8337 N LOUISE AVE 91325
Certificate Information: 8337 N LOUISE AVE 91325
- Application / Permit
- 21010-20000-02920
- Plan Check / Job No.
- B21VN07484
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 35'-3" X 20'-1" TWO STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) PER LAMC 12.22 A.33(c) and (d); EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 6/9/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/1/2021 | SELLA BENYAMIN |
| Corrections Issued | 7/7/2021 | SELLA BENYAMIN |
| Quality Review Completed | 7/9/2021 | STEVEN KIM |
| Building Plans Picked Up | 7/14/2021 | APPLICANT |
| Plan Check Approved | 1/21/2022 | SELLA BENYAMIN |
| Issued | 6/9/2023 | APPLICANT |
| CofO in Progress | 4/5/2024 | JAVIER RAMOS JR |
| Permit Finaled | 5/15/2024 | RUBEN SALAS |
| CofO Issued | 5/15/2024 | RUBEN SALAS |
| Permit Finaled | 5/15/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 9/21/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 9/22/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 9/22/2021 | GABRIEL ROBLES |
| Hydrant and Access approval | Cleared | 11/30/2021 | KURT CORRAL |
| Low Impact Development | Cleared | 12/6/2021 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 12/20/2021 | ABDULLAH SADOZAI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Martirossyan,, Armen; Lic. No.: C64223 | 802 PORTOLA AVE GLENDALE, CA 91206 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/5/2023 | Partial Approval | JAVIER RAMOS JR |
| Sewer | 7/5/2023 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 7/17/2023 | Partial Inspection | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 7/17/2023 | Approved | JAVIER RAMOS JR |
| Deputy Wood Construction | 7/31/2023 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 7/31/2023 | Partial Approval | JAVIER RAMOS JR |
| Gas Test | 8/15/2023 | Partial Approval | JAVIER RAMOS JR |
| Underground Mechanical | 8/15/2023 | Partial Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 8/18/2023 | Partial Approval | JAVIER RAMOS JR |
| HVAC-Rough | 9/12/2023 | Corrections Issued | MICHEL ABAJAN |
| HVAC-Rough | 9/15/2023 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 9/21/2023 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 9/21/2023 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 9/21/2023 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 9/21/2023 | Corrections Issued | JAVIER RAMOS JR |
| Underground Mechanical | 9/21/2023 | Approved | JAVIER RAMOS JR |
| Deputy Wood Construction | 9/26/2023 | Conditional Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2023 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 10/4/2023 | Approved | JAVIER RAMOS JR |
| Verify Sprinkler Sign Off | 10/4/2023 | Approved | JAVIER RAMOS JR |
| Insulation | 10/12/2023 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 10/12/2023 | Partial Approval | JAVIER RAMOS JR |
| Drywall Nailing | 10/17/2023 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 11/20/2023 | Approved | JAVIER RAMOS JR |
| Shower Pan | 11/20/2023 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 2/20/2024 | Corrections Issued | JAVIER RAMOS JR |
| ELECTRICAL-Final | 2/23/2024 | Approved | JAVIER RAMOS JR |
| Service/Power Release | 2/23/2024 | Not Ready for Inspection | JAVIER RAMOS JR |
| PLUMBING-Final | 2/26/2024 | No Access for Inspection | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 4/2/2024 | No Access for Inspection | MATTHEW NELSON |
| Final | 4/2/2024 | No Access for Inspection | MATTHEW NELSON |
| Green Building Final | 4/2/2024 | No Access for Inspection | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 4/2/2024 | SGSOV Not Ready | MATTHEW NELSON |
| Service/Power Release | 4/2/2024 | No Access for Inspection | MATTHEW NELSON |
| Smoke Detectors | 4/2/2024 | No Access for Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 4/3/2024 | Approved | JAVIER RAMOS JR |
| Final | 4/3/2024 | OK to Issue CofO | JAVIER RAMOS JR |
| Gas Test | 4/3/2024 | Approved | JAVIER RAMOS JR |
| Green Building Final | 4/3/2024 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 4/3/2024 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 4/3/2024 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 4/3/2024 | SGSOV Approved | JAVIER RAMOS JR |
| Service/Power Release | 4/3/2024 | Approved | JAVIER RAMOS JR |
| Smoke Detectors | 4/3/2024 | Approved | JAVIER RAMOS JR |