11140 N GAVIOTA AVE 91344

Certificate Information: 11140 N GAVIOTA AVE 91344

Application / Permit
21010-20000-03070
Plan Check / Job No.
B21VN07866
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(E) GARAGE TO BE REMOVED EXCEPT FOR 1 WALL AND BUILD A NEW 2-STORY (35'-0"x20'-0"),1191.17 SQFT DETACHED ADU PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 2/10/2022
Issuing Office
Current Status
CofO Issued on 8/14/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/13/2021 APPLICANT
Assigned to Plan Check Engineer 8/12/2021 PETER MOSESIAN
Corrections Issued 8/14/2021 PETER MOSESIAN
Quality Review Completed 8/20/2021 OMID HEDAYAT
Building Plans Picked Up 8/24/2021 APPLICANT
Plan Check Approved 2/1/2022 PETER MOSESIAN
Issued 2/10/2022 APPLICANT
CofO in Progress 7/29/2024 JAVIER RAMOS JR
Permit Finaled 8/14/2024 DANIEL ORRANTE
CofO Issued 8/14/2024 DANIEL ORRANTE
Permit Finaled 8/14/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 8/23/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 8/31/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 8/31/2021 DAGOVERTO GUERRERO
Grading Pre-Inspection Cleared 10/8/2021 ALEXANDER ANDREWS
Hydrant and Access approval Cleared 10/11/2021 MATTHEW CRAIG
Low Impact Development Cleared 10/27/2021 CHRIS VONG
Roof/Waste drainage to street Cleared 10/28/2021 DAGOVERTO GUERRERO
Construction near power lines Cleared 12/13/2021 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/12/2024 Conditional Approval DAVID MATSON
PLUMBING-Rough 1/12/2024 Partial Approval JAVIER RAMOS JR
Pre-Inspection 1/12/2024 Approved JAVIER RAMOS JR
Footing/Foundation/Slab 1/17/2024 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 2/6/2024 Not Ready for Inspection CRAIG DAVIS
Deputy Wood Construction 2/6/2024 Conditional Approval JOHN COLEMAN
Green Building Rough 2/6/2024 Not Ready for Inspection CRAIG DAVIS
Wood Frame 2/6/2024 Partial Approval CRAIG DAVIS
Deputy Wood Construction 2/14/2024 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 2/14/2024 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 3/1/2024 Corrections Issued JAVIER RAMOS JR
ELECTRICAL-Rough 3/1/2024 Approved JAVIER RAMOS JR
Green Building Rough 3/1/2024 Approved JAVIER RAMOS JR
HVAC-Rough 3/1/2024 Approved JAVIER RAMOS JR
PLUMBING-Rough 3/1/2024 Corrections Issued JAVIER RAMOS JR
Insulation 3/8/2024 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 3/8/2024 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 3/8/2024 Approved JAVIER RAMOS JR
Drywall Nailing 3/15/2024 Approved SALVADOR MARTINEZ
Sewer 4/26/2024 Approved RYAN SALAZAR
Underground Mechanical 5/2/2024 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 7/3/2024 Approved JENNIFER RABUCHIN
Final 7/3/2024 Corrections Issued JENNIFER RABUCHIN
Green Building Final 7/3/2024 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 7/3/2024 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 7/3/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 7/9/2024 Approved JAVIER RAMOS JR
Final 7/9/2024 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 7/9/2024 Approved JAVIER RAMOS JR
HVAC-Final 7/9/2024 Approved JAVIER RAMOS JR
PLUMBING-Final 7/9/2024 Approved JAVIER RAMOS JR