17951 W ACRE ST 91325
Certificate Information: 17951 W ACRE ST 91325
- Application / Permit
- 21010-20000-03194
- Plan Check / Job No.
- B21VN08263
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 16' X 25' ADU. PER LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 10/20/2021
- Issuing Office
- Current Status
- CofO Issued on 2/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/7/2021 | HERNAN ARREOLA |
| Corrections Issued | 7/7/2021 | HERNAN ARREOLA |
| Plan Check Approved | 7/27/2021 | HERNAN ARREOLA |
| Issued | 10/20/2021 | APPLICANT |
| CofO in Progress | 1/25/2023 | JAVIER RAMOS JR |
| CofO Issued | 2/6/2023 | MICHAEL SMITH |
| Permit Finaled | 2/6/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 7/13/2021 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 7/13/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 10/15/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 10/15/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Tran,, Duane Phat; Lic. No.: C91229 | 1106 S NEWHOPE ST SANTA ANA, CA 92704 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/30/2022 | Not Ready for Inspection | RAUL OLAGI |
| PLUMBING-Rough | 3/30/2022 | Partial Approval | JAVIER RAMOS JR |
| Sewer | 3/30/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Excavation/Setback/Form/Re-Bar | 4/14/2022 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2022 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 5/12/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 5/19/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| PLUMBING-Rough | 5/19/2022 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 5/23/2022 | Corrections Issued | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 6/7/2022 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 6/7/2022 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 6/7/2022 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 6/7/2022 | Partial Approval | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 6/7/2022 | Partial Approval | JAVIER RAMOS JR |
| Verify Sprinkler Sign Off | 6/7/2022 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 6/14/2022 | Approved | JAVIER RAMOS JR |
| Insulation | 6/14/2022 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 6/21/2022 | Approved | DEANDRE HOFFMAN |
| Sewer | 7/1/2022 | Approved | JAVIER RAMOS JR |
| Shower Pan | 7/1/2022 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 7/7/2022 | Corrections Issued | JACK KARGODORIAN |
| Interior/Exterior Lathing | 7/11/2022 | Approved | ALAN MORELOS |
| Rough-Elec/Plmb/HVAC | 8/15/2022 | Partial Inspection | JAVIER RAMOS JR |
| Underground Mechanical | 8/15/2022 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 8/18/2022 | Corrections Issued | JAVIER RAMOS JR |
| Final | 8/18/2022 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Final | 8/18/2022 | Corrections Issued | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 11/3/2022 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 11/3/2022 | Approved | JAVIER RAMOS JR |
| Final | 11/3/2022 | Corrections Issued | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 11/3/2022 | Approved | JAVIER RAMOS JR |
| Green Building Final | 11/3/2022 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 11/3/2022 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 11/3/2022 | SGSOV Not Required | JAVIER RAMOS JR |
| Service/Power Release | 11/3/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Smoke Detectors | 11/3/2022 | Approved | JAVIER RAMOS JR |
| Final | 12/8/2022 | Partial Inspection | JAVIER RAMOS JR |
| Service/Power Release | 12/8/2022 | Partial Inspection | JAVIER RAMOS JR |
| Final | 1/25/2023 | OK to Issue CofO | JAVIER RAMOS JR |
| Service/Power Release | 1/25/2023 | Approved | JAVIER RAMOS JR |