21803 W CHATSWORTH ST 91311

Certificate Information: 21803 W CHATSWORTH ST 91311

Application / Permit
21010-20000-03358
Plan Check / Job No.
B21VN08756
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 30'x40' ONE-STORY DET. ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d); ALL WORK PER WFPP
Permit Issued
Issued on 12/2/2022
Issuing Office
Valley
Current Status
CofO Issued on 5/19/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/7/2021 APPLICANT
Assigned to Plan Check Engineer 8/12/2021 SEAN SHAHMIRI
Corrections Issued 8/15/2021 SEAN SHAHMIRI
Quality Review Completed 8/25/2021 OMID HEDAYAT
Plan Check Approved 11/21/2022 SEAN SHAHMIRI
Issued 12/2/2022 APPLICANT
CofO in Progress 3/9/2025 JEFFREY PARD
Permit Finaled 5/19/2025 JOHN JANSON
CofO Issued 5/19/2025 JOHN JANSON
Permit Finaled 5/19/2025 JOHN JANSON

Permit Application Clearance Information

Hydrant and Access approval Cleared 11/4/2021 MATTHEW CRAIG
Grading Pre-Inspection Cleared 12/9/2021 ALEXANDER ANDREWS
Address approval Cleared 12/22/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 1/4/2022 CARLOS AGUILERA
Sewer availability Cleared 1/24/2022 CARLOS AGUILERA
Low Impact Development Cleared 7/19/2022 CHRIS VONG
Roof/Waste drainage to street Cleared 7/25/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/18/2024 Approved JEFFREY PARD
Footing/Foundation/Slab 1/23/2024 Not Ready for Inspection JEFFREY PARD
PLUMBING-Rough 1/23/2024 Partial Approval JEFFREY PARD
Footing/Foundation/Slab 1/25/2024 Approved JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 1/31/2024 Approved JEFFREY PARD
BUILDING-Rough-Frame 2/13/2024 Partial Approval JEFFREY PARD
ELECTRICAL-Rough 2/13/2024 Approved JEFFREY PARD
Green Building Rough 2/13/2024 Not Ready for Inspection JEFFREY PARD
HVAC-Rough 2/13/2024 Approved JEFFREY PARD
PLUMBING-Rough 2/13/2024 Approved JEFFREY PARD
BUILDING-Rough-Frame 2/14/2024 Not Ready for Inspection JEFFREY PARD
Gas Test 2/14/2024 Not Ready for Inspection JEFFREY PARD
Green Building Rough 2/14/2024 Not Ready for Inspection JEFFREY PARD
Insulation 2/14/2024 Not Ready for Inspection JEFFREY PARD
Interior/Exterior Lathing 2/14/2024 Not Ready for Inspection JEFFREY PARD
Interior/Exterior Lathing 2/20/2024 Approved JEFFREY PARD
Shower Pan 3/7/2024 Approved HENRY KIM
BUILDING-Rough-Frame 3/18/2024 Approved STEVEN BACK
Green Building Rough 3/18/2024 Approved STEVEN BACK
Insulation 3/19/2024 Approved HENRY KIM
Verify Sprinkler Sign Off 3/19/2024 Approved HENRY KIM
Drywall Nailing 3/27/2024 Approved STEVEN BACK
Sewer 3/27/2024 Approved STEVEN BACK
Underground Mechanical 3/27/2024 Approved STEVEN BACK
ELECTRICAL-Rough 7/23/2024 Partial Approval JEFFREY PARD
Underground Mechanical 9/11/2024 Approved SCOTT SOBEL
ELECTRICAL-Rough 10/22/2024 Corrections Issued JEFFREY PARD
Final 2/6/2025 Corrections Issued STEVEN BACK
Green Building Final 2/6/2025 Not Ready for Inspection STEVEN BACK
SGSOV-Seismic Gas S/O Valve 2/6/2025 SGSOV Not Ready STEVEN BACK
Smoke Detectors 2/6/2025 Approved STEVEN BACK
Final 2/12/2025 Not Ready for Inspection JEFFREY PARD
Green Building Final 2/12/2025 Not Ready for Inspection JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 2/12/2025 SGSOV Not Ready JEFFREY PARD
Final 2/20/2025 Not Ready for Inspection JEFFREY PARD
Green Building Final 2/20/2025 Not Ready for Inspection JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 2/20/2025 SGSOV Not Ready JEFFREY PARD
Service/Power Release 2/20/2025 Approved JEFFREY PARD
Final 3/7/2025 OK to Issue CofO JEFFREY PARD
Green Building Final 3/7/2025 Approved JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 3/7/2025 SGSOV Approved JEFFREY PARD