4822 N KATHERINE AVE 91423
Certificate Information: 4822 N KATHERINE AVE 91423
- Application / Permit
- 21010-20000-02912
- Plan Check / Job No.
- B21VN07437
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 67' X 39' TWO STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 1/18/2022
- Issuing Office
- Current Status
- CofO Issued on 9/1/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/24/2021 | SELLA BENYAMIN |
| Corrections Issued | 6/29/2021 | SELLA BENYAMIN |
| Quality Review Completed | 7/2/2021 | STEVEN KIM |
| Building Plans Picked Up | 7/6/2021 | APPLICANT |
| Applicant returned to address corrections | 12/14/2021 | SELLA BENYAMIN |
| Plan Check Approved | 1/18/2022 | JON BLAINE |
| Issued | 1/18/2022 | APPLICANT |
| CofO in Progress | 9/1/2022 | MISAEL ESPARZA |
| Permit Finaled | 9/1/2022 | MICHAEL SMITH |
| CofO Issued | 9/1/2022 | MICHAEL SMITH |
| Permit Finaled | 9/1/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/22/2021 | GABRIEL ROBLES |
| Permit | Cleared | 9/22/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 9/22/2021 | GABRIEL ROBLES |
| ZI | Cleared | 10/25/2021 | MIGUEL GAMBOA |
| Low Impact Development | Cleared | 11/19/2021 | ANTHONY VARGAS |
| Trees in Parkway | Cleared | 11/24/2021 | ADALBERTO VERA |
| Roof/Waste drainage to street | Cleared | 11/30/2021 | DAGOVERTO GUERRERO |
| Hydrant and Access approval | Cleared | 12/6/2021 | MATTHEW CRAIG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/28/2022 | Partial Approval | ARAM AVEDISIAN |
| Excavation/Setback/Form/Re-Bar | 2/4/2022 | Partial Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 2/4/2022 | Partial Approval | MISAEL ESPARZA |
| Deputy Wood Construction | 2/10/2022 | Conditional Approval | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 2/11/2022 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 2/11/2022 | Partial Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 2/17/2022 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 3/2/2022 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 3/2/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 3/2/2022 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 3/2/2022 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 3/3/2022 | Approved | MISAEL ESPARZA |
| HVAC-Rough | 3/3/2022 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2022 | Partial Approval | MISAEL ESPARZA |
| PLUMBING-Rough | 3/7/2022 | Approved | MISAEL ESPARZA |
| Pre-Inspection | 3/11/2022 | Approved | MISAEL ESPARZA |
| Wood Frame | 3/11/2022 | Partial Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 3/21/2022 | Conditional Approval | MISAEL ESPARZA |
| Green Building Rough | 3/21/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Interior/Exterior Lathing | 3/21/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 3/21/2022 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 3/24/2022 | Partial Approval | MISAEL ESPARZA |
| Shower Pan | 3/24/2022 | Approved | MISAEL ESPARZA |
| Insulation | 4/1/2022 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 4/1/2022 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 4/6/2022 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 7/1/2022 | Not Ready for Inspection | MATT KELLERMAN |
| Gas Test | 7/1/2022 | Approved | MATT KELLERMAN |
| HVAC-Final | 7/1/2022 | Approved | MATT KELLERMAN |
| PLUMBING-Final | 7/1/2022 | Not Ready for Inspection | MATT KELLERMAN |
| ELECTRICAL-Final | 7/6/2022 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Final | 7/6/2022 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Final | 7/12/2022 | No Access for Inspection | MISAEL ESPARZA |
| PLUMBING-Final | 7/12/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 7/29/2022 | Approved | MISAEL ESPARZA |
| Final | 7/29/2022 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 7/29/2022 | Approved | MISAEL ESPARZA |
| Green Building Final | 7/29/2022 | Approved | MISAEL ESPARZA |
| Green Building Rough | 7/29/2022 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 7/29/2022 | SGSOV Approved | MISAEL ESPARZA |
| Service/Power Release | 7/29/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Smoke Detectors | 7/29/2022 | Approved | MISAEL ESPARZA |
| Final | 8/16/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Service/Power Release | 8/16/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Final | 8/31/2022 | OK to Issue CofO | MISAEL ESPARZA |
| Service/Power Release | 8/31/2022 | Approved | MISAEL ESPARZA |