17165 W LUDLOW ST 91344
Certificate Information: 17165 W LUDLOW ST 91344
- Application / Permit
- 21010-20000-03356
- Plan Check / Job No.
- B21VN08754
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 1-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)(d) & WFPP
- Permit Issued
- Issued on 5/10/2022
- Issuing Office
- Current Status
- CofO Issued on 9/30/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/12/2021 | NILOOFAR MEHRAIN |
| Corrections Issued | 8/17/2021 | NILOOFAR MEHRAIN |
| Quality Review Completed | 8/19/2021 | STEVEN KIM |
| Building Plans Picked Up | 8/23/2021 | APPLICANT |
| Applicant returned to address corrections | 3/2/2022 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 3/25/2022 | NILOOFAR MEHRAIN |
| Plan Check Approved | 5/2/2022 | NILOOFAR MEHRAIN |
| Issued | 5/10/2022 | APPLICANT |
| CofO in Progress | 9/16/2022 | DAVID SCANTLIN |
| Permit Finaled | 9/30/2022 | JOHN JANSON |
| CofO Issued | 9/30/2022 | JOHN JANSON |
| Permit Finaled | 9/30/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 8/27/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 9/8/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 9/8/2021 | DAGOVERTO GUERRERO |
| Construction near power lines | Cleared | 10/8/2021 | RIDWAN HARDY |
| Construction within easement | Cleared | 10/8/2021 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 1/5/2022 | GILBERT URREA |
| Low Impact Development | Cleared | 1/28/2022 | CHRIS PARK |
| Roof/Waste drainage to street | Cleared | 2/9/2022 | AMIR KASHFI |
| ZI | Cleared | 2/11/2022 | DANIEL CORONADO |
Contact Information
| No Data Available. |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 5/13/2022 | Approved | DAVID SCANTLIN |
| Footing/Foundation/Slab | 5/16/2022 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 6/14/2022 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Rough | 6/14/2022 | Approved | DAVID SCANTLIN |
| Green Building Rough | 6/14/2022 | Not Ready for Inspection | DAVID SCANTLIN |
| HVAC-Rough | 6/14/2022 | Approved | DAVID SCANTLIN |
| PLUMBING-Rough | 6/14/2022 | Approved | DAVID SCANTLIN |
| Sewer | 6/14/2022 | Not Ready for Inspection | DAVID SCANTLIN |
| Verify Sprinkler Sign Off | 6/14/2022 | Approved | DAVID SCANTLIN |
| Wood Frame | 6/14/2022 | Approved | DAVID SCANTLIN |
| Insulation | 6/17/2022 | Corrections Issued | DAVID SCANTLIN |
| Interior/Exterior Lathing | 6/17/2022 | Partial Approval | DAVID SCANTLIN |
| Drywall Nailing | 6/22/2022 | Approved | DAVID SCANTLIN |
| Insulation | 6/22/2022 | Approved | DAVID SCANTLIN |
| Sewer | 6/22/2022 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 7/1/2022 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 7/20/2022 | Approved | DAVID SCANTLIN |
| Final | 7/20/2022 | Corrections Issued | DAVID SCANTLIN |
| Green Building Final | 7/20/2022 | Not Ready for Inspection | DAVID SCANTLIN |
| Green Building Rough | 7/20/2022 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 7/20/2022 | SGSOV Approved | DAVID SCANTLIN |
| Service/Power Release | 7/20/2022 | Not Ready for Inspection | DAVID SCANTLIN |
| Smoke Detectors | 7/20/2022 | Approved | DAVID SCANTLIN |
| Final | 9/16/2022 | OK to Issue CofO | DAVID SCANTLIN |
| Green Building Final | 9/16/2022 | Approved | DAVID SCANTLIN |
| Service/Power Release | 9/16/2022 | Approved | DAVID SCANTLIN |