6907-6909 N AGNES AVE 91605
Certificate Information: 6907-6909 N AGNES AVE 91605
- Application / Permit
- 21010-20000-03320
- Plan Check / Job No.
- B21VN08636
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) DETACHED 2-STORY TWO-ACCESSORY DWELLIING UNITS OVER 6-CAR CARPORT PER LAMC 12.22A33(c)(d)
- Permit Issued
- Issued on 1/12/2023
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 4/11/2025
- Certificate of Occupancy
- Permit Finaled More Information
Permit Application Status History
| Submitted | 7/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/5/2021 | COLIN LOREDO |
| Corrections Issued | 8/12/2021 | COLIN LOREDO |
| Quality Review Completed | 8/20/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 8/27/2021 | APPLICANT |
| Applicant returned to address corrections | 8/16/2022 | NILOOFAR MEHRAIN |
| Plan Check Approved | 1/12/2023 | NILOOFAR MEHRAIN |
| Issued | 1/12/2023 | APPLICANT |
| Refund in Progress | 3/10/2025 | SELENIA GARCIA |
| Refund Closed | 3/10/2025 | SELENIA GARCIA |
| Issued | 3/10/2025 | SELENIA GARCIA |
| CofO Issued | 4/11/2025 | JEFFREY DURAN |
| Permit Finaled | 4/11/2025 | JEFFREY DURAN |
Permit Application Clearance Information
| Address approval | Cleared | 10/7/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 10/13/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 10/13/2021 | DAGOVERTO GUERRERO |
| Hydrant and Access approval | Cleared | 1/11/2022 | KURT CORRAL |
| Construction near power lines | Cleared | 1/20/2022 | RIDWAN HARDY |
| Low Impact Development | Cleared | 7/27/2022 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 7/28/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ebrahimi,, Amirhosin; Lic. No.: C92049 | 8619 RESEDA BLVD UNIT 304B NORTHRIDGE, CA 91324 |
Inspector Information
| DEANDRE HOFFMAN, (818) 374-1182 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/11/2023 | Not Ready for Inspection | JOHN HAYES |
| Pre-Inspection | 7/17/2023 | No Access for Inspection | JOHN KITCKO |
| Pre-Inspection | 2/16/2024 | Approved | JOHN KITCKO |
| Excavation/Setback/Form/Re-Bar | 3/20/2024 | Not Ready for Inspection | JEFFREY DURAN |
| Excavation/Setback/Form/Re-Bar | 3/21/2024 | Partial Approval | JOHN KITCKO |
| Deputy Drilled-In Anchors | 4/4/2024 | Conditional Approval | JOHN KITCKO |
| Footing/Foundation/Slab | 4/16/2024 | Corrections Issued | ROBERT DAVIS |
| Excavation/Setback/Form/Re-Bar | 4/18/2024 | Approved | ROBERT DAVIS |
| Footing/Foundation/Slab | 4/18/2024 | Approved | ROBERT DAVIS |
| Structural Steel Frame | 4/18/2024 | Corrections Issued | ROBERT DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2024 | Partial Approval | JOHN KITCKO |
| Structural Steel Frame | 5/16/2024 | Partial Approval | JOHN KITCKO |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2024 | Not Ready for Inspection | ANDREW DORSO |
| Wood Frame | 8/7/2024 | Corrections Issued | ANDREW DORSO |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2024 | Partial Approval | DANNY RODRIGUEZ |
| Wood Frame | 8/12/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Wood Frame | 8/14/2024 | Not Ready for Inspection | JOHN KITCKO |
| Wood Frame | 9/4/2024 | Approved | JOHN KITCKO |
| Interior/Exterior Lathing | 9/26/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Insulation | 10/10/2024 | Approved | JOHN KITCKO |
| Interior/Exterior Lathing | 10/10/2024 | Not Ready for Inspection | JOHN KITCKO |
| Interior/Exterior Lathing | 10/16/2024 | Approved | JOHN KITCKO |
| Interior/Exterior Lathing | 10/23/2024 | Partial Approval | JOHN KITCKO |
| Drywall Nailing | 12/24/2024 | Not Ready for Inspection | JOHN KITCKO |
| Green Building Rough | 12/24/2024 | Approved | JOHN KITCKO |
| Drywall Nailing | 1/3/2025 | Approved | JOHN KITCKO |
| BUILDING-Rough-Frame | 3/6/2025 | Approved | JOHN KITCKO |
| Final | 3/6/2025 | Not Ready for Inspection | JOHN KITCKO |
| Green Building Final | 3/6/2025 | Approved | JOHN KITCKO |
| SGSOV-Seismic Gas S/O Valve | 3/6/2025 | SGSOV Approved | JOHN KITCKO |
| Service/Power Release | 3/6/2025 | Not Required | JOHN KITCKO |
| Smoke Detectors | 3/6/2025 | Approved | JOHN KITCKO |
| Verify Sprinkler Sign Off | 3/6/2025 | Approved | JOHN KITCKO |
| Final | 4/3/2025 | Partial Inspection | JOHN KITCKO |