10013 N NOBLE AVE 91345
Certificate Information: 10013 N NOBLE AVE 91345
- Application / Permit
- 21010-20000-03141
- Plan Check / Job No.
- B21VN08090
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 1-STORY 46'-3" X 31'-0", 1200 SQ FT IRREGULAR SHAPED ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)-(d). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 12/6/2021
- Issuing Office
- Current Status
- CofO Issued on 3/15/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/8/2021 | COLIN LOREDO |
| Corrections Issued | 7/13/2021 | COLIN LOREDO |
| Quality Review Completed | 7/28/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 7/30/2021 | APPLICANT |
| Plan Check Approved | 12/2/2021 | COLIN LOREDO |
| Issued | 12/6/2021 | APPLICANT |
| CofO in Progress | 2/23/2023 | JENNIFER RABUCHIN |
| CofO Issued | 3/15/2023 | MICHAEL SMITH |
| Permit Finaled | 3/15/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 7/31/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 8/2/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 8/2/2021 | GABRIEL ROBLES |
| Hydrant and Access approval | Cleared | 9/25/2021 | RUEL COLE |
| Construction near power lines | Cleared | 11/10/2021 | TINA MIRANDA |
| Low Impact Development | Cleared | 11/18/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 11/20/2021 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/31/2022 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 3/31/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 4/12/2022 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 5/3/2022 | Partial Inspection | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/3/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 5/3/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| PLUMBING-Rough | 5/3/2022 | Partial Approval | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 5/3/2022 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 5/26/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 5/26/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 5/26/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 5/26/2022 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 6/1/2022 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 6/1/2022 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 6/1/2022 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 6/1/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 6/1/2022 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 6/8/2022 | Partial Approval | JENNIFER RABUCHIN |
| Shower Pan | 6/8/2022 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 6/13/2022 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 6/13/2022 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 6/13/2022 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 6/17/2022 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 6/17/2022 | Approved | JENNIFER RABUCHIN |
| Insulation | 6/17/2022 | Approved | JENNIFER RABUCHIN |
| Sewer | 7/7/2022 | Approved | JENNIFER RABUCHIN |
| Gas Test | 8/3/2022 | Partial Approval | JENNIFER RABUCHIN |
| Underground Mechanical | 8/3/2022 | Partial Approval | JENNIFER RABUCHIN |
| Underground Mechanical | 9/26/2022 | Approved | DEANDRE HOFFMAN |
| ELECTRICAL-Final | 12/23/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 12/23/2022 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Final | 12/23/2022 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Final | 12/23/2022 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 1/24/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 1/24/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 1/24/2023 | Approved | JENNIFER RABUCHIN |
| Gas Test | 1/24/2023 | Approved | JENNIFER RABUCHIN |
| Green Building Final | 1/24/2023 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 1/24/2023 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Final | 1/24/2023 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 1/24/2023 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 1/24/2023 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 2/21/2023 | Approved | JENNIFER RABUCHIN |
| Final | 2/21/2023 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 2/21/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 2/21/2023 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 2/21/2023 | Approved | JENNIFER RABUCHIN |