12833 W CHALON ROAD 90049
Certificate Information: 12833 W CHALON ROAD 90049
- Application / Permit
- 21010-20000-03178
- Plan Check / Job No.
- B21VN08193
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- NEW DETACHED (48'-0"x24'-0"), 3-CAR GARAGE
- Permit Issued
- Issued on 1/10/2022
- Issuing Office
- Current Status
- CofO Issued on 10/16/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/8/2021 | PETER MOSESIAN |
| Corrections Issued | 7/10/2021 | PETER MOSESIAN |
| Quality Review Completed | 7/14/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 7/20/2021 | APPLICANT |
| Plan Check Approved | 1/10/2022 | PETER MOSESIAN |
| Issued | 1/10/2022 | APPLICANT |
| CofO in Progress | 5/31/2023 | KEVIN SARGSYAN |
| CofO in Progress | 5/31/2023 | KEVIN SARGSYAN |
| Permit Finaled | 10/16/2023 | DANIEL ORRANTE |
| CofO Issued | 10/16/2023 | DANIEL ORRANTE |
| Permit Finaled | 10/16/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Private street | Cleared | 7/26/2021 | MIGUEL GAMBOA |
| ZA Case | Cleared | 7/26/2021 | MIGUEL GAMBOA |
| ZA Case | Cleared | 7/26/2021 | MIGUEL GAMBOA |
| ZA Case | Cleared | 7/26/2021 | MIGUEL GAMBOA |
| ZA Case | Cleared | 7/26/2021 | MIGUEL GAMBOA |
| ZI | Cleared | 7/26/2021 | MIGUEL GAMBOA |
| BHO/Hillside ordinance | Cleared | 7/29/2021 | NIKTA MOUSAVI |
| BHO/Hillside ordinance | Cleared | 7/29/2021 | NIKTA MOUSAVI |
| BHO/Hillside ordinance | Cleared | 7/29/2021 | NIKTA MOUSAVI |
| BHO/Hillside ordinance | Cleared | 7/29/2021 | NIKTA MOUSAVI |
| BHO/Hillside ordinance | Cleared | 8/2/2021 | NIKTA MOUSAVI |
| Eng Process Fee Ord 176,300 | Cleared | 8/2/2021 | NIKTA MOUSAVI |
| Watercourse | Cleared | 8/2/2021 | MAHELET GEBEYHU |
| Permit | Cleared | 8/7/2021 | CATHERINE ADROVER |
| Trees in Parkway | Cleared | 8/11/2021 | JOHN KIM |
| Hydrant and Access approval | Cleared | 9/3/2021 | GILBERT URREA |
| Low Impact Development | Cleared | 12/21/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 1/3/2022 | NIKTA MOUSAVI |
Contact Information
| Architect | Mccarthy,, Dion P; Lic. No.: C26044 | DESIGNARC 10524 ILONA AVE. LOS ANGELES, CA 90064 |
| Contractor | Ceci Clarke Inc; Lic. No.: 1040135-B | 444 ARNEILL ROAD CAMARILLO, CA 93010 |
| Engineer | Galbreath,, Sean Martin; Lic. No.: S5653 | 600 SOUTH LAKE AVE STE 308 PASADENA, CA 91106 |
| Landscape Architect | Eriksson,, Nord Jon; Lic. No.: LA2858 | 844 E. GREEN STREET STE 201 PASADENA, CA 91101 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/14/2022 | Corrections Issued | JUAN VALENZUELA |
| Piling/Pier/Caisson | 3/16/2022 | Partial Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 3/23/2022 | Partial Approval | JUAN VALENZUELA |
| Masonry Wall/Backfill | 4/4/2022 | Approved | MICHAEL PELHAM |
| Footing/Foundation/Slab | 4/20/2022 | Partial Approval | JUAN VALENZUELA |
| FLOOD-Proofing Certificate | 5/9/2022 | Approved | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2022 | Partial Approval | JUAN VALENZUELA |
| Green Building Rough | 5/9/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2022 | Approved | JUAN VALENZUELA |
| Green Building Rough | 5/20/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| ELECTRICAL-Rough | 5/31/2022 | Approved | JUAN VALENZUELA |
| Insulation | 5/31/2022 | Approved | JUAN VALENZUELA |
| Green Building Rough | 6/6/2022 | Approved | JUAN VALENZUELA |
| Drywall Nailing | 6/28/2022 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 9/27/2022 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 10/18/2022 | Approved | JUAN VALENZUELA |
| PLUMBING-Rough | 10/19/2022 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Final | 1/18/2023 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Final | 2/2/2023 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 3/1/2023 | Approved | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 3/1/2023 | Approved | KEVIN SARGSYAN |
| Green Building Final | 3/1/2023 | Approved | KEVIN SARGSYAN |
| Smoke Detectors | 3/1/2023 | Approved | KEVIN SARGSYAN |
| Final | 4/5/2023 | Corrections Issued | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 4/5/2023 | SGSOV Approved | KEVIN SARGSYAN |
| Service/Power Release | 4/5/2023 | Approved | KEVIN SARGSYAN |
| Final | 5/31/2023 | OK to Issue CofO | KEVIN SARGSYAN |