10434 N JARDINE AVE 91040
Certificate Information: 10434 N JARDINE AVE 91040
- Application / Permit
- 21010-20000-03053
- Plan Check / Job No.
- B21VN07792
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 37'-4" X 38'-4.25" IRREGULAR SHAPED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d) W/ ATTACHED TRELLIS PATIO COVER. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 9/30/2021
- Issuing Office
- Current Status
- CofO Issued on 9/12/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/18/2021 | RAPHAEL ROSAS |
| Corrections Issued | 6/19/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 9/17/2021 | RAPHAEL ROSAS |
| Issued | 9/30/2021 | APPLICANT |
| Building Plans Picked Up | 10/4/2021 | APPLICANT |
| CofO in Progress | 9/12/2022 | DAVID ANDERSON |
| CofO in Progress | 9/12/2022 | DAVID ANDERSON |
| Permit Finaled | 9/12/2022 | MICHAEL SMITH |
| CofO Issued | 9/12/2022 | MICHAEL SMITH |
| Permit Finaled | 9/12/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 6/22/2021 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 6/23/2021 | LEE GUILBEAUX |
| Sewer availability | Cleared | 6/23/2021 | LEE GUILBEAUX |
| Grading Pre-Inspection | Cleared | 6/30/2021 | BRIAN MILLER |
| Hydrant and Access approval | Cleared | 9/1/2021 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 9/8/2021 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 9/8/2021 | LEE GUILBEAUX |
| GPI Written Notices | Cleared | 9/17/2021 | RAPHAEL ROSAS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Arakelyan,, Aram; Lic. No.: C82796 | 145 S GLENOAKS BI 328 BURBANK, CA 91502 |
Inspector Information
| MATTHEW NELSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/19/2021 | Not Ready for Inspection | WILLIAM KUEHN |
| Pre-Inspection | 10/19/2021 | Partial Inspection | WILLIAM KUEHN |
| Underground Mechanical | 11/5/2021 | Partial Inspection | WILLIAM KUEHN |
| Footing/Foundation/Slab | 11/12/2021 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/27/2021 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 1/18/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 1/18/2022 | Corrections Issued | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 1/18/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Rough | 1/18/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 1/18/2022 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 1/18/2022 | Approved | GREGG CUMMINGS |
| Verify Sprinkler Sign Off | 1/18/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Wood Frame | 1/18/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 2/16/2022 | Partial Approval | GREGG CUMMINGS |
| ELECTRICAL-Rough | 2/16/2022 | Approved | GREGG CUMMINGS |
| Green Building Rough | 2/16/2022 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 2/16/2022 | Approved | GREGG CUMMINGS |
| Verify Sprinkler Sign Off | 2/16/2022 | Approved | GREGG CUMMINGS |
| Insulation | 3/1/2022 | Corrections Issued | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 3/1/2022 | Partial Approval | ASHLEY THOMPSON |
| Drywall Nailing | 3/31/2022 | Approved | MATTHEW NELSON |
| Shower Pan | 3/31/2022 | Approved | MATTHEW NELSON |
| Piling/Pier/Caisson | 7/28/2022 | Not Ready for Inspection | DAVID ANDERSON |
| Piling/Pier/Caisson | 8/2/2022 | Corrections Issued | DAVID ANDERSON |
| Sewer | 8/2/2022 | Approved | DAVID ANDERSON |
| Footing/Foundation/Slab | 8/3/2022 | Corrections Issued | DAVID ANDERSON |
| Footing/Foundation/Slab | 8/5/2022 | Partial Approval | DAVID ANDERSON |
| BUILDING-Rough-Frame | 8/31/2022 | Corrections Issued | DAVID ANDERSON |
| Wood Frame | 8/31/2022 | Not Ready for Inspection | DAVID ANDERSON |
| ELECTRICAL-Final | 9/6/2022 | Not Ready for Inspection | DAVID ANDERSON |
| Final | 9/6/2022 | Corrections Issued | DAVID ANDERSON |
| Footing/Foundation/Slab | 9/6/2022 | Approved | DAVID ANDERSON |
| Green Building Final | 9/6/2022 | Approved | DAVID ANDERSON |
| HVAC-Final | 9/6/2022 | Approved | DAVID ANDERSON |
| PLUMBING-Final | 9/6/2022 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 9/6/2022 | SGSOV Not Ready | DAVID ANDERSON |
| Service/Power Release | 9/6/2022 | Not Ready for Inspection | DAVID ANDERSON |
| Smoke Detectors | 9/6/2022 | Approved | DAVID ANDERSON |
| Wood Frame | 9/6/2022 | Not Ready for Inspection | DAVID ANDERSON |
| BUILDING-Rough-Frame | 9/9/2022 | Approved | DAVID ANDERSON |
| ELECTRICAL-Final | 9/9/2022 | Approved | DAVID ANDERSON |
| Final | 9/9/2022 | OK to Issue CofO | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 9/9/2022 | SGSOV Approved | DAVID ANDERSON |
| Wood Frame | 9/9/2022 | Approved | DAVID ANDERSON |
| Final | 9/12/2022 | OK to Issue CofO | DAVID ANDERSON |
| Service/Power Release | 9/12/2022 | Approved | DAVID ANDERSON |