8409 W CORA ST 91040

Certificate Information: 8409 W CORA ST 91040

Application / Permit
21010-20000-02963
Plan Check / Job No.
B21VN07577
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2 STORY S.F.D WITH ATTACHED GARAGE ( 35'-9"x50'-5") FIRE SPRINKLER NFPA-13D
Permit Issued
Issued on 4/22/2022
Issuing Office
Current Status
CofO Issued on 3/25/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/15/2021 APPLICANT
Assigned to Plan Check Engineer 7/15/2021 MOHAMMAD ESMAILI
Corrections Issued 7/21/2021 MOHAMMAD ESMAILI
Quality Review Completed 7/29/2021 OMID HEDAYAT
Building Plans Picked Up 8/3/2021 APPLICANT
Applicant returned to address corrections 3/9/2022 MOHAMMAD ESMAILI
Plan Check Approved 4/13/2022 MOHAMMAD ESMAILI
Issued 4/22/2022 APPLICANT
CofO in Progress 3/4/2025 DAVID ANDERSON
Permit Finaled 3/25/2025 RUBEN SALAS
CofO Issued 3/25/2025 RUBEN SALAS
Permit Finaled 3/25/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/20/2021 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 9/20/2021 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 9/20/2021 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 9/20/2021 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 9/20/2021 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 9/20/2021 CARLOS AGUILERA
Miscellaneous Cleared 9/20/2021 CARLOS AGUILERA
Permit Cleared 9/20/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 9/21/2021 CARLOS AGUILERA
Sewer availability Cleared 9/21/2021 CARLOS AGUILERA
Trees in Parkway Cleared 12/2/2021 ADALBERTO VERA
Distance to fire station Cleared 1/8/2022 RUEL COLE
Hydrant and Access approval Cleared 1/8/2022 RUEL COLE
Low Impact Development Cleared 1/21/2022 TA ANH
Roof/Waste drainage to street Cleared 1/24/2022 CARLOS AGUILERA
GPI Written Notices Cleared 3/9/2022 MOHAMMAD ESMAILI
Grading Pre-Inspection Cleared 3/9/2022 MOHAMMAD ESMAILI

Contact Information

Contractor Owner-Builder       ,
Engineer Li,, Dacheng David; Lic. No.: C58075 1400 N KRAEMER BLVD #712      PLACENTIA, CA 92781

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/10/2022 Not Ready for Inspection MATTHEW NELSON
Pre-Inspection 6/10/2022 Not Ready for Inspection MATTHEW NELSON
Pre-Inspection 6/14/2022 Partial Inspection MATTHEW NELSON
Excavation/Setback/Form/Re-Bar 6/15/2022 Partial Inspection MATTHEW NELSON
Pre-Inspection 6/15/2022 Partial Inspection MATTHEW NELSON
Excavation/Setback/Form/Re-Bar 6/29/2022 Partial Approval MATTHEW NELSON
Pre-Inspection 6/29/2022 Partial Approval MATTHEW NELSON
Underground Mechanical 7/8/2022 Approved MATTHEW NELSON
Excavation/Setback/Form/Re-Bar 8/26/2022 Approved DAVID ANDERSON
Footing/Foundation/Slab 8/26/2022 Approved DAVID ANDERSON
Wood Frame 9/29/2022 Approved DAVID ANDERSON
BUILDING-Rough-Frame 11/10/2022 Not Ready for Inspection DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 11/10/2022 Approved DAVID ANDERSON
Green Building Rough 11/10/2022 Not Ready for Inspection DAVID ANDERSON
Verify Sprinkler Sign Off 11/10/2022 Corrections Issued DAVID ANDERSON
Special/Order Compliance 11/14/2022 Corrections Issued DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 1/17/2023 Approved WILLIAM WREN
Gas Test 1/17/2023 Approved WILLIAM WREN
PLUMBING-Rough 1/17/2023 Approved WILLIAM WREN
Green Building Rough 2/27/2023 Approved DAVID ANDERSON
HVAC-Rough 2/27/2023 Approved DAVID ANDERSON
BUILDING-Rough-Frame 3/10/2023 Approved DAVID ANDERSON
Deputy Wood Construction 3/10/2023 Conditional Approval JUAN VALENZUELA
ELECTRICAL-Rough 3/10/2023 Approved DAVID ANDERSON
Verify Sprinkler Sign Off 3/10/2023 Approved DAVID ANDERSON
Wood Frame 3/10/2023 Approved DAVID ANDERSON
Insulation 5/1/2023 Corrections Issued DAVID ANDERSON
Interior/Exterior Lathing 5/1/2023 Approved DAVID ANDERSON
Shower Pan 5/1/2023 Approved DAVID ANDERSON
Insulation 5/9/2023 Approved DAVID ANDERSON
Drywall Nailing 5/25/2023 Approved DAVID ANDERSON
Interior/Exterior Lathing 8/8/2023 Approved DAVID ANDERSON
Sewer 10/27/2023 Approved DAVID ANDERSON
ELECTRICAL-Final 10/15/2024 Not Ready for Inspection DAVID ANDERSON
PLUMBING-Final 10/15/2024 Not Ready for Inspection DAVID ANDERSON
Service/Power Release 10/15/2024 Not Ready for Inspection DAVID ANDERSON
Smoke Detectors 10/15/2024 Approved DAVID ANDERSON
Underground Mechanical 10/15/2024 Approved DAVID ANDERSON
ELECTRICAL-Final 11/1/2024 Corrections Issued DAVID ANDERSON
PLUMBING-Final 11/1/2024 Partial Approval DAVID ANDERSON
ELECTRICAL-Final 11/15/2024 Approved DAVID ANDERSON
Service/Power Release 11/15/2024 Not Ready for Inspection DAVID ANDERSON
Final 2/28/2025 OK to Issue CofO DAVID ANDERSON
Green Building Final 2/28/2025 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 2/28/2025 SGSOV Approved DAVID ANDERSON
Service/Power Release 2/28/2025 Approved DAVID ANDERSON