10759 N REDMONT AVE 91042
Certificate Information: 10759 N REDMONT AVE 91042
- Application / Permit
- 21010-20000-03158
- Plan Check / Job No.
- B21VN08118
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Patio Cover
- Work Description
- NEW 17'-4" x 17'-1" DETACHED PATIO PER ENGINEER
- Permit Issued
- Issued on 9/15/2021
- Issuing Office
- Current Status
- CofO Issued on 8/17/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/30/2021 | ANGELICA DAVE |
| Corrections Issued | 6/30/2021 | ANGELICA DAVE |
| Applicant returned to address corrections | 9/1/2021 | ANGELICA DAVE |
| Issued | 9/15/2021 | APPLICANT |
| Building Plans Picked Up | 9/22/2021 | APPLICANT |
| CofO in Progress | 8/1/2022 | MATTHEW NELSON |
| Permit Finaled | 8/17/2022 | MICHAEL SMITH |
| CofO Issued | 8/17/2022 | MICHAEL SMITH |
| Permit Finaled | 8/17/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/12/2021 | CARLOS AGUILERA |
| Watercourse | Cleared | 7/12/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 7/13/2021 | CARLOS AGUILERA |
| Grading Pre-Inspection | Cleared | 8/27/2021 | PATRICK MISCHLICH |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/20/2022 | Corrections Issued | MATTHEW NELSON |
| Footing/Foundation/Slab | 1/25/2022 | Approved | MATTHEW NELSON |
| Wood Frame | 2/10/2022 | Corrections Issued | MATTHEW NELSON |
| BUILDING-Rough-Frame | 3/17/2022 | Approved | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 3/17/2022 | Approved | MATTHEW NELSON |
| Wood Frame | 3/17/2022 | Approved | MATTHEW NELSON |
| Final | 4/4/2022 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 4/4/2022 | SGSOV Not Ready | MATTHEW NELSON |
| Service/Power Release | 4/4/2022 | Not Ready for Inspection | MATTHEW NELSON |
| Smoke Detectors | 4/4/2022 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 5/11/2022 | Approved | MATTHEW NELSON |
| Final | 5/11/2022 | Partial Approval | MATTHEW NELSON |
| HVAC-Final | 5/11/2022 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 5/11/2022 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 5/11/2022 | SGSOV Approved | MATTHEW NELSON |
| Service/Power Release | 5/11/2022 | Not Ready for Inspection | MATTHEW NELSON |
| Final | 8/1/2022 | OK to Issue CofO | MATTHEW NELSON |
| Service/Power Release | 8/1/2022 | Approved | MATTHEW NELSON |