12004 W ROSCOE BLVD 91605
Certificate Information: 12004 W ROSCOE BLVD 91605
- Application / Permit
- 21010-20000-03172
- Plan Check / Job No.
- B21VN08185
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *ePLAN CHECK* 1. EXISTING GARAGE CONVERTED TO A.D.U. 370.49 SQ FT PER GCS 65852.2(e)(1)(A) 2. (N) THANKLESS WATER HEATER 3. (N) MINI SPLIT HVAC UNIT 4. (N) REDGARD VAPOR BARRIER
- Permit Issued
- Issued on 8/3/2021
- Issuing Office
- Current Status
- CofO Issued on 3/23/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/28/2021 | ZAW HAN |
| Corrections Issued | 6/28/2021 | ZAW HAN |
| Applicant returned to address corrections | 7/12/2021 | ZAW HAN |
| Plan Check Approved | 7/26/2021 | ZAW HAN |
| Issued | 8/3/2021 | APPLICANT |
| CofO in Progress | 3/7/2023 | MICKEY YAMASHITA |
| CofO in Progress | 3/7/2023 | MICKEY YAMASHITA |
| CofO Issued | 3/23/2023 | DAVID JAMES |
| Permit Finaled | 3/23/2023 | DAVID JAMES |
Permit Application Clearance Information
| Address approval | Cleared | 7/2/2021 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 7/2/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 7/2/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 7/13/2021 | DAGOVERTO GUERRERO |
| Clean Up Green Up | Cleared | 7/22/2021 | MINDY NGUYEN |
Contact Information
| Contractor | Prime Point Contracting Inc; Lic. No.: 812371-B | 22287 MULHOLLAND HWY #322 CALABASAS, CA 91302 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: NA76828 | , |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIO CUEVAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 8/9/2022 | Corrections Issued | MICKEY YAMASHITA |
| Gas Test | 8/9/2022 | Corrections Issued | MICKEY YAMASHITA |
| Gas Test | 8/10/2022 | Partial Approval | MICKEY YAMASHITA |
| ELECTRICAL-Rough | 8/22/2022 | Not Ready for Inspection | MICKEY YAMASHITA |
| Footing/Foundation/Slab | 8/22/2022 | Not Ready for Inspection | MICKEY YAMASHITA |
| PLUMBING-Rough | 8/22/2022 | Not Ready for Inspection | MICKEY YAMASHITA |
| Footing/Foundation/Slab | 8/29/2022 | Corrections Issued | MICKEY YAMASHITA |
| PLUMBING-Rough | 8/29/2022 | Not Ready for Inspection | MICKEY YAMASHITA |
| Footing/Foundation/Slab | 9/7/2022 | Conditional Approval | MICKEY YAMASHITA |
| PLUMBING-Rough | 9/7/2022 | Not Ready for Inspection | MICKEY YAMASHITA |
| BUILDING-Rough-Frame | 9/9/2022 | Corrections Issued | THOMAS WOODS |
| ELECTRICAL-Rough | 9/9/2022 | Not Ready for Inspection | THOMAS WOODS |
| Footing/Foundation/Slab | 9/9/2022 | Not Ready for Inspection | THOMAS WOODS |
| Green Building Rough | 9/9/2022 | Not Ready for Inspection | THOMAS WOODS |
| PLUMBING-Rough | 9/9/2022 | Not Ready for Inspection | THOMAS WOODS |
| BUILDING-Rough-Frame | 9/12/2022 | Not Ready for Inspection | MICKEY YAMASHITA |
| ELECTRICAL-Rough | 9/12/2022 | Corrections Issued | MICKEY YAMASHITA |
| Footing/Foundation/Slab | 9/12/2022 | Corrections Issued | MICKEY YAMASHITA |
| Green Building Rough | 9/12/2022 | Corrections Issued | MICKEY YAMASHITA |
| HVAC-Rough | 9/12/2022 | Not Ready for Inspection | MICKEY YAMASHITA |
| PLUMBING-Rough | 9/12/2022 | Corrections Issued | MICKEY YAMASHITA |
| Sewer | 9/12/2022 | Corrections Issued | MICKEY YAMASHITA |
| ELECTRICAL-Rough | 9/29/2022 | Corrections Issued | MICKEY YAMASHITA |
| PLUMBING-Rough | 9/29/2022 | Corrections Issued | MICKEY YAMASHITA |
| BUILDING-Rough-Frame | 10/4/2022 | Corrections Issued | MICKEY YAMASHITA |
| ELECTRICAL-Rough | 10/4/2022 | Corrections Issued | MICKEY YAMASHITA |
