6438 N FIRMAMENT AVE 91406

Certificate Information: 6438 N FIRMAMENT AVE 91406

Application / Permit
21010-20000-02908
Plan Check / Job No.
B21VN07424
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*ePLAN CHECK* (N) ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)&(d)
Permit Issued
Issued on 2/17/2022
Issuing Office
Current Status
Issued on 2/14/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/22/2021 APPLICANT
Assigned to Plan Check Engineer 7/15/2021 LAMAR DAVIS
Corrections Issued 7/20/2021 LAMAR DAVIS
Quality Review Completed 7/31/2021 PRANITA SHAH
Applicant returned to address corrections 9/7/2021 LAMAR DAVIS
Applicant returned to address corrections 9/15/2021 LAMAR DAVIS
Applicant returned to address corrections 1/5/2022 LAMAR DAVIS
Plan Check Approved 2/3/2022 LAMAR DAVIS
Issued 2/17/2022 APPLICANT
CofO in Progress 12/1/2023 RYAN SALAZAR
No Progress 2/14/2024 ROBERT GOLD

Permit Application Clearance Information

Miscellaneous Cleared 9/7/2021 LAMAR DAVIS
Address approval Cleared 9/10/2021 GABRIEL ROBLES
ZI Cleared 9/13/2021 RICHARD REASER
Eng Process Fee Ord 176,300 Cleared 10/20/2021 GABRIEL ROBLES
Sewer availability Cleared 10/20/2021 GABRIEL ROBLES
Hydrant and Access approval Cleared 11/24/2021 MATTHEW CRAIG
Low Impact Development Cleared 1/21/2022 TA ANH
Roof/Waste drainage to street Cleared 1/31/2022 JOSE DUARTE-DIAZ
Miscellaneous Cleared 2/2/2022 LAMAR DAVIS

Contact Information

Contractor S & S Design And Construction Inc; Lic. No.: 779304-B 25876 THE OLD ROAD UNIT 402      VALENCIA, CA 91381
Engineer Eden,, Joseph Taki; Lic. No.: C39955 14412 FRIAR ST      VAN NUYS, CA 91401

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/10/2022 Corrections Issued JENNIFER RABUCHIN
Sewer 3/10/2022 Not Ready for Inspection JENNIFER RABUCHIN
Footing/Foundation/Slab 4/14/2022 Corrections Issued RICHARD DOCKUS
PLUMBING-Rough 5/13/2022 Partial Approval RICHARD DOCKUS
Footing/Foundation/Slab 5/26/2022 Corrections Issued RAUL OLAGI
Footing/Foundation/Slab 6/21/2022 Corrections Issued RICHARD DOCKUS
Footing/Foundation/Slab 6/30/2022 Approved RICHARD DOCKUS
Deputy Drilled-In Anchors 8/3/2022 Conditional Approval DEANDRE HOFFMAN
Deputy Wood Construction 8/3/2022 Conditional Approval DEANDRE HOFFMAN
HVAC-Rough 8/16/2022 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 8/16/2022 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 8/22/2022 Corrections Issued RICHARD DOCKUS
HVAC-Rough 8/22/2022 Approved RICHARD DOCKUS
MERV13>=Rough 8/22/2022 Approved RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 8/29/2022 Corrections Issued RICHARD DOCKUS
Gas Test 8/29/2022 Approved RICHARD DOCKUS
PLUMBING-Rough 8/29/2022 Approved RICHARD DOCKUS
ELECTRICAL-Rough 9/2/2022 Approved RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 9/2/2022 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 9/12/2022 Partial Inspection JENNIFER RABUCHIN
Green Building Rough 9/12/2022 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 9/12/2022 Partial Approval JENNIFER RABUCHIN
Verify Sprinkler Sign Off 9/12/2022 Approved JENNIFER RABUCHIN
Insulation 9/20/2022 Corrections Issued ASHLEY THOMPSON
Insulation 10/3/2022 Approved RICHARD DOCKUS
Drywall Nailing 10/14/2022 Approved DEANDRE HOFFMAN
BUILDING-Rough-Frame 2/27/2023 Approved RYAN SALAZAR
Final 2/27/2023 Corrections Issued RYAN SALAZAR
Green Building Final 2/27/2023 Not Ready for Inspection RYAN SALAZAR
MERV13>=Final 2/27/2023 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 2/27/2023 SGSOV Approved RYAN SALAZAR
Service/Power Release 2/27/2023 Not Ready for Inspection RYAN SALAZAR
Smoke Detectors 2/27/2023 Approved RYAN SALAZAR
Final 11/30/2023 OK to Issue CofO RYAN SALAZAR
Green Building Final 11/30/2023 Approved RYAN SALAZAR
Service/Power Release 11/30/2023 Approved RYAN SALAZAR
Special/Order Compliance 1/16/2025 Corrections Issued RYAN SALAZAR