8362 N REMY AVE 91306
Certificate Information: 8362 N REMY AVE 91306
- Application / Permit
- 21010-20000-03259
- Plan Check / Job No.
- B21VN08453
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePLAN. NEW DETACHED ACCESSORY DWELLING UNIT AT REAR PER LAMC 12.22 A.33(c)-(d).
- Permit Issued
- Issued on 1/25/2022
- Issuing Office
- Current Status
- CofO Issued on 3/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/7/2021 | KEVIN MORALES |
| Corrections Issued | 7/7/2021 | KEVIN MORALES |
| Applicant returned to address corrections | 1/11/2022 | KEVIN MORALES |
| Plan Check Approved | 1/21/2022 | KEVIN MORALES |
| Issued | 1/25/2022 | APPLICANT |
| CofO in Progress | 2/26/2025 | CHRIS CHRISTENSEN |
| Permit Finaled | 3/19/2025 | JOHN JANSON |
| CofO Issued | 3/19/2025 | JOHN JANSON |
| Permit Finaled | 3/19/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 7/23/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 7/26/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 7/26/2021 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 10/7/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 1/7/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 1/19/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/10/2022 | Corrections Issued | PETER FOLLING |
| Pre-Inspection | 3/10/2022 | Not Ready for Inspection | PETER FOLLING |
| Sewer | 3/10/2022 | Not Ready for Inspection | PETER FOLLING |
| PLUMBING-Rough | 3/14/2022 | Corrections Issued | JEFFREY PARD |
| Sewer | 3/14/2022 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 3/16/2022 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 3/24/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 3/25/2022 | Partial Approval | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 4/4/2022 | Partial Approval | CHRIS CHRISTENSEN |
| Excavation/Setback/Form/Re-Bar | 4/13/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| Excavation/Setback/Form/Re-Bar | 4/18/2022 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 5/18/2022 | Partial Approval | CHRIS CHRISTENSEN |
| Deputy Wood Construction | 5/19/2022 | Conditional Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 6/7/2022 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 6/7/2022 | Approved | CHRIS CHRISTENSEN |
| HVAC-Rough | 6/21/2022 | Approved | CHRIS CHRISTENSEN |
| Wood Frame | 7/1/2022 | Partial Approval | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 10/11/2022 | Approved | KRISTEN CAUSEY |
| Insulation | 3/24/2023 | Approved | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 3/24/2023 | Approved | KRISTEN CAUSEY |
| Shower Pan | 3/24/2023 | Approved | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 4/7/2023 | Partial Inspection | KRISTEN CAUSEY |
| Drywall Nailing | 6/9/2023 | Not Ready for Inspection | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 6/14/2023 | Approved | JUSTIN HAWLEY |
| Drywall Nailing | 6/14/2023 | Approved | JUSTIN HAWLEY |
| Verify Sprinkler Sign Off | 6/14/2023 | Approved | JUSTIN HAWLEY |
| Pre-Inspection | 5/28/2024 | Approved | CHRIS CHRISTENSEN |
| Final | 1/14/2025 | Corrections Issued | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 1/14/2025 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 1/14/2025 | SGSOV Not Ready | CHRIS CHRISTENSEN |
| Service/Power Release | 1/14/2025 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Smoke Detectors | 1/14/2025 | Approved | CHRIS CHRISTENSEN |
| Final | 2/21/2025 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 2/21/2025 | SGSOV Not Ready | CHRIS CHRISTENSEN |
| Service/Power Release | 2/21/2025 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Final | 2/26/2025 | OK to Issue CofO | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 2/26/2025 | SGSOV Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 2/26/2025 | Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 3/13/2025 | Approved | CHRIS CHRISTENSEN |