 4'-1" PATIO COVER PER LAMC 12.22 A.33(c) and (d) ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 1/12/2022
- Issuing Office
- Current Status
- CofO Issued on 1/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/12/2021 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 8/16/2021 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 8/25/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 8/26/2021 | APPLICANT |
| Applicant returned to address corrections | 12/29/2021 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 1/12/2022 | SEWADA ZADOORAN MILAGARDI |
| Issued | 1/12/2022 | APPLICANT |
| CofO in Progress | 1/2/2025 | THOMAS LOGRASSO |
| Permit Finaled | 1/3/2025 | DEROLD HAUFF |
| CofO Issued | 1/3/2025 | DEROLD HAUFF |
| Permit Finaled | 1/3/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/3/2021 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 9/9/2021 | THOMAS LANG |
| ZI | Cleared | 9/20/2021 | KENTON TRINH |
| ZI | Cleared | 9/21/2021 | ADRINEH MELKONIAN |
| Low Impact Development | Cleared | 10/20/2021 | KHAING AYE |
| Hydrant and Access approval | Cleared | 11/5/2021 | KURT CORRAL |
| Roof/Waste drainage to street | Cleared | 11/10/2021 | THAN WIN |
| Sewer availability | Cleared | 11/18/2021 | PAMELA TENEZA |
| Construction near power lines | Cleared | 11/22/2021 | RIDWAN HARDY |
| Construction within easement | Cleared | 11/22/2021 | RIDWAN HARDY |
| Grading Pre-Inspection | Cleared | 1/3/2022 | ALEXANDER ANDREWS |
| GPI Written Notices | Cleared | 1/10/2022 | SEWADA ZADOORAN MILAGARDI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Abedian,, Vanik; Lic. No.: S5323 | 2906 JOLLEY DR BURBANK, CA 91504 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/18/2022 | Partial Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 4/1/2022 | Partial Approval | HAMIK HARTOUNIAN |
| Underground Mechanical | 4/7/2022 | Partial Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/2/2022 | Partial Approval | HAMIK HARTOUNIAN |
| Deputy Drilled-In Anchors | 5/4/2022 | Conditional Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2022 | Approved | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 5/5/2022 | Partial Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 6/8/2022 | Partial Approval | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 6/8/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 7/11/2022 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 7/11/2022 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 7/22/2022 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 8/8/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Wood Frame | 8/8/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| HVAC-Rough | 9/16/2022 | Approved | HAMIK HARTOUNIAN |
| MERV13>=Rough | 9/16/2022 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 9/28/2022 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 9/28/2022 | Approved | HAMIK HARTOUNIAN |
| Insulation | 9/28/2022 | Approved | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 9/28/2022 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 10/13/2022 | Approved | CHARLES BOGHOSKHAN |
| Final | 6/12/2024 | Corrections Issued | THOMAS LOGRASSO |
| Green Building Final | 6/12/2024 | Approved | THOMAS LOGRASSO |
| MERV13>=Final | 6/12/2024 | Approved | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 6/12/2024 | SGSOV Approved | THOMAS LOGRASSO |
| Smoke Detectors | 6/12/2024 | Approved | THOMAS LOGRASSO |
| Final | 9/11/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 11/27/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 12/31/2024 | OK to Issue CofO | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 12/31/2024 | Approved | THOMAS LOGRASSO |