4715 E LINCOLN AVE 90042

Certificate Information: 4715 E LINCOLN AVE 90042

Application / Permit
21010-20000-03044
Plan Check / Job No.
B21VN07753
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2-STORY DETACHED ADU AT REAR (30'-0"x20'-0") PER LAMC 12.22 A.33(c)(d)
Permit Issued
Issued on 10/25/2021
Issuing Office
Current Status
CofO Issued on 11/18/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/17/2021 APPLICANT
Assigned to Plan Check Engineer 7/22/2021 PETER MOSESIAN
Corrections Issued 7/28/2021 PETER MOSESIAN
Quality Review Completed 8/9/2021 OMID HEDAYAT
Building Plans Picked Up 8/9/2021 APPLICANT
Plan Check Approved 10/20/2021 PETER MOSESIAN
Issued 10/25/2021 APPLICANT
CofO in Progress 9/19/2022 JEFFREY MEAD
CofO Issued 11/18/2022 DEROLD HAUFF
Permit Finaled 11/18/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/30/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 8/3/2021 CECILIO NAVARRO
Sewer availability Cleared 8/3/2021 CECILIO NAVARRO
Grading Pre-Inspection Cleared 9/14/2021 TIMOTHY POWELL
Hydrant and Access approval Cleared 9/25/2021 RUEL COLE
Construction near power lines Cleared 10/1/2021 RIDWAN HARDY
Low Impact Development Cleared 10/13/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 10/15/2021 CECILIO NAVARRO

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/2/2022 Not Ready for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 2/2/2022 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 2/2/2022 Partial Approval CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 2/3/2022 Approved CRAIG VAUGHAN
Underground Mechanical 2/3/2022 Not Ready for Inspection CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 2/17/2022 Partial Approval COREY HUPP
Floor/Roof Diaphrgm/Shear Wall 3/7/2022 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 4/1/2022 Approved CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 4/1/2022 Partial Approval CRAIG VAUGHAN
HVAC-Rough 4/1/2022 Approved CRAIG VAUGHAN
PLUMBING-Rough 4/1/2022 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 4/6/2022 Approved CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 4/6/2022 Approved CRAIG VAUGHAN
Green Building Rough 4/6/2022 Approved CRAIG VAUGHAN
Rough-Elec/Plmb/HVAC 4/6/2022 Approved CRAIG VAUGHAN
Verify Sprinkler Sign Off 4/6/2022 Approved CRAIG VAUGHAN
Insulation 4/14/2022 Approved JOAQUIN GREENOUGH
Interior/Exterior Lathing 4/26/2022 Conditional Approval HAMIK HARTOUNIAN
Drywall Nailing 4/27/2022 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 4/27/2022 Approved CRAIG VAUGHAN
Sewer 7/6/2022 Not Ready for Inspection OSVALDO PARAMO
Sewer 7/8/2022 Conditional Approval SCOTT FINNILA
Final 8/24/2022 Corrections Issued CRAIG VAUGHAN
Footing/Foundation/Slab 8/24/2022 Approved CRAIG VAUGHAN
Green Building Final 8/24/2022 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 8/24/2022 SGSOV Not Ready CRAIG VAUGHAN
Service/Power Release 8/24/2022 Not Ready for Inspection CRAIG VAUGHAN
Smoke Detectors 8/24/2022 Approved CRAIG VAUGHAN
Final 9/13/2022 Corrections Issued BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 9/13/2022 SGSOV Approved BRIAN SULLIVAN
Service/Power Release 9/13/2022 Not Ready for Inspection BRIAN SULLIVAN
Final 9/16/2022 OK to Issue CofO JEFFREY MEAD
Service/Power Release 9/16/2022 Approved JEFFREY MEAD