4729 N BALBOA AVE 91316
Certificate Information: 4729 N BALBOA AVE 91316
- Application / Permit
- 21010-20000-02936
- Plan Check / Job No.
- B21VN07537
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED (20'-8"x 24'3") ADU PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g) W/NFPA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 10/25/2021
- Issuing Office
- Current Status
- CofO Issued on 4/27/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/22/2021 | PETER MOSESIAN |
| Corrections Issued | 7/27/2021 | PETER MOSESIAN |
| Quality Review Completed | 7/30/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 8/2/2021 | APPLICANT |
| Plan Check Approved | 10/18/2021 | PETER MOSESIAN |
| Issued | 10/25/2021 | APPLICANT |
| CofO in Progress | 10/27/2025 | THOMAS FINNILA |
| Permit Finaled | 4/27/2026 | JOHN JANSON |
| CofO Issued | 4/27/2026 | JOHN JANSON |
| Permit Finaled | 4/27/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 8/17/2021 | DAGOVERTO GUERRERO |
| BHO/Hillside ordinance | Cleared | 8/17/2021 | DAGOVERTO GUERRERO |
| BHO/Hillside ordinance | Cleared | 8/17/2021 | DAGOVERTO GUERRERO |
| BHO/Hillside ordinance | Cleared | 8/17/2021 | DAGOVERTO GUERRERO |
| BHO/Hillside ordinance | Cleared | 8/17/2021 | DAGOVERTO GUERRERO |
| BHO/Hillside ordinance | Cleared | 8/17/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 8/17/2021 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 8/17/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 8/17/2021 | DAGOVERTO GUERRERO |
| Street Frontage | Cleared | 8/17/2021 | DAGOVERTO GUERRERO |
| ZA Case | Cleared | 8/19/2021 | DANIEL CORONADO |
| ZA Case | Cleared | 8/19/2021 | DANIEL CORONADO |
| ZA Case | Cleared | 8/19/2021 | DANIEL CORONADO |
| ZA Case | Cleared | 8/19/2021 | DANIEL CORONADO |
| ZA Case | Cleared | 8/19/2021 | DANIEL CORONADO |
| Hydrant and Access approval | Cleared | 10/1/2021 | KURT CORRAL |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Svatek Builders Inc; Lic. No.: 1037007-B | 13547 VENTURA BLVD #223 SHERMAN OAKS, CA 91423 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/22/2024 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 3/22/2024 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 3/22/2024 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 6/17/2024 | Corrections Issued | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/17/2024 | Not Ready for Inspection | THOMAS FINNILA |
| HVAC-Rough | 6/17/2024 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 6/17/2024 | Corrections Issued | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 7/18/2024 | Corrections Issued | THOMAS FINNILA |
| HVAC-Rough | 7/18/2024 | Conditional Approval | THOMAS FINNILA |
| PLUMBING-Rough | 7/18/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 7/23/2024 | Partial Approval | THOMAS FINNILA |
| HVAC-Rough | 7/23/2024 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 7/23/2024 | Conditional Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2024 | Partial Approval | THOMAS FINNILA |
| Drywall Nailing | 11/7/2024 | No Access for Inspection | MORRIS JACKSON |
| Green Building Rough | 11/7/2024 | No Access for Inspection | MORRIS JACKSON |
| Drywall Nailing | 11/26/2024 | Partial Approval | THOMAS FINNILA |
| Green Building Rough | 11/26/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Sewer | 1/21/2025 | Not Ready for Inspection | THOMAS FINNILA |
| Sewer | 1/24/2025 | Approved | JOHN COLEMAN |
| Gas Test | 1/28/2025 | Approved | JOHN COLEMAN |
| Rough-Elec/Plmb/HVAC | 1/28/2025 | Approved | JOHN COLEMAN |
| BUILDING-Rough-Frame | 3/18/2025 | Not Ready for Inspection | THOMAS FINNILA |
| Green Building Rough | 3/18/2025 | Approved | THOMAS FINNILA |
| Verify Sprinkler Sign Off | 3/18/2025 | Corrections Issued | THOMAS FINNILA |
| BUILDING-Rough-Frame | 3/24/2025 | Approved | THOMAS FINNILA |
| Verify Sprinkler Sign Off | 3/24/2025 | Approved | THOMAS FINNILA |
| Insulation | 4/21/2025 | Approved | JOHN KIDWELL |
| Drywall Nailing | 5/6/2025 | Approved | JOHN COLEMAN |
| Interior/Exterior Lathing | 5/6/2025 | Approved | JOHN COLEMAN |
| Shower Pan | 5/6/2025 | Approved | JOHN COLEMAN |
| Green Building Final | 9/19/2025 | Not Ready for Inspection | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 9/19/2025 | SGSOV Not Ready | THOMAS FINNILA |
| Service/Power Release | 9/19/2025 | Not Ready for Inspection | THOMAS FINNILA |
| Final | 9/29/2025 | Corrections Issued | THOMAS FINNILA |
| Green Building Final | 9/29/2025 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 9/29/2025 | SGSOV Approved | THOMAS FINNILA |
| Service/Power Release | 9/29/2025 | Not Required | THOMAS FINNILA |
| Smoke Detectors | 9/29/2025 | Approved | THOMAS FINNILA |
| Special/Order Compliance | 9/30/2025 | Corrections Issued | THOMAS FINNILA |
| Final | 10/3/2025 | Corrections Issued | THOMAS FINNILA |
| Final | 10/23/2025 | OK to Issue CofO | THOMAS FINNILA |