14545 W HATTERAS ST 1-2 91411

Certificate Information: 14545 W HATTERAS ST 1-2 91411

Application / Permit
21010-20000-02988
Plan Check / Job No.
B21VN07642
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
2 NEW ACCESSORY DWELLING UNIT AND ROOF TOP DECK ( 32'-6"X42'-6") PER LAMC 12.22 A.33(c), (d), and (g). BUILDING IS FULLY SPRINKLERED WITH NFPA 13D, TYPE VA CONSTRUCTION.
Permit Issued
Issued on 8/20/2024
Issuing Office
Valley
Current Status
CofO in Progress on 7/20/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/15/2021 APPLICANT
Assigned to Plan Check Engineer 7/15/2021 MOHAMMAD ESMAILI
Corrections Issued 7/17/2021 MOHAMMAD ESMAILI
Quality Review Completed 7/29/2021 OMID HEDAYAT
Building Plans Picked Up 8/2/2021 APPLICANT
Plan Check Approved 8/9/2024 MOHAMMAD ESMAILI
Issued 8/20/2024 APPLICANT
CofO in Progress 7/20/2026 VINCENT HANLEY

Permit Application Clearance Information

Construction near power lines Cleared 11/18/2021 RIDWAN HARDY
Low Impact Development Cleared 11/24/2021 LONDY ALVARADO
Address approval Cleared 1/3/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 1/3/2022 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 1/3/2022 CARLOS AGUILERA
Sewer availability Cleared 1/19/2022 CARLOS AGUILERA
"Q" conditions Cleared 6/27/2024 STEVEN WECHSLER
ZA Case Cleared 6/27/2024 STEVEN WECHSLER
ZA Case Cleared 6/27/2024 STEVEN WECHSLER
Hydrant and Access approval Cleared 7/12/2024 RUEL COLE

Contact Information

Contractor Owner-Builder       ,
Engineer Alson,, Ken; Lic. No.: C41697 9744 MAPLE ST 201      BELLFLOWER, CA 90706

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/27/2024 Partial Inspection RYAN SALAZAR
PLUMBING-Rough 9/17/2024 Partial Approval RYAN SALAZAR
Excavation/Setback/Form/Re-Bar 9/23/2024 Approved RYAN SALAZAR
Deputy Wood Construction 10/29/2024 Conditional Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 11/1/2024 Approved RYAN SALAZAR
ELECTRICAL-Rough 12/2/2024 Approved RYAN SALAZAR
HVAC-Rough 12/2/2024 Approved RYAN SALAZAR
Interior/Exterior Lathing 12/2/2024 Partial Approval RYAN SALAZAR
PLUMBING-Rough 12/2/2024 Approved RYAN SALAZAR
Insulation 12/9/2024 Corrections Issued LOUIS ESCOTO
Shower Pan 12/9/2024 Approved LOUIS ESCOTO
Drywall Nailing 12/13/2024 Approved RYAN SALAZAR
Insulation 12/13/2024 Approved RYAN SALAZAR
Interior/Exterior Lathing 12/17/2024 Approved RYAN SALAZAR
Gas Test 3/17/2025 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 3/17/2025 SGSOV Approved RYAN SALAZAR
BUILDING-Rough-Frame 7/17/2026 Approved VINCENT HANLEY
ELECTRICAL-Final 7/17/2026 Approved VINCENT HANLEY
Final 7/17/2026 OK to Issue CofO VINCENT HANLEY
Footing/Foundation/Slab 7/17/2026 Approved VINCENT HANLEY
Green Building Final 7/17/2026 Approved VINCENT HANLEY
Green Building Rough 7/17/2026 Approved VINCENT HANLEY
HVAC-Final 7/17/2026 Approved VINCENT HANLEY
PLUMBING-Final 7/17/2026 Approved VINCENT HANLEY
Service/Power Release 7/17/2026 Approved VINCENT HANLEY
Smoke Detectors 7/17/2026 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 7/17/2026 Approved VINCENT HANLEY