4715 E LINCOLN AVE 90042
Certificate Information: 4715 E LINCOLN AVE 90042
- Application / Permit
- 21010-20000-03044
- Plan Check / Job No.
- B21VN07753
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2-STORY DETACHED ADU AT REAR (30'-0"x20'-0") PER LAMC 12.22 A.33(c)(d)
- Permit Issued
- Issued on 10/25/2021
- Issuing Office
- Current Status
- CofO Issued on 11/18/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/22/2021 | PETER MOSESIAN |
| Corrections Issued | 7/28/2021 | PETER MOSESIAN |
| Quality Review Completed | 8/9/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 8/9/2021 | APPLICANT |
| Plan Check Approved | 10/20/2021 | PETER MOSESIAN |
| Issued | 10/25/2021 | APPLICANT |
| CofO in Progress | 9/19/2022 | JEFFREY MEAD |
| CofO Issued | 11/18/2022 | DEROLD HAUFF |
| Permit Finaled | 11/18/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/30/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 8/3/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 8/3/2021 | CECILIO NAVARRO |
| Grading Pre-Inspection | Cleared | 9/14/2021 | TIMOTHY POWELL |
| Hydrant and Access approval | Cleared | 9/25/2021 | RUEL COLE |
| Construction near power lines | Cleared | 10/1/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 10/13/2021 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 10/15/2021 | CECILIO NAVARRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/2/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 2/2/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 2/2/2022 | Partial Approval | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 2/3/2022 | Approved | CRAIG VAUGHAN |
| Underground Mechanical | 2/3/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/17/2022 | Partial Approval | COREY HUPP |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 4/1/2022 | Approved | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2022 | Partial Approval | CRAIG VAUGHAN |
| HVAC-Rough | 4/1/2022 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 4/1/2022 | Partial Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 4/6/2022 | Approved | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/6/2022 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 4/6/2022 | Approved | CRAIG VAUGHAN |
| Rough-Elec/Plmb/HVAC | 4/6/2022 | Approved | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 4/6/2022 | Approved | CRAIG VAUGHAN |
| Insulation | 4/14/2022 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 4/26/2022 | Conditional Approval | HAMIK HARTOUNIAN |
| Drywall Nailing | 4/27/2022 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 4/27/2022 | Approved | CRAIG VAUGHAN |
| Sewer | 7/6/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| Sewer | 7/8/2022 | Conditional Approval | SCOTT FINNILA |
| Final | 8/24/2022 | Corrections Issued | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 8/24/2022 | Approved | CRAIG VAUGHAN |
| Green Building Final | 8/24/2022 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 8/24/2022 | SGSOV Not Ready | CRAIG VAUGHAN |
| Service/Power Release | 8/24/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Smoke Detectors | 8/24/2022 | Approved | CRAIG VAUGHAN |
| Final | 9/13/2022 | Corrections Issued | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 9/13/2022 | SGSOV Approved | BRIAN SULLIVAN |
| Service/Power Release | 9/13/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Final | 9/16/2022 | OK to Issue CofO | JEFFREY MEAD |
| Service/Power Release | 9/16/2022 | Approved | JEFFREY MEAD |