20805 W BURBANK BLVD 91367

Certificate Information: 20805 W BURBANK BLVD 91367

Application / Permit
21010-20000-03283
Plan Check / Job No.
B21VN08526
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 22'6" X 22'6" DETACHED 2-STORY ACCESSORY DWELLING UNIT AS PER LAMC 12.22.A.33 (C) AND (D), ALL WORK PER ENGINEERING
Permit Issued
Issued on 4/7/2022
Issuing Office
Current Status
CofO Issued on 7/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/1/2021 APPLICANT
Assigned to Plan Check Engineer 8/5/2021 RARES BODEA
Corrections Issued 8/11/2021 RARES BODEA
Quality Review Completed 8/13/2021 STEVEN KIM
Applicant returned to address corrections 3/18/2022 RARES BODEA
Plan Check Approved 4/6/2022 RARES BODEA
Issued 4/7/2022 APPLICANT
CofO in Progress 7/28/2022 STEVEN BACK
Permit Finaled 7/29/2022 JOHN JANSON
CofO Issued 7/29/2022 JOHN JANSON
Permit Finaled 7/29/2022 JOHN JANSON
Building Plans Picked Up 9/21/2023 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 9/8/2021 TIMOTHY POWELL
Hydrant and Access approval Cleared 9/10/2021 MATTHEW CRAIG
Low Impact Development Cleared 11/2/2021 TA ANH
Eng Process Fee Ord 176,300 Cleared 11/3/2021 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 11/3/2021 CARLOS AGUILERA
Sewer availability Cleared 11/3/2021 CARLOS AGUILERA
Construction near power lines Cleared 3/9/2022 NADER ISKANDER
Address approval Cleared 4/1/2022 CARLOS AGUILERA
GPI Written Notices Cleared 4/6/2022 RARES BODEA

Contact Information

Contractor Owner-Builder       ,
Engineer Basma,, Ali J; Lic. No.: C53080 21757 DEVONSHIRE ST.   SUITE 3    CANOGA PARK, CA 91311

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/12/2022 Approved DAVID SCANTLIN
Excavation/Setback/Form/Re-Bar 4/15/2022 Approved JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 4/25/2022 Partial Approval STEVEN BACK
Special/Order Compliance 4/25/2022 Corrections Issued STEVEN BACK
BUILDING-Rough-Frame 5/18/2022 Corrections Issued STEVEN BACK
ELECTRICAL-Rough 5/18/2022 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 5/18/2022 Corrections Issued STEVEN BACK
HVAC-Rough 5/18/2022 Approved STEVEN BACK
PLUMBING-Rough 5/18/2022 Corrections Issued STEVEN BACK
Shower Pan 5/18/2022 Approved STEVEN BACK
Deputy Wood Construction 5/19/2022 Conditional Approval STEVEN BACK
Interior/Exterior Lathing 5/23/2022 Partial Approval STEVEN BACK
BUILDING-Rough-Frame 6/10/2022 Approved STEVEN BACK
Green Building Rough 6/10/2022 Approved STEVEN BACK
Interior/Exterior Lathing 6/10/2022 Approved STEVEN BACK
PLUMBING-Rough 6/10/2022 Approved STEVEN BACK
Drywall Nailing 6/15/2022 Approved STEVEN BACK
Insulation 6/15/2022 Approved STEVEN BACK
Final 7/22/2022 Corrections Issued STEVEN BACK
Footing/Foundation/Slab 7/22/2022 Approved STEVEN BACK
Green Building Final 7/22/2022 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 7/22/2022 SGSOV Not Ready STEVEN BACK
Service/Power Release 7/22/2022 Not Ready for Inspection STEVEN BACK
Smoke Detectors 7/22/2022 Approved STEVEN BACK
Final 7/28/2022 OK to Issue CofO STEVEN BACK
SGSOV-Seismic Gas S/O Valve 7/28/2022 SGSOV Approved STEVEN BACK
Service/Power Release 7/28/2022 Approved STEVEN BACK