10332 N JORDAN AVE 91311
Certificate Information: 10332 N JORDAN AVE 91311
- Application / Permit
- 21010-20000-03067
- Plan Check / Job No.
- B21VN07858
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 20' X 30' TWO STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d); EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 2/25/2022
- Issuing Office
- Current Status
- CofO Issued on 8/31/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/22/2021 | SELLA BENYAMIN |
| Corrections Issued | 7/26/2021 | SELLA BENYAMIN |
| Quality Review Completed | 7/28/2021 | STEVEN KIM |
| Building Plans Picked Up | 7/29/2021 | APPLICANT |
| Applicant returned to address corrections | 1/21/2022 | SELLA BENYAMIN |
| Plan Check Approved | 2/10/2022 | SELLA BENYAMIN |
| Issued | 2/25/2022 | APPLICANT |
| CofO in Progress | 7/14/2023 | CHRIS CHRISTENSEN |
| CofO Issued | 8/31/2023 | JOHN JANSON |
| Permit Finaled | 8/31/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 8/11/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 8/13/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 9/7/2021 | GABRIEL ROBLES |
| Hydrant and Access approval | Cleared | 10/26/2021 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 11/5/2021 | TA ANH |
| Roof/Waste drainage to street | Cleared | 11/8/2021 | ABDULLAH SADOZAI |
| GPI Written Notices | Cleared | 2/10/2022 | SELLA BENYAMIN |
| Grading Pre-Inspection | Cleared | 2/10/2022 | SELLA BENYAMIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Abedian,, Vanik; Lic. No.: S5323 | 2906 JOLLEY DR BURBANK, CA 91504 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/22/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| Underground Mechanical | 3/22/2022 | Partial Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 3/29/2022 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 7/21/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 7/21/2022 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 7/21/2022 | Conditional Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 7/21/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| HVAC-Rough | 7/21/2022 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 7/21/2022 | Approved | CHRIS CHRISTENSEN |
| Sewer | 7/21/2022 | Approved | CHRIS CHRISTENSEN |
| Shower Pan | 7/21/2022 | Approved | CHRIS CHRISTENSEN |
| Verify Sprinkler Sign Off | 7/21/2022 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 9/13/2022 | Partial Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 9/28/2022 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 9/28/2022 | Conditional Approval | CHRIS CHRISTENSEN |
| Wood Frame | 9/28/2022 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 10/5/2022 | Approved | JUSTIN HAWLEY |
| Insulation | 10/5/2022 | Approved | JUSTIN HAWLEY |
| Drywall Nailing | 10/13/2022 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 10/13/2022 | Approved | CHRIS CHRISTENSEN |
| Shower Pan | 10/13/2022 | Approved | CHRIS CHRISTENSEN |
| Green Building Final | 2/6/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 5/25/2023 | Approved | CHRIS CHRISTENSEN |
| Final | 5/25/2023 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 5/25/2023 | Approved | CHRIS CHRISTENSEN |
| HVAC-Final | 5/25/2023 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 5/25/2023 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 5/25/2023 | SGSOV Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 5/25/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Smoke Detectors | 5/25/2023 | Approved | CHRIS CHRISTENSEN |
| Final | 7/14/2023 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Service/Power Release | 7/14/2023 | Approved | CHRIS CHRISTENSEN |