10778 N REDMONT AVE 91042

Certificate Information: 10778 N REDMONT AVE 91042

Application / Permit
21010-20000-03057
Plan Check / Job No.
B21VN07815
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*ePLAN CHECK* (N) ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)&(e)
Permit Issued
Issued on 8/19/2022
Issuing Office
Current Status
CofO Issued on 9/11/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/18/2021 APPLICANT
Assigned to Plan Check Engineer 7/8/2021 LAMAR DAVIS
Corrections Issued 7/20/2021 LAMAR DAVIS
Quality Review Completed 7/31/2021 PRANITA SHAH
Applicant returned to address corrections 3/10/2022 LAMAR DAVIS
Applicant returned to address corrections 5/11/2022 LAMAR DAVIS
Plan Check Approved 8/16/2022 LAMAR DAVIS
Issued 8/19/2022 APPLICANT
CofO in Progress 7/26/2023 WILLIAM WREN
No Progress 7/26/2023 WILLIAM WREN
CofO in Progress 7/26/2023 WILLIAM WREN
CofO in Progress 9/5/2023 WILLIAM WREN
Permit Finaled 9/11/2023 RUBEN SALAS
CofO Issued 9/11/2023 RUBEN SALAS
Permit Finaled 9/11/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/17/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 8/18/2021 CARLOS AGUILERA
Sewer availability Cleared 8/18/2021 CARLOS AGUILERA
Hydrant and Access approval Cleared 1/5/2022 GILBERT URREA
GPI Written Notices Cleared 2/7/2022 BRIAN MILLER
Grading Pre-Inspection Cleared 2/7/2022 BRIAN MILLER
Miscellaneous Cleared 3/11/2022 LAMAR DAVIS
Construction near power lines Cleared 3/30/2022 WALTER RAMIREZ
Low Impact Development Cleared 6/20/2022 ROGELIO CORTES
Roof/Waste drainage to street Cleared 7/5/2022 CARLOS AGUILERA
Miscellaneous Cleared 8/2/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Motavvef,, Nasser; Lic. No.: C40977 15335 MORRISON ST 370      SHERMAN OAKS, CA 91403

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/22/2022 Corrections Issued WILLIAM WREN
Footing/Foundation/Slab 11/29/2022 Approved WILLIAM WREN
BUILDING-Rough-Frame 12/13/2022 Corrections Issued CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 12/16/2022 Partial Approval WILLIAM WREN
PLUMBING-Rough 12/16/2022 Partial Approval WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 12/20/2022 Approved WILLIAM WREN
Insulation 12/20/2022 Partial Approval WILLIAM WREN
Deputy Wood Construction 12/21/2022 Conditional Approval DAVID MATSON
Deputy Wood Construction 1/6/2023 Conditional Approval DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 1/6/2023 Conditional Approval WILLIAM WREN
ELECTRICAL-Rough 2/13/2023 Corrections Issued WILLIAM WREN
HVAC-Rough 2/13/2023 Corrections Issued WILLIAM WREN
PLUMBING-Rough 2/13/2023 Approved WILLIAM WREN
BUILDING-Rough-Frame 2/15/2023 Approved WILLIAM WREN
Deputy Wood Construction 2/15/2023 Conditional Approval DAVID MATSON
ELECTRICAL-Rough 2/15/2023 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 2/15/2023 Approved WILLIAM WREN
Green Building Rough 2/15/2023 Approved WILLIAM WREN
HVAC-Rough 2/15/2023 Approved WILLIAM WREN
Verify Sprinkler Sign Off 2/15/2023 Approved WILLIAM WREN
Interior/Exterior Lathing 2/21/2023 Partial Approval WILLIAM WREN
Insulation 2/23/2023 Approved WILLIAM WREN
Drywall Nailing 2/27/2023 Approved WILLIAM WREN
Sewer 3/29/2023 Approved WILLIAM WREN
Gas Test 4/4/2023 Approved WILLIAM WREN
Underground Mechanical 4/4/2023 Approved WILLIAM WREN
ELECTRICAL-Rough 4/7/2023 Partial Approval MATTHEW NELSON
Shower Pan 6/1/2023 Approved WILLIAM WREN
Final 7/13/2023 Corrections Issued DAVID ANDERSON
Green Building Final 7/13/2023 Not Ready for Inspection DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 7/13/2023 SGSOV Not Ready DAVID ANDERSON
Service/Power Release 7/13/2023 Not Ready for Inspection DAVID ANDERSON
Smoke Detectors 7/13/2023 Approved DAVID ANDERSON
Final 7/25/2023 Not Ready for Inspection WILLIAM WREN
Green Building Final 7/25/2023 Approved WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 7/25/2023 SGSOV Approved WILLIAM WREN
Service/Power Release 7/25/2023 Approved WILLIAM WREN
Final 7/26/2023 Corrections Issued WILLIAM WREN
Final 8/31/2023 OK to Issue CofO WILLIAM WREN