23355 W VANOWEN ST 91307

Certificate Information: 23355 W VANOWEN ST 91307

Application / Permit
21010-20000-03258
Plan Check / Job No.
B21VN08452
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan. New detached 1-story ADU per ordinance 186,481.
Permit Issued
Issued on 10/19/2022
Issuing Office
Current Status
CofO in Progress on 1/17/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/1/2021 APPLICANT
Assigned to Plan Check Engineer 7/6/2021 FERNANDO FLORES
Corrections Issued 7/7/2021 HELEN NGUYEN
Plan Check Approved 8/13/2022 FERNANDO FLORES
Issued 10/19/2022 APPLICANT
CofO in Progress 5/23/2024 TROY SANDERS
No Progress 1/17/2025 HENRY KIM
CofO in Progress 1/17/2025 HENRY KIM

Permit Application Clearance Information

Address approval Cleared 9/14/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 9/20/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 9/20/2021 DAGOVERTO GUERRERO
Hydrant and Access approval Cleared 2/23/2022 JOHN CONNEALLY
Low Impact Development Cleared 8/3/2022 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 8/4/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Gaga Builders Inc; Lic. No.: 1038675-B       ,
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 8916 LONGDON AVE #C      TEMPLE CITY, CA 91780

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/29/2022 Approved TROY SANDERS
Footing/Foundation/Slab 12/12/2022 Approved TROY SANDERS
BUILDING-Rough-Frame 12/28/2022 Approved TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 12/28/2022 Partial Approval TROY SANDERS
Green Building Rough 12/28/2022 Not Ready for Inspection TROY SANDERS
Rough-Elec/Plmb/HVAC 12/28/2022 Approved TROY SANDERS
Verify Sprinkler Sign Off 12/28/2022 Approved TROY SANDERS
Drywall Nailing 1/3/2023 Approved TROY SANDERS
Green Building Rough 1/3/2023 Approved TROY SANDERS
Insulation 1/3/2023 Approved TROY SANDERS
Interior/Exterior Lathing 1/3/2023 Approved TROY SANDERS
Shower Pan 1/3/2023 Approved TROY SANDERS
Drywall Nailing 1/5/2023 Approved TROY SANDERS
Green Building Rough 1/5/2023 Approved TROY SANDERS
Insulation 1/5/2023 Approved TROY SANDERS
Final 7/24/2023 Corrections Issued TROY SANDERS
Green Building Final 7/24/2023 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 7/24/2023 SGSOV Approved TROY SANDERS
Service/Power Release 7/24/2023 Approved TROY SANDERS
Smoke Detectors 7/24/2023 Approved TROY SANDERS
Final 5/22/2024 OK to Issue CofO TROY SANDERS
Special/Order Compliance 1/8/2025 Corrections Issued TROY SANDERS