7939 N WILKINSON AVE 91605
Certificate Information: 7939 N WILKINSON AVE 91605
- Application / Permit
- 21010-20000-03219
- Plan Check / Job No.
- B21VN08297
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert 1131 sf 2nd story recreation room to ADU. NO WORK TO 1ST FLOOR.
- Permit Issued
- Issued on 12/21/2021
- Issuing Office
- Current Status
- CofO Issued on 3/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/7/2021 | JOE VO |
| Corrections Issued | 7/7/2021 | JOE VO |
| Applicant returned to address corrections | 11/3/2021 | JOE VO |
| Applicant returned to address corrections | 11/8/2021 | JOE VO |
| Applicant returned to address corrections | 12/17/2021 | JOE VO |
| Plan Check Approved | 12/20/2021 | JOE VO |
| Issued | 12/21/2021 | APPLICANT |
| CofO in Progress | 2/1/2023 | MATTHEW NELSON |
| No Progress | 2/15/2023 | DAVID MATSON |
| CofO in Progress | 2/15/2023 | DAVID MATSON |
| CofO in Progress | 2/28/2023 | DAVID MATSON |
| Permit Finaled | 3/7/2023 | MICHAEL SMITH |
| CofO Issued | 3/7/2023 | MICHAEL SMITH |
| Permit Finaled | 3/7/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 7/7/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 7/7/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 11/8/2021 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 12/17/2021 | JOHN CONNEALLY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Roberts,, Jeffrey Allan; Lic. No.: NA56881 | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/19/2022 | Approved | DEANDRE HOFFMAN |
| Drywall Nailing | 12/5/2022 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 1/31/2023 | Approved | MATTHEW NELSON |
| Final | 1/31/2023 | Conditional Approval | MATTHEW NELSON |
| Green Building Final | 1/31/2023 | Approved | MATTHEW NELSON |
| Green Building Rough | 1/31/2023 | Approved | MATTHEW NELSON |
| MERV13>=Final | 1/31/2023 | Approved | MATTHEW NELSON |
| MERV13>=Rough | 1/31/2023 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 1/31/2023 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 1/31/2023 | Approved | MATTHEW NELSON |
| Special/Order Compliance | 2/15/2023 | Corrections Issued | DAVID MATSON |