19243 W SANTA RITA ST 91356

Certificate Information: 19243 W SANTA RITA ST 91356

Application / Permit
21010-20000-03112
Plan Check / Job No.
B21VN08002
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 32'-7" X 32' ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)¹, (d)¹, and (g)
Permit Issued
Issued on 5/11/2022
Issuing Office
Current Status
CofO Issued on 4/18/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/25/2021 APPLICANT
Assigned to Plan Check Engineer 7/8/2021 SELLA BENYAMIN
Corrections Issued 7/12/2021 SELLA BENYAMIN
Quality Review Completed 7/14/2021 STEVEN KIM
Building Plans Picked Up 7/15/2021 APPLICANT
Applicant returned to address corrections 2/16/2022 SELLA BENYAMIN
Applicant returned to address corrections 3/21/2022 SELLA BENYAMIN
Plan Check Approved 4/28/2022 SELLA BENYAMIN
Issued 5/11/2022 APPLICANT
CofO in Progress 10/14/2025 SEAN WIRCH
Permit Finaled 4/18/2026 MICHAEL PELHAM
CofO Issued 4/18/2026 MICHAEL PELHAM
Permit Finaled 4/18/2026 MICHAEL PELHAM

Permit Application Clearance Information

Address approval Cleared 8/24/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 8/25/2021 CARLOS AGUILERA
Sewer availability Cleared 8/25/2021 CARLOS AGUILERA
Hydrant and Access approval Cleared 1/11/2022 GILBERT URREA
Low Impact Development Cleared 2/3/2022 SUNG JOON WON
Roof/Waste drainage to street Cleared 2/3/2022 CARLOS AGUILERA
GPI Written Notices Cleared 4/28/2022 SELLA BENYAMIN
Grading Pre-Inspection Cleared 4/28/2022 SELLA BENYAMIN

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/10/2022 Approved DAVID SCANTLIN
Underground Mechanical 6/10/2022 Approved DAVID SCANTLIN
Footing/Foundation/Slab 6/15/2022 Approved DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 6/24/2022 Partial Approval DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 7/26/2022 Partial Approval DAVID SANDOVAL
HVAC-Rough 7/26/2022 Not Ready for Inspection DAVID SANDOVAL
PLUMBING-Rough 7/26/2022 Approved DAVID SANDOVAL
ELECTRICAL-Rough 8/16/2022 Approved DAVID SANDOVAL
Interior/Exterior Lathing 8/16/2022 Partial Approval DAVID SANDOVAL
Shower Pan 8/16/2022 Approved DAVID SANDOVAL
Insulation 8/22/2022 Not Ready for Inspection DAVID SANDOVAL
Interior/Exterior Lathing 8/22/2022 Not Ready for Inspection DAVID SANDOVAL
Drywall Nailing 9/2/2022 Approved DAVID SANDOVAL
Insulation 9/2/2022 Approved DAVID SANDOVAL
Special/Order Compliance 4/5/2023 Partial Inspection DAVID SCANTLIN
Special/Order Compliance 4/5/2023 Partial Inspection SEAN WIRCH
Special/Order Compliance 5/12/2023 Corrections Issued SEAN WIRCH
Special/Order Compliance 6/7/2023 Partial Inspection SEAN WIRCH
ELECTRICAL-Final 3/12/2024 Not Ready for Inspection JOHN KIDWELL
HVAC-Final 3/12/2024 Not Ready for Inspection JOHN KIDWELL
PLUMBING-Final 3/12/2024 Not Ready for Inspection JOHN KIDWELL
Service/Power Release 3/12/2024 Not Ready for Inspection JOHN KIDWELL
ELECTRICAL-Final 4/12/2024 Approved JOHN KIDWELL
PLUMBING-Final 4/12/2024 Approved JOHN KIDWELL
Service/Power Release 4/12/2024 Not Ready for Inspection JOHN KIDWELL
BUILDING-Rough-Frame 7/12/2024 Approved JOHN KIDWELL
Final 7/12/2024 Corrections Issued JOHN KIDWELL
Green Building Final 7/12/2024 Approved JOHN KIDWELL
Green Building Rough 7/12/2024 Approved JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 7/12/2024 SGSOV Approved JOHN KIDWELL
Service/Power Release 7/12/2024 Not Ready for Inspection JOHN KIDWELL
Smoke Detectors 7/12/2024 Approved JOHN KIDWELL
Verify Sprinkler Sign Off 7/12/2024 Approved JOHN KIDWELL
Final 7/18/2024 Not Ready for Inspection JOHN KIDWELL
Service/Power Release 7/18/2024 Approved JOHN KIDWELL
Final 10/15/2025 OK to Issue CofO SEAN WIRCH