| Gas Test | 10/4/2022 | Corrections Issued | MICKEY YAMASHITA |
| Green Building Rough | 10/4/2022 | Corrections Issued | MICKEY YAMASHITA |
| PLUMBING-Rough | 10/4/2022 | Approved | MICKEY YAMASHITA |
| BUILDING-Rough-Frame | 10/6/2022 | Corrections Issued | MICKEY YAMASHITA |
| ELECTRICAL-Rough | 10/6/2022 | Approved | MICKEY YAMASHITA |
| Gas Test | 10/6/2022 | Corrections Issued | MICKEY YAMASHITA |
| BUILDING-Rough-Frame | 10/12/2022 | Conditional Approval | MICKEY YAMASHITA |
| Green Building Rough | 10/12/2022 | Approved | MICKEY YAMASHITA |
| BUILDING-Rough-Frame | 10/17/2022 | Not Ready for Inspection | MICKEY YAMASHITA |
| Gas Test | 10/17/2022 | Not Ready for Inspection | MICKEY YAMASHITA |
| BUILDING-Rough-Frame | 10/19/2022 | Approved | MICKEY YAMASHITA |
| Floor/Roof Diaphrgm/Shear Wall | 10/19/2022 | Approved | MICKEY YAMASHITA |
| Gas Test | 10/19/2022 | Partial Approval | MICKEY YAMASHITA |
| HVAC-Rough | 10/19/2022 | Not Ready for Inspection | MICKEY YAMASHITA |
| Drywall Nailing | 10/25/2022 | Approved | MICKEY YAMASHITA |
| Gas Test | 10/25/2022 | Approved | MICKEY YAMASHITA |
| HVAC-Rough | 10/25/2022 | Approved | MICKEY YAMASHITA |
| Insulation | 10/25/2022 | Approved | MICKEY YAMASHITA |
| Sewer | 10/25/2022 | Approved | MICKEY YAMASHITA |
| Interior/Exterior Lathing | 10/27/2022 | Approved | THOMAS WOODS |
| Final | 1/18/2023 | No Access for Inspection | MICKEY YAMASHITA |
| Green Building Final | 1/18/2023 | No Access for Inspection | MICKEY YAMASHITA |
| SGSOV-Seismic Gas S/O Valve | 1/18/2023 | SGSOV Not Ready | MICKEY YAMASHITA |
| Smoke Detectors | 1/18/2023 | No Access for Inspection | MICKEY YAMASHITA |
| BUILDING-Rough-Frame | 1/19/2023 | Corrections Issued | MICKEY YAMASHITA |
| Final | 1/19/2023 | Not Ready for Inspection | MICKEY YAMASHITA |
| Green Building Final | 1/19/2023 | Corrections Issued | MICKEY YAMASHITA |
| PLUMBING-Final | 1/19/2023 | Corrections Issued | MICKEY YAMASHITA |
| SGSOV-Seismic Gas S/O Valve | 1/19/2023 | SGSOV Not Ready | MICKEY YAMASHITA |
| Smoke Detectors | 1/19/2023 | Corrections Issued | MICKEY YAMASHITA |
| BUILDING-Rough-Frame | 2/1/2023 | Corrections Issued | MICKEY YAMASHITA |
| Final | 2/1/2023 | Corrections Issued | MICKEY YAMASHITA |
| Green Building Final | 2/1/2023 | Corrections Issued | MICKEY YAMASHITA |
| HVAC-Final | 2/1/2023 | Corrections Issued | MICKEY YAMASHITA |
| SGSOV-Seismic Gas S/O Valve | 2/1/2023 | SGSOV Not Ready | MICKEY YAMASHITA |
| Smoke Detectors | 2/1/2023 | Corrections Issued | MICKEY YAMASHITA |
| BUILDING-Rough-Frame | 2/9/2023 | No Access for Inspection | MICKEY YAMASHITA |
| Final | 2/9/2023 | No Access for Inspection | MICKEY YAMASHITA |
| Green Building Final | 2/9/2023 | No Access for Inspection | MICKEY YAMASHITA |
| SGSOV-Seismic Gas S/O Valve | 2/9/2023 | SGSOV Not Ready | MICKEY YAMASHITA |
| Smoke Detectors | 2/9/2023 | No Access for Inspection | MICKEY YAMASHITA |
| BUILDING-Rough-Frame | 2/14/2023 | Approved | MICKEY YAMASHITA |
| Final | 2/14/2023 | Corrections Issued | MICKEY YAMASHITA |
| Green Building Final | 2/14/2023 | Corrections Issued | MICKEY YAMASHITA |
| SGSOV-Seismic Gas S/O Valve | 2/14/2023 | SGSOV Approved | MICKEY YAMASHITA |
| Smoke Detectors | 2/14/2023 | Approved | MICKEY YAMASHITA |
| Final | 3/2/2023 | Not Ready for Inspection | MICKEY YAMASHITA |
| Green Building Final | 3/2/2023 | Not Ready for Inspection | MICKEY YAMASHITA |
| Final | 3/7/2023 | OK to Issue CofO | MICKEY YAMASHITA |