13974 W LOUVRE ST 91331

Certificate Information: 13974 W LOUVRE ST 91331

Application / Permit
21010-20000-02926
Plan Check / Job No.
B21VN07505
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2-STORY DETACHED ADU (29'-4"x22'-4"), 1192 SQFT PER LAMC 12.22 A.33(c)(d)
Permit Issued
Issued on 3/15/2022
Issuing Office
Current Status
Issued on 3/15/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/15/2021 APPLICANT
Assigned to Plan Check Engineer 7/15/2021 PETER MOSESIAN
Corrections Issued 7/18/2021 PETER MOSESIAN
Quality Review Completed 7/30/2021 OMID HEDAYAT
Building Plans Picked Up 8/4/2021 APPLICANT
Plan Check Approved 2/11/2022 PETER MOSESIAN
Issued 3/15/2022 APPLICANT

Permit Application Clearance Information

Address approval Cleared 10/5/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 10/6/2021 CARLOS AGUILERA
Sewer availability Cleared 10/6/2021 CARLOS AGUILERA
Hydrant and Access approval Cleared 1/10/2022 GILBERT URREA
Low Impact Development Cleared 1/27/2022 JONATAN VELASQUEZ
Roof/Waste drainage to street Cleared 1/28/2022 ABDULLAH SADOZAI

Contact Information

Contractor Owner-Builder       ,
Engineer Medina,, Armando; Lic. No.: C83911 121 N VAIL AVE      MONTEBELLO, CA 90640

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 5/18/2022 Partial Approval MICHEL ABAJAN
Footing/Foundation/Slab 8/10/2022 Approved MICHEL ABAJAN
METHANE-Barrier 8/10/2022 Approved MICHEL ABAJAN
METHANE-Subgrade 8/10/2022 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 9/9/2022 Partial Approval MICHEL ABAJAN
PLUMBING-Rough 9/9/2022 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 9/23/2022 Partial Approval MICHEL ABAJAN
Underground Mechanical 9/23/2022 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 10/20/2022 Partial Approval MICHEL ABAJAN
PLUMBING-Rough 10/20/2022 Approved MICHEL ABAJAN
Deputy Wood Construction 10/24/2022 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 4/27/2023 Approved MICHEL ABAJAN
ELECTRICAL-Rough 4/27/2023 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 4/27/2023 Partial Approval MICHEL ABAJAN
Green Building Rough 4/27/2023 Approved MICHEL ABAJAN
HVAC-Rough 4/27/2023 Approved MICHEL ABAJAN
MERV13>=Rough 4/27/2023 Approved MICHEL ABAJAN
METHANE-Rough 4/27/2023 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 4/27/2023 Approved MICHEL ABAJAN
Interior/Exterior Lathing 5/8/2023 Approved MICHEL ABAJAN
Shower Pan 5/8/2023 Approved MICHEL ABAJAN
Insulation 12/18/2023 Approved MICHEL ABAJAN
Drywall Nailing 1/8/2024 Approved MICHEL ABAJAN
Interior/Exterior Lathing 1/8/2024 Approved MICHEL ABAJAN
ELECTRICAL-Rough 9/23/2024 Partial Approval MICHEL ABAJAN
Final 4/24/2026 Corrections Issued JENNIFER RABUCHIN
Green Building Final 4/24/2026 Approved JENNIFER RABUCHIN
MERV13>=Final 4/24/2026 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 4/24/2026 SGSOV Approved JENNIFER RABUCHIN
Service/Power Release 4/24/2026 Not Ready for Inspection JENNIFER RABUCHIN
Smoke Detectors 4/24/2026 Approved JENNIFER RABUCHIN
Final 5/28/2026 Corrections Issued MICHEL ABAJAN
Service/Power Release 5/28/2026 Corrections Issued MICHEL ABAJAN