519 N MARTEL AVE 90036
Certificate Information: 519 N MARTEL AVE 90036
- Application / Permit
- 21010-20000-03084
- Plan Check / Job No.
- B21VN07913
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 23'-9" X 34'-1" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d) W/ ATTACHED 3'-7" X 13'-9" PORCH. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 4/20/2022
- Issuing Office
- Current Status
- CofO Issued on 10/9/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/30/2021 | RAPHAEL ROSAS |
| Corrections Issued | 7/1/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 1/4/2022 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 3/5/2022 | RAPHAEL ROSAS |
| Building Plans Picked Up | 4/1/2022 | APPLICANT |
| Plan Check Approved | 4/20/2022 | RAPHAEL ROSAS |
| Issued | 4/20/2022 | APPLICANT |
| CofO in Progress | 8/29/2023 | LILIANA PORTILLO |
| CofO in Progress | 9/29/2023 | DONALD CRICHLOW |
| CofO in Progress | 10/2/2023 | LILIANA PORTILLO |
| Permit Finaled | 10/5/2023 | DONALD CRICHLOW |
| CofO Issued | 10/9/2023 | DEROLD HAUFF |
| Permit Finaled | 10/9/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/8/2021 | AMAAN MALIK |
| Construction near power lines | Cleared | 12/14/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 1/25/2022 | ANTHONY VARGAS |
| Hydrant and Access approval | Cleared | 2/19/2022 | CINDY JOSSELYN |
| Eng Process Fee Ord 176,300 | Cleared | 2/28/2022 | AMIR KASHFI |
| Sewer availability | Cleared | 2/28/2022 | AMIR KASHFI |
| Roof/Waste drainage to street | Cleared | 3/15/2022 | AMIR KASHFI |
Contact Information
| Contractor | Psg Hardware & Supply; Lic. No.: 1079377-B | 10418 GLADE AVENUE CHATSWORTH, CA 91311 |
| Engineer | Luisoni,, Antonio Stefano; Lic. No.: S1781 | 12757 DEON PLACE GRANADA HILLS, CA 91344 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/26/2022 | Corrections Issued | ADAM ESCOTO |
| PLUMBING-Rough | 4/26/2022 | Corrections Issued | ADAM ESCOTO |
| Pre-Inspection | 4/26/2022 | Corrections Issued | ADAM ESCOTO |
| Excavation/Setback/Form/Re-Bar | 4/28/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 4/28/2022 | Corrections Issued | JOSEPH MCGARRY |
| METHANE-Barrier | 4/28/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| METHANE-Subgrade | 4/28/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| PLUMBING-Rough | 4/28/2022 | Partial Approval | JOSEPH MCGARRY |
| Special/Order Compliance | 4/28/2022 | Partial Inspection | ADAM ESCOTO |
| Excavation/Setback/Form/Re-Bar | 5/5/2022 | Not Ready for Inspection | ADAM ESCOTO |
| Footing/Foundation/Slab | 5/5/2022 | Not Ready for Inspection | ADAM ESCOTO |
| METHANE-Barrier | 5/5/2022 | Approved | ADAM ESCOTO |
| METHANE-Subgrade | 5/5/2022 | Approved | ADAM ESCOTO |
| Excavation/Setback/Form/Re-Bar | 5/6/2022 | Approved | ADAM ESCOTO |
| Floor/Roof Diaphrgm/Shear Wall | 5/23/2022 | Partial Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 7/8/2022 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 7/8/2022 | Corrections Issued | JOSEPH MCGARRY |
| PLUMBING-Rough | 7/8/2022 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 8/15/2022 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 8/15/2022 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 8/15/2022 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 8/17/2022 | Partial Approval | MICHAEL LEWIS |
| Green Building Rough | 8/17/2022 | Approved | MICHAEL LEWIS |
| METHANE-Rough | 8/17/2022 | Approved | MICHAEL LEWIS |
| Verify Sprinkler Sign Off | 8/17/2022 | Partial Inspection | MICHAEL LEWIS |
| Special/Order Compliance | 8/24/2022 | Approved | MICHAEL LEWIS |
| Insulation | 9/6/2022 | Corrections Issued | MICHAEL LEWIS |
| Interior/Exterior Lathing | 9/6/2022 | Approved | MICHAEL LEWIS |
| Insulation | 9/13/2022 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 9/13/2022 | Approved | MICHAEL LEWIS |
| Shower Pan | 9/13/2022 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 9/26/2022 | Approved | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 5/15/2023 | SGSOV Not Ready | LILIANA PORTILLO |
| Service/Power Release | 5/24/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 6/1/2023 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 6/1/2023 | Corrections Issued | LILIANA PORTILLO |
| Final | 6/1/2023 | Corrections Issued | LILIANA PORTILLO |
| Footing/Foundation/Slab | 6/1/2023 | Approved | LILIANA PORTILLO |
| Green Building Final | 6/1/2023 | Conditional Approval | LILIANA PORTILLO |
| HVAC-Final | 6/1/2023 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Final | 6/1/2023 | Corrections Issued | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 6/1/2023 | SGSOV Not Ready | LILIANA PORTILLO |
| Service/Power Release | 6/1/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| Smoke Detectors | 6/1/2023 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 7/3/2023 | Approved | LILIANA PORTILLO |
| Final | 7/3/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| Green Building Final | 7/3/2023 | Approved | LILIANA PORTILLO |
| HVAC-Final | 7/3/2023 | Partial Approval | LILIANA PORTILLO |
| PLUMBING-Final | 7/3/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 7/3/2023 | SGSOV Not Ready | LILIANA PORTILLO |
| Service/Power Release | 7/3/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 7/10/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| HVAC-Final | 7/10/2023 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 7/10/2023 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 7/10/2023 | SGSOV Not Ready | LILIANA PORTILLO |
| Service/Power Release | 7/10/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 8/25/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 8/25/2023 | SGSOV Not Ready | LILIANA PORTILLO |
| Service/Power Release | 8/25/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 8/29/2023 | Corrections Issued | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 8/29/2023 | SGSOV Approved | LILIANA PORTILLO |
| Service/Power Release | 8/29/2023 | Approved | LILIANA PORTILLO |
| Final | 9/29/2023 | OK to Issue CofO | LILIANA PORTILLO |