8711 N CRANFORD AVE 91352
Certificate Information: 8711 N CRANFORD AVE 91352
- Application / Permit
- 21010-20000-03357
- Plan Check / Job No.
- B21VN08755
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 1-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)(d) & WFPP
- Permit Issued
- Issued on 4/13/2022
- Issuing Office
- Current Status
- CofO Issued on 8/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/12/2021 | NILOOFAR MEHRAIN |
| Corrections Issued | 8/17/2021 | NILOOFAR MEHRAIN |
| Quality Review Completed | 8/19/2021 | STEVEN KIM |
| Building Plans Picked Up | 8/20/2021 | APPLICANT |
| Applicant returned to address corrections | 2/25/2022 | NILOOFAR MEHRAIN |
| Plan Check Approved | 3/21/2022 | NILOOFAR MEHRAIN |
| Issued | 4/13/2022 | APPLICANT |
| CofO in Progress | 8/12/2024 | MATTHEW NELSON |
| CofO Issued | 8/16/2024 | DANIEL ORRANTE |
| Permit Finaled | 8/16/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 11/12/2021 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/10/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 1/10/2022 | JOSE DUARTE-DIAZ |
| Hydrant and Access approval | Cleared | 1/16/2022 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 2/3/2022 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 2/3/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/10/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Excavation/Setback/Form/Re-Bar | 5/13/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 5/13/2022 | Approved | CHRISTOPHER DELLEFIELD |
| METHANE-Barrier | 5/13/2022 | Approved | CHRISTOPHER DELLEFIELD |
| METHANE-Subgrade | 5/13/2022 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 6/7/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 6/7/2022 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 6/7/2022 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 6/7/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Sewer | 6/7/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Underground Mechanical | 6/7/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2022 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 6/21/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 6/21/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 6/21/2022 | Approved | CHRISTOPHER DELLEFIELD |
| METHANE-Rough | 6/21/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Verify Sprinkler Sign Off | 6/21/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 6/27/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 6/27/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 8/19/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Shower Pan | 8/19/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Shower Pan | 8/25/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 8/9/2024 | OK to Issue CofO | MATTHEW NELSON |
| Green Building Final | 8/9/2024 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 8/9/2024 | SGSOV Approved | MATTHEW NELSON |
| Service/Power Release | 8/9/2024 | Approved | MATTHEW NELSON |
| Smoke Detectors | 8/9/2024 | Approved | MATTHEW NELSON |