4822 N KATHERINE AVE 91423

Certificate Information: 4822 N KATHERINE AVE 91423

Application / Permit
21010-20000-02913
Plan Check / Job No.
B21VN07437
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
NEW 15' X 21'-1" REC ROOM WITH HALF BATHROOM AND SHOWER WITH EXTERIOR ACCESS ONLY
Permit Issued
Issued on 1/14/2022
Issuing Office
Current Status
CofO Issued on 9/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/14/2021 APPLICANT
Assigned to Plan Check Engineer 6/24/2021 SELLA BENYAMIN
Corrections Issued 6/29/2021 SELLA BENYAMIN
Quality Review Completed 7/2/2021 STEVEN KIM
Building Plans Picked Up 7/6/2021 APPLICANT
Applicant returned to address corrections 12/14/2021 SELLA BENYAMIN
Plan Check Approved 1/11/2022 SELLA BENYAMIN
Issued 1/14/2022 APPLICANT
CofO in Progress 9/1/2022 MISAEL ESPARZA
Permit Finaled 9/1/2022 MICHAEL SMITH
CofO Issued 9/1/2022 MICHAEL SMITH
Permit Finaled 9/1/2022 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/22/2021 GABRIEL ROBLES
ZI Cleared 10/25/2021 MIGUEL GAMBOA
Low Impact Development Cleared 11/22/2021 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 11/30/2021 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/2/2022 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 3/3/2022 Partial Approval MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 3/7/2022 Approved MISAEL ESPARZA
Footing/Foundation/Slab 3/7/2022 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 3/10/2022 Not Ready for Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 3/11/2022 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 3/21/2022 Not Ready for Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 3/21/2022 Corrections Issued MISAEL ESPARZA
Green Building Rough 3/21/2022 Not Ready for Inspection MISAEL ESPARZA
Verify Sprinkler Sign Off 3/21/2022 Approved MISAEL ESPARZA
ELECTRICAL-Rough 3/24/2022 Conditional Approval MISAEL ESPARZA
PLUMBING-Rough 3/24/2022 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 3/29/2022 Approved MISAEL ESPARZA
ELECTRICAL-Rough 3/29/2022 Approved MISAEL ESPARZA
Insulation 3/29/2022 Approved MISAEL ESPARZA
Interior/Exterior Lathing 3/29/2022 Partial Approval MISAEL ESPARZA
Insulation 4/1/2022 Approved MISAEL ESPARZA
Drywall Nailing 4/6/2022 Approved MISAEL ESPARZA
ELECTRICAL-Final 7/1/2022 Corrections Issued MATT KELLERMAN
Gas Test 7/1/2022 Approved MATT KELLERMAN
Green Building Final 7/1/2022 Approved MATT KELLERMAN
PLUMBING-Final 7/1/2022 Corrections Issued MATT KELLERMAN
Smoke Detectors 7/1/2022 Approved MATT KELLERMAN
ELECTRICAL-Final 7/6/2022 Corrections Issued MISAEL ESPARZA
PLUMBING-Final 7/6/2022 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Final 7/12/2022 Approved MISAEL ESPARZA
PLUMBING-Final 7/12/2022 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 7/29/2022 Approved MISAEL ESPARZA
Final 7/29/2022 Corrections Issued MISAEL ESPARZA
Green Building Rough 7/29/2022 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 7/29/2022 SGSOV Approved MISAEL ESPARZA
Service/Power Release 7/29/2022 Not Ready for Inspection MISAEL ESPARZA
Final 8/16/2022 Partial Inspection MISAEL ESPARZA
Service/Power Release 8/16/2022 Not Required MISAEL ESPARZA
Final 8/31/2022 OK to Issue CofO MISAEL ESPARZA