4955 N RUBIO AVE 91436
Certificate Information: 4955 N RUBIO AVE 91436
- Application / Permit
- 21010-20000-02905
- Plan Check / Job No.
- B21VN07422
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW (66'-1 3/16"x 39'-3 1/2") TWO STORY SINGLE FAMILY DWELLING WITH ATTACHED 2- CAR GARAGE. NFPA-13D AUTOMATIC FIRE SPRINKLER THROUGHOUT. WORK PER ENGINEER.
- Permit Issued
- Issued on 3/17/2022
- Issuing Office
- Current Status
- CofO Issued on 2/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/24/2021 | TROY DEGUZMAN |
| Corrections Issued | 6/26/2021 | TROY DEGUZMAN |
| Quality Review Completed | 6/28/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 6/29/2021 | APPLICANT |
| Applicant returned to address corrections | 2/22/2022 | TROY DEGUZMAN |
| Applicant returned to address corrections | 3/1/2022 | TROY DEGUZMAN |
| Plan Check Approved | 3/10/2022 | TROY DEGUZMAN |
| Issued | 3/17/2022 | APPLICANT |
| CofO in Progress | 2/6/2023 | VINCENT HANLEY |
| Permit Finaled | 2/13/2023 | JOHN JANSON |
| CofO Issued | 2/13/2023 | JOHN JANSON |
| Permit Finaled | 2/13/2023 | JOHN JANSON |
Permit Application Clearance Information
| Watercourse | Cleared | 8/27/2021 | DAGOVERTO GUERRERO |
| Permit | Cleared | 9/1/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 9/2/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 9/2/2021 | DAGOVERTO GUERRERO |
| Hydrant and Access approval | Cleared | 10/16/2021 | GILBERT URREA |
| Hydrant and Access approval | Cleared | 10/16/2021 | GILBERT URREA |
| Address approval | Cleared | 10/19/2021 | DAGOVERTO GUERRERO |
| Trees in Parkway | Cleared | 11/10/2021 | ADALBERTO VERA |
| Low Impact Development | Cleared | 1/18/2022 | JONATAN VELASQUEZ |
| Roof/Waste drainage to street | Cleared | 1/20/2022 | DAGOVERTO GUERRERO |
| Miscellaneous | Cleared | 2/7/2022 | DAGOVERTO GUERRERO |
| Green Code | Cleared | 2/17/2022 | TROY DEGUZMAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/21/2022 | Corrections Issued | SEAN HAUPT |
| Excavation/Setback/Form/Re-Bar | 3/24/2022 | Corrections Issued | DAVID SANDOVAL |
| Underground Mechanical | 3/24/2022 | Partial Approval | DAVID SANDOVAL |
| Excavation/Setback/Form/Re-Bar | 3/30/2022 | Approved | DAVID SANDOVAL |
| Footing/Foundation/Slab | 3/30/2022 | Approved | DAVID SANDOVAL |
| Underground Mechanical | 3/30/2022 | Partial Approval | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 4/6/2022 | Partial Approval | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 5/3/2022 | No Access for Inspection | DAVID SANDOVAL |
| ELECTRICAL-Rough | 6/6/2022 | Corrections Issued | ROBERT GOLD |
| HVAC-Rough | 6/6/2022 | Approved | ROBERT GOLD |
| PLUMBING-Rough | 6/6/2022 | Approved | ROBERT GOLD |
| BUILDING-Rough-Frame | 6/24/2022 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 6/24/2022 | Approved | VINCENT HANLEY |
| Green Building Rough | 6/24/2022 | Approved | VINCENT HANLEY |
| Shower Pan | 6/24/2022 | Approved | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 6/24/2022 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 6/28/2022 | Not Ready for Inspection | VINCENT HANLEY |
| Shower Pan | 6/28/2022 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 7/1/2022 | Approved | VINCENT HANLEY |
| Insulation | 7/7/2022 | Partial Approval | VINCENT HANLEY |
| Drywall Nailing | 7/15/2022 | Approved | VINCENT HANLEY |
| Sewer | 8/22/2022 | Corrections Issued | DAVID SANDOVAL |
| Sewer | 8/25/2022 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 1/4/2023 | Approved | VINCENT HANLEY |
| Final | 1/4/2023 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 1/4/2023 | Approved | VINCENT HANLEY |
| HVAC-Final | 1/4/2023 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 1/4/2023 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 1/4/2023 | SGSOV Approved | VINCENT HANLEY |
| Service/Power Release | 1/4/2023 | Corrections Issued | VINCENT HANLEY |
| Smoke Detectors | 1/4/2023 | Approved | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 1/4/2023 | Approved | VINCENT HANLEY |
| Final | 2/3/2023 | OK to Issue CofO | VINCENT HANLEY |
| Service/Power Release | 2/3/2023 | Approved | VINCENT HANLEY |