10013 N NOBLE AVE 91345

Certificate Information: 10013 N NOBLE AVE 91345

Application / Permit
21010-20000-03141
Plan Check / Job No.
B21VN08090
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1-STORY 46'-3" X 31'-0", 1200 SQ FT IRREGULAR SHAPED ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)-(d). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 12/6/2021
Issuing Office
Current Status
CofO Issued on 3/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/23/2021 APPLICANT
Assigned to Plan Check Engineer 7/8/2021 COLIN LOREDO
Corrections Issued 7/13/2021 COLIN LOREDO
Quality Review Completed 7/28/2021 OMID HEDAYAT
Building Plans Picked Up 7/30/2021 APPLICANT
Plan Check Approved 12/2/2021 COLIN LOREDO
Issued 12/6/2021 APPLICANT
CofO in Progress 2/23/2023 JENNIFER RABUCHIN
CofO Issued 3/15/2023 MICHAEL SMITH
Permit Finaled 3/15/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 7/31/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 8/2/2021 GABRIEL ROBLES
Sewer availability Cleared 8/2/2021 GABRIEL ROBLES
Hydrant and Access approval Cleared 9/25/2021 RUEL COLE
Construction near power lines Cleared 11/10/2021 TINA MIRANDA
Low Impact Development Cleared 11/18/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 11/20/2021 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/31/2022 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 3/31/2022 Corrections Issued JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 4/12/2022 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 5/3/2022 Partial Inspection JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 5/3/2022 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 5/3/2022 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 5/3/2022 Partial Approval JENNIFER RABUCHIN
Verify Sprinkler Sign Off 5/3/2022 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 5/26/2022 Not Ready for Inspection JENNIFER RABUCHIN
ELECTRICAL-Rough 5/26/2022 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 5/26/2022 Approved JENNIFER RABUCHIN
PLUMBING-Rough 5/26/2022 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 6/1/2022 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 6/1/2022 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 6/1/2022 Approved JENNIFER RABUCHIN
Green Building Rough 6/1/2022 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 6/1/2022 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 6/8/2022 Partial Approval JENNIFER RABUCHIN
Shower Pan 6/8/2022 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 6/13/2022 Approved JENNIFER RABUCHIN
Green Building Rough 6/13/2022 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 6/13/2022 Approved JENNIFER RABUCHIN
Drywall Nailing 6/17/2022 Approved JENNIFER RABUCHIN
Green Building Rough 6/17/2022 Approved JENNIFER RABUCHIN
Insulation 6/17/2022 Approved JENNIFER RABUCHIN
Sewer 7/7/2022 Approved JENNIFER RABUCHIN
Gas Test 8/3/2022 Partial Approval JENNIFER RABUCHIN
Underground Mechanical 8/3/2022 Partial Approval JENNIFER RABUCHIN
Underground Mechanical 9/26/2022 Approved DEANDRE HOFFMAN
ELECTRICAL-Final 12/23/2022 Corrections Issued JENNIFER RABUCHIN
Final 12/23/2022 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 12/23/2022 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 12/23/2022 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Final 1/24/2023 Corrections Issued JENNIFER RABUCHIN
Final 1/24/2023 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 1/24/2023 Approved JENNIFER RABUCHIN
Gas Test 1/24/2023 Approved JENNIFER RABUCHIN
Green Building Final 1/24/2023 Approved JENNIFER RABUCHIN
HVAC-Final 1/24/2023 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 1/24/2023 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 1/24/2023 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 1/24/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 2/21/2023 Approved JENNIFER RABUCHIN
Final 2/21/2023 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 2/21/2023 Approved JENNIFER RABUCHIN
PLUMBING-Final 2/21/2023 Approved JENNIFER RABUCHIN
Service/Power Release 2/21/2023 Approved JENNIFER RABUCHIN