11140 N GAVIOTA AVE 91344
Certificate Information: 11140 N GAVIOTA AVE 91344
- Application / Permit
- 21010-20000-03070
- Plan Check / Job No.
- B21VN07866
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (E) GARAGE TO BE REMOVED EXCEPT FOR 1 WALL AND BUILD A NEW 2-STORY (35'-0"x20'-0"),1191.17 SQFT DETACHED ADU PER LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 2/10/2022
- Issuing Office
- Current Status
- CofO Issued on 8/14/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/12/2021 | PETER MOSESIAN |
| Corrections Issued | 8/14/2021 | PETER MOSESIAN |
| Quality Review Completed | 8/20/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 8/24/2021 | APPLICANT |
| Plan Check Approved | 2/1/2022 | PETER MOSESIAN |
| Issued | 2/10/2022 | APPLICANT |
| CofO in Progress | 7/29/2024 | JAVIER RAMOS JR |
| Permit Finaled | 8/14/2024 | DANIEL ORRANTE |
| CofO Issued | 8/14/2024 | DANIEL ORRANTE |
| Permit Finaled | 8/14/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 8/23/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 8/31/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 8/31/2021 | DAGOVERTO GUERRERO |
| Grading Pre-Inspection | Cleared | 10/8/2021 | ALEXANDER ANDREWS |
| Hydrant and Access approval | Cleared | 10/11/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 10/27/2021 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 10/28/2021 | DAGOVERTO GUERRERO |
| Construction near power lines | Cleared | 12/13/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/12/2024 | Conditional Approval | DAVID MATSON |
| PLUMBING-Rough | 1/12/2024 | Partial Approval | JAVIER RAMOS JR |
| Pre-Inspection | 1/12/2024 | Approved | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 1/17/2024 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 2/6/2024 | Not Ready for Inspection | CRAIG DAVIS |
| Deputy Wood Construction | 2/6/2024 | Conditional Approval | JOHN COLEMAN |
| Green Building Rough | 2/6/2024 | Not Ready for Inspection | CRAIG DAVIS |
| Wood Frame | 2/6/2024 | Partial Approval | CRAIG DAVIS |
| Deputy Wood Construction | 2/14/2024 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 2/14/2024 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 3/1/2024 | Corrections Issued | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 3/1/2024 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 3/1/2024 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 3/1/2024 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 3/1/2024 | Corrections Issued | JAVIER RAMOS JR |
| Insulation | 3/8/2024 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 3/8/2024 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 3/8/2024 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 3/15/2024 | Approved | SALVADOR MARTINEZ |
| Sewer | 4/26/2024 | Approved | RYAN SALAZAR |
| Underground Mechanical | 5/2/2024 | Partial Approval | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 7/3/2024 | Approved | JENNIFER RABUCHIN |
| Final | 7/3/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 7/3/2024 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 7/3/2024 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 7/3/2024 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 7/9/2024 | Approved | JAVIER RAMOS JR |
| Final | 7/9/2024 | OK to Issue CofO | JAVIER RAMOS JR |
| Green Building Final | 7/9/2024 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 7/9/2024 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 7/9/2024 | Approved | JAVIER RAMOS JR |