4729 N BALBOA AVE 91316

Certificate Information: 4729 N BALBOA AVE 91316

Application / Permit
21010-20000-02936
Plan Check / Job No.
B21VN07537
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED (20'-8"x 24'3") ADU PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g) W/NFPA 13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 10/25/2021
Issuing Office
Current Status
CofO Issued on 4/27/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/16/2021 APPLICANT
Assigned to Plan Check Engineer 7/22/2021 PETER MOSESIAN
Corrections Issued 7/27/2021 PETER MOSESIAN
Quality Review Completed 7/30/2021 OMID HEDAYAT
Building Plans Picked Up 8/2/2021 APPLICANT
Plan Check Approved 10/18/2021 PETER MOSESIAN
Issued 10/25/2021 APPLICANT
CofO in Progress 10/27/2025 THOMAS FINNILA
Permit Finaled 4/27/2026 JOHN JANSON
CofO Issued 4/27/2026 JOHN JANSON
Permit Finaled 4/27/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 8/17/2021 DAGOVERTO GUERRERO
BHO/Hillside ordinance Cleared 8/17/2021 DAGOVERTO GUERRERO
BHO/Hillside ordinance Cleared 8/17/2021 DAGOVERTO GUERRERO
BHO/Hillside ordinance Cleared 8/17/2021 DAGOVERTO GUERRERO
BHO/Hillside ordinance Cleared 8/17/2021 DAGOVERTO GUERRERO
BHO/Hillside ordinance Cleared 8/17/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 8/17/2021 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 8/17/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 8/17/2021 DAGOVERTO GUERRERO
Street Frontage Cleared 8/17/2021 DAGOVERTO GUERRERO
ZA Case Cleared 8/19/2021 DANIEL CORONADO
ZA Case Cleared 8/19/2021 DANIEL CORONADO
ZA Case Cleared 8/19/2021 DANIEL CORONADO
ZA Case Cleared 8/19/2021 DANIEL CORONADO
ZA Case Cleared 8/19/2021 DANIEL CORONADO
Hydrant and Access approval Cleared 10/1/2021 KURT CORRAL

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Svatek Builders Inc; Lic. No.: 1037007-B 13547 VENTURA BLVD #223      SHERMAN OAKS, CA 91423

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/22/2024 Approved VINCENT HANLEY
Footing/Foundation/Slab 3/22/2024 Approved VINCENT HANLEY
PLUMBING-Rough 3/22/2024 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 6/17/2024 Corrections Issued THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 6/17/2024 Not Ready for Inspection THOMAS FINNILA
HVAC-Rough 6/17/2024 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 6/17/2024 Corrections Issued THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 7/18/2024 Corrections Issued THOMAS FINNILA
HVAC-Rough 7/18/2024 Conditional Approval THOMAS FINNILA
PLUMBING-Rough 7/18/2024 Not Ready for Inspection THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 7/23/2024 Partial Approval THOMAS FINNILA
HVAC-Rough 7/23/2024 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 7/23/2024 Conditional Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 8/12/2024 Partial Approval THOMAS FINNILA
Drywall Nailing 11/7/2024 No Access for Inspection MORRIS JACKSON
Green Building Rough 11/7/2024 No Access for Inspection MORRIS JACKSON
Drywall Nailing 11/26/2024 Partial Approval THOMAS FINNILA
Green Building Rough 11/26/2024 Not Ready for Inspection THOMAS FINNILA
Sewer 1/21/2025 Not Ready for Inspection THOMAS FINNILA
Sewer 1/24/2025 Approved JOHN COLEMAN
Gas Test 1/28/2025 Approved JOHN COLEMAN
Rough-Elec/Plmb/HVAC 1/28/2025 Approved JOHN COLEMAN
BUILDING-Rough-Frame 3/18/2025 Not Ready for Inspection THOMAS FINNILA
Green Building Rough 3/18/2025 Approved THOMAS FINNILA
Verify Sprinkler Sign Off 3/18/2025 Corrections Issued THOMAS FINNILA
BUILDING-Rough-Frame 3/24/2025 Approved THOMAS FINNILA
Verify Sprinkler Sign Off 3/24/2025 Approved THOMAS FINNILA
Insulation 4/21/2025 Approved JOHN KIDWELL
Drywall Nailing 5/6/2025 Approved JOHN COLEMAN
Interior/Exterior Lathing 5/6/2025 Approved JOHN COLEMAN
Shower Pan 5/6/2025 Approved JOHN COLEMAN
Green Building Final 9/19/2025 Not Ready for Inspection THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 9/19/2025 SGSOV Not Ready THOMAS FINNILA
Service/Power Release 9/19/2025 Not Ready for Inspection THOMAS FINNILA
Final 9/29/2025 Corrections Issued THOMAS FINNILA
Green Building Final 9/29/2025 Approved THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 9/29/2025 SGSOV Approved THOMAS FINNILA
Service/Power Release 9/29/2025 Not Required THOMAS FINNILA
Smoke Detectors 9/29/2025 Approved THOMAS FINNILA
Special/Order Compliance 9/30/2025 Corrections Issued THOMAS FINNILA
Final 10/3/2025 Corrections Issued THOMAS FINNILA
Final 10/23/2025 OK to Issue CofO THOMAS FINNILA