10914 S MAIN ST 1-20 90061

Certificate Information: 10914 S MAIN ST 1-20 90061

Application / Permit
21010-20000-03282
Plan Check / Job No.
B21VN08524
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 32' X 130' THREE STORY 20 UNITS APARTMENT FULLY SPRINKLERED NFPA-13 (TYPE V-A CONSTRUCTION ) ( TOC, TIER 1 ( INCREASE TO TIER 2 - 100% AFFORDABLE HOUSING LOW INCOME UNITS) [PER ADM-2021-2810-TOC], ALL WORK PER ENGINEERING
Permit Issued
Issued on 5/6/2024
Issuing Office
West Los Angeles
Current Status
Issued on 5/6/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/1/2021 APPLICANT
Disabled Access Plans Picked Up 7/13/2021 APPLICANT
Green Plans Picked Up 7/20/2021 APPLICANT
Assigned to Plan Check Engineer 8/5/2021 RARES BODEA
Corrections Issued 8/17/2021 RARES BODEA
Quality Review Completed 8/19/2021 STEVEN KIM
Building Plans Picked Up 8/20/2021 APPLICANT
Plan Check Approved 7/17/2023 RARES BODEA
Issued 5/6/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 10/1/2021 CECILIO NAVARRO
Community Plan Implem. Overlay Cleared 10/1/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 10/4/2021 CECILIO NAVARRO
Highway dedication Cleared 10/19/2021 CHRISTOPHER ROCHA
Hydrant and Access approval Cleared 11/24/2021 MATTHEW CRAIG
Fire Marshall Fire Life Safety Cleared 1/5/2022 RONILO MULAWIN
DCP conditions approval Cleared 3/24/2022 LOUIE MILLER
Density Bonus 12.22.A.31 Cleared 3/24/2022 LOUIE MILLER
Building over 3-story or 36-ft Cleared 5/9/2022 CALOSHA APPROVED
Roof/Waste drainage to street Cleared 5/23/2022 JEANIE LAM
Sewer availability Cleared 5/26/2022 JEANIE LAM
Opn space landscape/Water mgmt Cleared 8/30/2022 MIGUEL GAMBOA
DAS Clearance Cleared 9/14/2022 RARES BODEA
Low Impact Development Cleared 9/15/2022 AMMAR ELTAWIL
Frnt yard landscape/Water mgmt Cleared 9/20/2022 MIGUEL GAMBOA
Miscellaneous Cleared 9/20/2022 MIGUEL GAMBOA
Green Code Cleared 9/29/2022 MICHAEL AYERS
Community Plan Implem. Overlay Cleared 1/23/2023 ADALBERTO VERA
Community Plan Implem. Overlay Cleared 2/6/2023 MOHAMMAD HASAN
Community Plan Implem. Overlay Cleared 3/24/2023 RIDWAN HARDY
Community Plan Implem. Overlay Cleared 6/20/2023 HELEN JADALI

Contact Information

Contractor Ariel Developers Inc; Lic. No.: 1013406-B 9854 NATIONAL BLVD #426      LOS ANGELES, CA 90034
Engineer Parvini,, Mehdi; Lic. No.: C63186 1226 SOUZA DRIVE      EL DORADO HILLS, CA 95762

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/15/2024 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 5/15/2024 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 5/16/2024 Partial Approval JAMES POWERS
Deputy Wood Construction 6/20/2024 Partial Approval JAMES POWERS
Deputy Wood Construction 7/18/2024 Partial Approval JAMES POWERS
Deputy Wood Construction 8/7/2024 Partial Approval JAMES POWERS
Deputy Wood Construction 9/11/2024 Partial Approval JAMES POWERS
Deputy Wood Construction 12/3/2024 Partial Approval JAMES POWERS
Drywall Nailing 8/18/2025 Approved RAFAEL ESPINOZA
Final 8/18/2025 Corrections Issued RAFAEL ESPINOZA
Footing/Foundation/Slab 8/18/2025 Approved RAFAEL ESPINOZA
Green Building Final 8/18/2025 Not Ready for Inspection RAFAEL ESPINOZA
Green Building Rough 8/18/2025 Approved RAFAEL ESPINOZA
Reinforced Masonry Frame 8/18/2025 Not Ready for Inspection RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 8/18/2025 SGSOV Approved RAFAEL ESPINOZA
Smoke Detectors 8/18/2025 Approved RAFAEL ESPINOZA
Structural Steel Frame 8/18/2025 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 8/18/2025 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 8/18/2025 Not Ready for Inspection RAFAEL ESPINOZA
Final 12/10/2025 No Access for Inspection RAFAEL CORTES
Green Building Final 12/10/2025 Not Ready for Inspection RAFAEL CORTES
Reinforced Masonry Frame 12/10/2025 Not Ready for Inspection RAFAEL CORTES
Structural Steel Frame 12/10/2025 Not Ready for Inspection RAFAEL CORTES
Verify Sprinkler Sign Off 12/10/2025 Not Ready for Inspection RAFAEL CORTES
Wood Frame 12/10/2025 Not Ready for Inspection RAFAEL CORTES
Final 12/15/2025 Not Ready for Inspection RAFAEL CORTES
Green Building Final 12/15/2025 Not Ready for Inspection RAFAEL CORTES
Reinforced Masonry Frame 12/15/2025 Not Ready for Inspection RAFAEL CORTES
Structural Steel Frame 12/15/2025 Not Ready for Inspection RAFAEL CORTES
Verify Sprinkler Sign Off 12/15/2025 Not Ready for Inspection RAFAEL CORTES
Wood Frame 12/15/2025 Not Ready for Inspection RAFAEL CORTES
Final 3/4/2026 Partial Inspection RAFAEL ESPINOZA
Green Building Final 3/4/2026 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Masonry Frame 3/4/2026 Approved RAFAEL ESPINOZA
Structural Steel Frame 3/4/2026 Approved RAFAEL ESPINOZA
Verify Sprinkler Sign Off 3/4/2026 Approved RAFAEL ESPINOZA
Wood Frame 3/4/2026 Not Ready for Inspection RAFAEL ESPINOZA
Final 4/6/2026 Partial Inspection RAFAEL ESPINOZA
Green Building Final 4/6/2026 Approved RAFAEL ESPINOZA
Wood Frame 4/6/2026 Not Ready for Inspection RAFAEL ESPINOZA
Insulation 5/21/2026 Approved JOEY BUCHANAN