20805 W BURBANK BLVD 91367
Certificate Information: 20805 W BURBANK BLVD 91367
- Application / Permit
- 21010-20000-03283
- Plan Check / Job No.
- B21VN08526
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 22'6" X 22'6" DETACHED 2-STORY ACCESSORY DWELLING UNIT AS PER LAMC 12.22.A.33 (C) AND (D), ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 4/7/2022
- Issuing Office
- Current Status
- CofO Issued on 7/29/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/5/2021 | RARES BODEA |
| Corrections Issued | 8/11/2021 | RARES BODEA |
| Quality Review Completed | 8/13/2021 | STEVEN KIM |
| Applicant returned to address corrections | 3/18/2022 | RARES BODEA |
| Plan Check Approved | 4/6/2022 | RARES BODEA |
| Issued | 4/7/2022 | APPLICANT |
| CofO in Progress | 7/28/2022 | STEVEN BACK |
| Permit Finaled | 7/29/2022 | JOHN JANSON |
| CofO Issued | 7/29/2022 | JOHN JANSON |
| Permit Finaled | 7/29/2022 | JOHN JANSON |
| Building Plans Picked Up | 9/21/2023 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 9/8/2021 | TIMOTHY POWELL |
| Hydrant and Access approval | Cleared | 9/10/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 11/2/2021 | TA ANH |
| Eng Process Fee Ord 176,300 | Cleared | 11/3/2021 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 11/3/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 11/3/2021 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 3/9/2022 | NADER ISKANDER |
| Address approval | Cleared | 4/1/2022 | CARLOS AGUILERA |
| GPI Written Notices | Cleared | 4/6/2022 | RARES BODEA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Basma,, Ali J; Lic. No.: C53080 | 21757 DEVONSHIRE ST. SUITE 3 CANOGA PARK, CA 91311 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 4/12/2022 | Approved | DAVID SCANTLIN |
| Excavation/Setback/Form/Re-Bar | 4/15/2022 | Approved | JEFFREY PARD |
| Floor/Roof Diaphrgm/Shear Wall | 4/25/2022 | Partial Approval | STEVEN BACK |
| Special/Order Compliance | 4/25/2022 | Corrections Issued | STEVEN BACK |
| BUILDING-Rough-Frame | 5/18/2022 | Corrections Issued | STEVEN BACK |
| ELECTRICAL-Rough | 5/18/2022 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 5/18/2022 | Corrections Issued | STEVEN BACK |
| HVAC-Rough | 5/18/2022 | Approved | STEVEN BACK |
| PLUMBING-Rough | 5/18/2022 | Corrections Issued | STEVEN BACK |
| Shower Pan | 5/18/2022 | Approved | STEVEN BACK |
| Deputy Wood Construction | 5/19/2022 | Conditional Approval | STEVEN BACK |
| Interior/Exterior Lathing | 5/23/2022 | Partial Approval | STEVEN BACK |
| BUILDING-Rough-Frame | 6/10/2022 | Approved | STEVEN BACK |
| Green Building Rough | 6/10/2022 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 6/10/2022 | Approved | STEVEN BACK |
| PLUMBING-Rough | 6/10/2022 | Approved | STEVEN BACK |
| Drywall Nailing | 6/15/2022 | Approved | STEVEN BACK |
| Insulation | 6/15/2022 | Approved | STEVEN BACK |
| Final | 7/22/2022 | Corrections Issued | STEVEN BACK |
| Footing/Foundation/Slab | 7/22/2022 | Approved | STEVEN BACK |
| Green Building Final | 7/22/2022 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 7/22/2022 | SGSOV Not Ready | STEVEN BACK |
| Service/Power Release | 7/22/2022 | Not Ready for Inspection | STEVEN BACK |
| Smoke Detectors | 7/22/2022 | Approved | STEVEN BACK |
| Final | 7/28/2022 | OK to Issue CofO | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 7/28/2022 | SGSOV Approved | STEVEN BACK |
| Service/Power Release | 7/28/2022 | Approved | STEVEN BACK |