519 N MARTEL AVE 90036

Certificate Information: 519 N MARTEL AVE 90036

Application / Permit
21010-20000-03084
Plan Check / Job No.
B21VN07913
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 23'-9" X 34'-1" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d) W/ ATTACHED 3'-7" X 13'-9" PORCH. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 4/20/2022
Issuing Office
Current Status
CofO Issued on 10/9/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/28/2021 APPLICANT
Assigned to Plan Check Engineer 6/30/2021 RAPHAEL ROSAS
Corrections Issued 7/1/2021 RAPHAEL ROSAS
Applicant returned to address corrections 1/4/2022 RAPHAEL ROSAS
Applicant returned to address corrections 3/5/2022 RAPHAEL ROSAS
Building Plans Picked Up 4/1/2022 APPLICANT
Plan Check Approved 4/20/2022 RAPHAEL ROSAS
Issued 4/20/2022 APPLICANT
CofO in Progress 8/29/2023 LILIANA PORTILLO
CofO in Progress 9/29/2023 DONALD CRICHLOW
CofO in Progress 10/2/2023 LILIANA PORTILLO
Permit Finaled 10/5/2023 DONALD CRICHLOW
CofO Issued 10/9/2023 DEROLD HAUFF
Permit Finaled 10/9/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/8/2021 AMAAN MALIK
Construction near power lines Cleared 12/14/2021 RIDWAN HARDY
Low Impact Development Cleared 1/25/2022 ANTHONY VARGAS
Hydrant and Access approval Cleared 2/19/2022 CINDY JOSSELYN
Eng Process Fee Ord 176,300 Cleared 2/28/2022 AMIR KASHFI
Sewer availability Cleared 2/28/2022 AMIR KASHFI
Roof/Waste drainage to street Cleared 3/15/2022 AMIR KASHFI

Contact Information

Contractor Psg Hardware & Supply; Lic. No.: 1079377-B 10418 GLADE AVENUE      CHATSWORTH, CA 91311
Engineer Luisoni,, Antonio Stefano; Lic. No.: S1781 12757 DEON PLACE      GRANADA HILLS, CA 91344

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/26/2022 Corrections Issued ADAM ESCOTO
PLUMBING-Rough 4/26/2022 Corrections Issued ADAM ESCOTO
Pre-Inspection 4/26/2022 Corrections Issued ADAM ESCOTO
Excavation/Setback/Form/Re-Bar 4/28/2022 Not Ready for Inspection JOSEPH MCGARRY
Footing/Foundation/Slab 4/28/2022 Corrections Issued JOSEPH MCGARRY
METHANE-Barrier 4/28/2022 Not Ready for Inspection JOSEPH MCGARRY
METHANE-Subgrade 4/28/2022 Not Ready for Inspection JOSEPH MCGARRY
PLUMBING-Rough 4/28/2022 Partial Approval JOSEPH MCGARRY
Special/Order Compliance 4/28/2022 Partial Inspection ADAM ESCOTO
Excavation/Setback/Form/Re-Bar 5/5/2022 Not Ready for Inspection ADAM ESCOTO
Footing/Foundation/Slab 5/5/2022 Not Ready for Inspection ADAM ESCOTO
METHANE-Barrier 5/5/2022 Approved ADAM ESCOTO
METHANE-Subgrade 5/5/2022 Approved ADAM ESCOTO
Excavation/Setback/Form/Re-Bar 5/6/2022 Approved ADAM ESCOTO
Floor/Roof Diaphrgm/Shear Wall 5/23/2022 Partial Approval JOSEPH MCGARRY
ELECTRICAL-Rough 7/8/2022 Approved JOSEPH MCGARRY
HVAC-Rough 7/8/2022 Corrections Issued JOSEPH MCGARRY
PLUMBING-Rough 7/8/2022 Approved JOSEPH MCGARRY
ELECTRICAL-Rough 8/15/2022 Approved MICHAEL LEWIS
HVAC-Rough 8/15/2022 Approved MICHAEL LEWIS
PLUMBING-Rough 8/15/2022 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 8/17/2022 Partial Approval MICHAEL LEWIS
Green Building Rough 8/17/2022 Approved MICHAEL LEWIS
METHANE-Rough 8/17/2022 Approved MICHAEL LEWIS
Verify Sprinkler Sign Off 8/17/2022 Partial Inspection MICHAEL LEWIS
Special/Order Compliance 8/24/2022 Approved MICHAEL LEWIS
Insulation 9/6/2022 Corrections Issued MICHAEL LEWIS
Interior/Exterior Lathing 9/6/2022 Approved MICHAEL LEWIS
Insulation 9/13/2022 Approved MICHAEL LEWIS
Interior/Exterior Lathing 9/13/2022 Approved MICHAEL LEWIS
Shower Pan 9/13/2022 Approved MICHAEL LEWIS
Drywall Nailing 9/26/2022 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 5/15/2023 SGSOV Not Ready LILIANA PORTILLO
Service/Power Release 5/24/2023 Not Ready for Inspection LILIANA PORTILLO
BUILDING-Rough-Frame 6/1/2023 Approved LILIANA PORTILLO
ELECTRICAL-Final 6/1/2023 Corrections Issued LILIANA PORTILLO
Final 6/1/2023 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 6/1/2023 Approved LILIANA PORTILLO
Green Building Final 6/1/2023 Conditional Approval LILIANA PORTILLO
HVAC-Final 6/1/2023 Corrections Issued LILIANA PORTILLO
PLUMBING-Final 6/1/2023 Corrections Issued LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 6/1/2023 SGSOV Not Ready LILIANA PORTILLO
Service/Power Release 6/1/2023 Not Ready for Inspection LILIANA PORTILLO
Smoke Detectors 6/1/2023 Approved LILIANA PORTILLO
ELECTRICAL-Final 7/3/2023 Approved LILIANA PORTILLO
Final 7/3/2023 Not Ready for Inspection LILIANA PORTILLO
Green Building Final 7/3/2023 Approved LILIANA PORTILLO
HVAC-Final 7/3/2023 Partial Approval LILIANA PORTILLO
PLUMBING-Final 7/3/2023 Not Ready for Inspection LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 7/3/2023 SGSOV Not Ready LILIANA PORTILLO
Service/Power Release 7/3/2023 Not Ready for Inspection LILIANA PORTILLO
Final 7/10/2023 Not Ready for Inspection LILIANA PORTILLO
HVAC-Final 7/10/2023 Approved LILIANA PORTILLO
PLUMBING-Final 7/10/2023 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 7/10/2023 SGSOV Not Ready LILIANA PORTILLO
Service/Power Release 7/10/2023 Not Ready for Inspection LILIANA PORTILLO
Final 8/25/2023 Not Ready for Inspection LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 8/25/2023 SGSOV Not Ready LILIANA PORTILLO
Service/Power Release 8/25/2023 Not Ready for Inspection LILIANA PORTILLO
Final 8/29/2023 Corrections Issued LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 8/29/2023 SGSOV Approved LILIANA PORTILLO
Service/Power Release 8/29/2023 Approved LILIANA PORTILLO
Final 9/29/2023 OK to Issue CofO LILIANA PORTILLO