11752 W ARMINTA ST 91605

Certificate Information: 11752 W ARMINTA ST 91605

Application / Permit
21010-20000-02925
Plan Check / Job No.
B21VN07500
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 30' X 20'3" IRREGULAR SHAPED 2-STORY DETACHED ACCESSORY DWELLING UNIT AS PER LAMC 12.22.A.33(C) AND (E) WITH 3' X 3'8" ATTACHED PORCH, ALL WORK PER ENGINEERING
Permit Issued
Issued on 12/1/2021
Issuing Office
Current Status
CofO Issued on 7/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/14/2021 APPLICANT
Assigned to Plan Check Engineer 7/15/2021 RARES BODEA
Corrections Issued 7/16/2021 RARES BODEA
Quality Review Completed 7/26/2021 STEVEN KIM
Building Plans Picked Up 7/27/2021 APPLICANT
Applicant returned to address corrections 11/1/2021 RARES BODEA
Plan Check Approved 12/1/2021 RARES BODEA
Issued 12/1/2021 APPLICANT
CofO in Progress 7/8/2024 MATTHEW NELSON
Permit Finaled 7/12/2024 RUBEN SALAS
CofO Issued 7/12/2024 RUBEN SALAS
Permit Finaled 7/12/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/24/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 8/24/2021 CARLOS AGUILERA
Permit Cleared 8/24/2021 CARLOS AGUILERA
Sewer availability Cleared 8/24/2021 CARLOS AGUILERA
Trees in Parkway Cleared 9/16/2021 ADRIAN SANCHEZ
Construction near power lines Cleared 9/28/2021 RIDWAN HARDY
Construction within easement Cleared 9/28/2021 RIDWAN HARDY
Hydrant and Access approval Cleared 10/11/2021 MATTHEW CRAIG
Low Impact Development Cleared 10/15/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 10/18/2021 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Mejia,, Fernando Finuliar; Lic. No.: C54382 8305 DUCOR AVE      WEST HILLS, CA 91304

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/14/2022 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Rough 4/14/2022 Partial Approval CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 4/18/2022 Approved CHRISTOPHER DELLEFIELD
Deputy Wood Construction 7/1/2022 Conditional Approval CHRISTOPHER DELLEFIELD
Drywall Nailing 7/8/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Gas Test 7/8/2022 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Rough 7/8/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 8/8/2022 Approved JENNIFER RABUCHIN
HVAC-Rough 8/8/2022 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 8/8/2022 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 8/31/2022 Corrections Issued CHRISTOPHER DELLEFIELD
HVAC-Rough 8/31/2022 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 8/31/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 9/6/2022 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 9/6/2022 Approved CHRISTOPHER DELLEFIELD
Green Building Rough 9/6/2022 Approved CHRISTOPHER DELLEFIELD
HVAC-Rough 9/6/2022 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Rough 9/6/2022 Approved CHRISTOPHER DELLEFIELD
Verify Sprinkler Sign Off 9/6/2022 Approved CHRISTOPHER DELLEFIELD
Insulation 9/13/2022 Approved CHRISTOPHER DELLEFIELD
Drywall Nailing 10/4/2022 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 10/4/2022 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 10/25/2022 Approved CHRISTOPHER DELLEFIELD
Shower Pan 10/25/2022 Approved CHRISTOPHER DELLEFIELD
Underground Mechanical 12/12/2022 Approved MATTHEW NELSON
ELECTRICAL-Final 11/3/2023 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 11/3/2023 Not Ready for Inspection CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 11/3/2023 SGSOV Not Ready CHRISTOPHER ROJAS
Service/Power Release 11/3/2023 Not Ready for Inspection CHRISTOPHER ROJAS
Smoke Detectors 11/3/2023 Approved CHRISTOPHER ROJAS
Service/Power Release 12/13/2023 Corrections Issued WILLIAM WREN
Final 3/19/2024 Corrections Issued MATTHEW NELSON
Green Building Final 3/19/2024 Corrections Issued MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 3/19/2024 SGSOV Not Ready MATTHEW NELSON
Service/Power Release 3/19/2024 Not Ready for Inspection MATTHEW NELSON
Final 6/6/2024 Corrections Issued MATTHEW NELSON
Green Building Final 6/6/2024 Corrections Issued MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 6/6/2024 SGSOV Not Ready MATTHEW NELSON
Service/Power Release 6/6/2024 Not Ready for Inspection MATTHEW NELSON
Final 6/13/2024 Corrections Issued MATTHEW NELSON
Green Building Final 6/13/2024 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 6/13/2024 SGSOV Approved MATTHEW NELSON
Service/Power Release 6/13/2024 Approved MATTHEW NELSON
Final 6/20/2024 Partial Approval KEVIN BERBERYAN
Final 7/3/2024 OK to Issue CofO MATTHEW NELSON