3770 1/2 S WILTON PL 90018

Certificate Information: 3770 1/2 S WILTON PL 90018

Application / Permit
21010-20000-03316
Plan Check / Job No.
B21VN08613
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 19.18' x 32' DETACHED ACCESSORY DWELLING UNIT, PER LAMC 12.22 A.33(c) AND (d).
Permit Issued
Issued on 9/20/2022
Issuing Office
Valley
Current Status
Issued on 9/20/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/2/2021 APPLICANT
Assigned to Plan Check Engineer 7/7/2021 LUIS RINCON
Corrections Issued 7/8/2021 LUIS RINCON
Applicant returned to address corrections 1/14/2022 LUKE GONZALES
Building Plans Picked Up 1/27/2022 APPLICANT
Applicant returned to address corrections 7/22/2022 LUIS RINCON
Plan Check Approved 9/14/2022 LUIS RINCON
Issued 9/20/2022 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/2/2021 THOMAS LANG
Sewer availability Cleared 8/2/2021 THOMAS LANG
Hydrant and Access approval Cleared 9/11/2021 JOHN CONNEALLY
Low Impact Development Cleared 11/10/2021 ANDRES COVARRUBIAS
Address approval Cleared 11/16/2021 JEANETTE VONG
Roof/Waste drainage to street Cleared 11/16/2021 JEANETTE VONG
Construction near power lines Cleared 3/24/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 11/4/2022 Not Ready for Inspection SABAS ALONSO
Underground Mechanical 11/4/2022 Partial Approval SABAS ALONSO
Excavation/Setback/Form/Re-Bar 11/16/2022 Approved SABAS ALONSO
Footing/Foundation/Slab 11/16/2022 Approved SABAS ALONSO
BUILDING-Rough-Frame 1/13/2023 Not Ready for Inspection SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 1/13/2023 Partial Approval SABAS ALONSO
Verify Sprinkler Sign Off 1/13/2023 Approved SABAS ALONSO
BUILDING-Rough-Frame 2/27/2023 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Rough 2/27/2023 Corrections Issued SABAS ALONSO
Green Building Rough 2/27/2023 Approved SABAS ALONSO
PLUMBING-Rough 2/27/2023 Approved SABAS ALONSO
Underground Mechanical 2/27/2023 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Rough 3/13/2023 Not Ready for Inspection SABAS ALONSO
HVAC-Rough 3/13/2023 Not Ready for Inspection SABAS ALONSO
Interior/Exterior Lathing 3/13/2023 Partial Approval SABAS ALONSO
PLUMBING-Rough 3/13/2023 Approved SABAS ALONSO
ELECTRICAL-Rough 5/5/2023 Corrections Issued ALEJANDRO DE ARTOLA
Sewer 5/5/2023 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 5/5/2023 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 5/9/2023 Approved LILIANA PORTILLO
ELECTRICAL-Rough 5/9/2023 Approved LILIANA PORTILLO
HVAC-Rough 5/9/2023 Approved LILIANA PORTILLO
Sewer 5/9/2023 Approved LILIANA PORTILLO
Insulation 10/4/2023 Corrections Issued SABAS ALONSO
Insulation 10/12/2023 Approved SABAS ALONSO
Drywall Nailing 10/17/2023 Not Ready for Inspection ANTHONY EGSON
Drywall Nailing 10/20/2023 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 10/20/2023 Approved JOSEPH MCGARRY
HVAC-Rough 11/30/2023 Approved SABAS ALONSO
PLUMBING-Final 11/30/2023 Approved SABAS ALONSO
Underground Mechanical 11/30/2023 Approved SABAS ALONSO
Final 1/4/2024 Corrections Issued SABAS ALONSO
Green Building Final 1/4/2024 Not Ready for Inspection SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 1/4/2024 SGSOV Not Ready SABAS ALONSO
Service/Power Release 1/4/2024 Not Ready for Inspection SABAS ALONSO
Smoke Detectors 1/4/2024 Approved SABAS ALONSO