15602 W MORRISON ST 91403
Certificate Information: 15602 W MORRISON ST 91403
- Application / Permit
- 21010-20000-03143
- Plan Check / Job No.
- B21VN08094
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY (79'-0"x38'-0"),3829 SQFT SINGLE FAMILY DWELLING W/ ATTACHED 2 CAR GARAGE (22'-0"x20'-0"), 413 SQFT WITH NFPA-13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 4/19/2022
- Issuing Office
- Current Status
- CofO Issued on 4/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/26/2021 | PETER MOSESIAN |
| Corrections Issued | 8/29/2021 | PETER MOSESIAN |
| Quality Review Completed | 9/2/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 9/3/2021 | APPLICANT |
| Plan Check Approved | 4/12/2022 | PETER MOSESIAN |
| Issued | 4/19/2022 | APPLICANT |
| CofO in Progress | 2/21/2024 | VINCENT HANLEY |
| CofO Issued | 4/16/2024 | JOHN JANSON |
| Permit Finaled | 4/16/2024 | JOHN JANSON |
Permit Application Clearance Information
| Permit | Cleared | 10/13/2021 | GABRIEL ROBLES |
| Low Impact Development | Cleared | 10/27/2021 | JONATAN VELASQUEZ |
| Sewer availability | Cleared | 11/23/2021 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 12/20/2021 | MATTHEW CRAIG |
| Roof/Waste drainage to street | Cleared | 12/22/2021 | AMIR KASHFI |
| Trees in Parkway | Cleared | 12/28/2021 | ADALBERTO VERA |
| Eng Process Fee Ord 176,300 | Cleared | 1/3/2022 | ABDULLAH SADOZAI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/12/2022 | Not Ready for Inspection | VINCENT HANLEY |
| PLUMBING-Rough | 5/16/2022 | Partial Approval | DAVID SANDOVAL |
| Deputy Reinf. Concrete | 5/26/2022 | Conditional Approval | MORRIS JACKSON |
| Footing/Foundation/Slab | 5/26/2022 | Approved | PETER FOLLING |
| Deputy Reinf. Concrete | 5/27/2022 | Conditional Approval | MORRIS JACKSON |
| BUILDING-Rough-Frame | 6/24/2022 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2022 | Partial Approval | VINCENT HANLEY |
| Green Building Rough | 6/24/2022 | Not Ready for Inspection | VINCENT HANLEY |
| MERV13>=Rough | 6/24/2022 | Not Ready for Inspection | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 6/24/2022 | Not Ready for Inspection | VINCENT HANLEY |
| ELECTRICAL-Rough | 10/26/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 10/26/2022 | Corrections Issued | DAVID SANDOVAL |
| HVAC-Rough | 10/26/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| PLUMBING-Rough | 10/26/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Deputy Wood Construction | 10/27/2022 | Conditional Approval | JUSTIN HAWLEY |
| Deputy Drilled-In Anchors | 11/15/2022 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 11/17/2022 | Corrections Issued | VINCENT HANLEY |
| ELECTRICAL-Rough | 11/17/2022 | Corrections Issued | VINCENT HANLEY |
| Green Building Rough | 11/17/2022 | Corrections Issued | VINCENT HANLEY |
| HVAC-Rough | 11/17/2022 | Corrections Issued | VINCENT HANLEY |
| MERV13>=Rough | 11/17/2022 | Not Ready for Inspection | VINCENT HANLEY |
| PLUMBING-Rough | 11/17/2022 | Corrections Issued | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 11/17/2022 | Corrections Issued | VINCENT HANLEY |
| BUILDING-Rough-Frame | 12/12/2022 | Corrections Issued | VINCENT HANLEY |
| ELECTRICAL-Rough | 12/12/2022 | Not Ready for Inspection | VINCENT HANLEY |
| Green Building Rough | 12/12/2022 | Not Ready for Inspection | VINCENT HANLEY |
| HVAC-Rough | 12/12/2022 | Not Ready for Inspection | VINCENT HANLEY |
| MERV13>=Rough | 12/12/2022 | Not Ready for Inspection | VINCENT HANLEY |
| PLUMBING-Rough | 12/12/2022 | Not Ready for Inspection | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 12/12/2022 | Corrections Issued | VINCENT HANLEY |
| ELECTRICAL-Rough | 12/28/2022 | Not Ready for Inspection | VINCENT HANLEY |
| HVAC-Rough | 12/28/2022 | Corrections Issued | VINCENT HANLEY |
| Interior/Exterior Lathing | 12/28/2022 | Not Ready for Inspection | VINCENT HANLEY |
| PLUMBING-Rough | 12/28/2022 | Not Ready for Inspection | VINCENT HANLEY |
| Interior/Exterior Lathing | 1/3/2023 | Corrections Issued | VINCENT HANLEY |
| BUILDING-Rough-Frame | 1/10/2023 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 1/10/2023 | Approved | VINCENT HANLEY |
| Green Building Rough | 1/10/2023 | Approved | VINCENT HANLEY |
| HVAC-Rough | 1/10/2023 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 1/10/2023 | Partial Approval | VINCENT HANLEY |
| MERV13>=Rough | 1/10/2023 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 1/10/2023 | Approved | VINCENT HANLEY |
| Shower Pan | 1/10/2023 | Approved | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 1/10/2023 | Approved | VINCENT HANLEY |
| Drywall Nailing | 2/8/2023 | Corrections Issued | JESUS PINEDA |
| Drywall Nailing | 2/8/2023 | Not Ready for Inspection | VINCENT HANLEY |
| Insulation | 2/8/2023 | Approved | VINCENT HANLEY |
| Drywall Nailing | 2/15/2023 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 2/15/2023 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 2/23/2023 | Partial Inspection | JESUS PINEDA |
| ELECTRICAL-Final | 11/13/2023 | Approved | VINCENT HANLEY |
| Gas Test | 11/13/2023 | Approved | VINCENT HANLEY |
| Service/Power Release | 11/14/2023 | Approved | VINCENT HANLEY |
| Final | 2/6/2024 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 2/6/2024 | Approved | VINCENT HANLEY |
| MERV13>=Final | 2/6/2024 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 2/6/2024 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 2/6/2024 | Approved | VINCENT HANLEY |
| Final | 2/21/2024 | OK to Issue CofO | VINCENT HANLEY |