451 E 43RD PL 90011
Certificate Information: 451 E 43RD PL 90011
- Application / Permit
- 21010-20000-03094
- Plan Check / Job No.
- B21VN07966
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan NEW ADU. New Accessory Dwelling unit by Installing a RADCO Approved Factory Built Housing Unit over a raised floor foundation per LADBS ADU Standard Plan ADU29. per RAD-31-1030. per Ordinance
- Permit Issued
- Issued on 9/23/2021
- Issuing Office
- Current Status
- CofO Issued on 9/16/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/23/2021 | MONICA RAMIREZ |
| Corrections Issued | 6/23/2021 | MONICA RAMIREZ |
| Plan Check Approved | 9/21/2021 | MONICA RAMIREZ |
| Issued | 9/23/2021 | APPLICANT |
| CofO in Progress | 8/22/2022 | JOAQUIN GREENOUGH |
| No Progress | 8/22/2022 | JOAQUIN GREENOUGH |
| CofO in Progress | 8/22/2022 | JOAQUIN GREENOUGH |
| Permit Finaled | 9/16/2022 | DEROLD HAUFF |
| CofO Issued | 9/16/2022 | DEROLD HAUFF |
| Permit Finaled | 9/16/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/19/2021 | RENZ SORIANO |
| Roof/Waste drainage to street | Cleared | 7/19/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 7/20/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 7/20/2021 | RENZ SORIANO |
| Construction near power lines | Cleared | 8/30/2021 | RIDWAN HARDY |
Contact Information
| Contractor | United Dwelling Construction Inc; Lic. No.: 1066382-B | , |
| Engineer | Farish,, William Crawford; Lic. No.: C30123 | 19432 CASTLEWOOD CR HUNTINGTON BEACH, CA 92648 |
| Engineer | Sveiven,, Shane; Lic. No.: C89133 | 1909 S ALMA STREET SAN PEDRO, CA 90731 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/29/2021 | Approved | ADAM ESCOTO |
| Excavation/Setback/Form/Re-Bar | 11/8/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 11/8/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Sewer | 11/8/2021 | Partial Approval | JOAQUIN GREENOUGH |
| Underground Mechanical | 11/8/2021 | Partial Approval | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 11/9/2021 | Conditional Approval | JOAQUIN GREENOUGH |
| Underground Mechanical | 11/9/2021 | Partial Approval | JOAQUIN GREENOUGH |
| Underground Mechanical | 11/18/2021 | Approved | HORACE FULTZ |
| Underground Mechanical | 11/23/2021 | No Access for Inspection | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 12/2/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Green Building Rough | 12/2/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| HVAC-Rough | 12/2/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Verify Sprinkler Sign Off | 12/2/2021 | Approved | JOAQUIN GREENOUGH |
| HVAC-Final | 12/3/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Wood Frame | 12/7/2021 | Partial Approval | HORACE FULTZ |
| HVAC-Rough | 12/13/2021 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 2/22/2022 | Corrections Issued | ANTHONY EGSON |
| HVAC-Final | 2/22/2022 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Final | 2/22/2022 | Corrections Issued | ANTHONY EGSON |
| Service/Power Release | 2/22/2022 | Corrections Issued | ANTHONY EGSON |
| BUILDING-Rough-Frame | 5/20/2022 | Approved | HORACE FULTZ |
| ELECTRICAL-Final | 5/20/2022 | Not Ready for Inspection | HORACE FULTZ |
| Final | 5/20/2022 | Corrections Issued | HORACE FULTZ |
| Footing/Foundation/Slab | 5/20/2022 | Approved | HORACE FULTZ |
| Green Building Final | 5/20/2022 | Approved | HORACE FULTZ |
| Green Building Rough | 5/20/2022 | Approved | HORACE FULTZ |
| SGSOV-Seismic Gas S/O Valve | 5/20/2022 | SGSOV Not Ready | HORACE FULTZ |
| Service/Power Release | 5/20/2022 | Corrections Issued | HORACE FULTZ |
| Smoke Detectors | 5/20/2022 | Approved | HORACE FULTZ |
| SGSOV-Seismic Gas S/O Valve | 6/30/2022 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 8/17/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 8/17/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 8/17/2022 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Service/Power Release | 8/17/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 8/19/2022 | Approved | JOAQUIN GREENOUGH |
| Final | 8/19/2022 | OK to Issue CofO | JOAQUIN GREENOUGH |
| HVAC-Final | 8/19/2022 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Final | 8/19/2022 | Approved | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 8/19/2022 | SGSOV Approved | JOAQUIN GREENOUGH |
| Service/Power Release | 8/19/2022 | Approved | JOAQUIN GREENOUGH |