12611 W GREENE AVE 90066
Certificate Information: 12611 W GREENE AVE 90066
- Application / Permit
- 21010-20000-02884
- Plan Check / Job No.
- B21VN07348
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- NEW 21'-3" X 11'-2" DETACHED REC. ROOM WITH ATTACHED 8'-9" X 11'-2" TRELLIS
- Permit Issued
- Issued on 10/28/2021
- Issuing Office
- Current Status
- CofO Issued on 7/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/24/2021 | SELLA BENYAMIN |
| Corrections Issued | 6/29/2021 | SELLA BENYAMIN |
| Quality Review Completed | 7/2/2021 | STEVEN KIM |
| Building Plans Picked Up | 7/7/2021 | APPLICANT |
| Plan Check Approved | 10/28/2021 | SELLA BENYAMIN |
| Issued | 10/28/2021 | APPLICANT |
| CofO in Progress | 7/11/2023 | HERBERT GIRON |
| Permit Finaled | 7/14/2023 | DANIEL ORRANTE |
| CofO Issued | 7/14/2023 | DANIEL ORRANTE |
| Permit Finaled | 7/14/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/20/2021 | SAUL GARCIA |
| Low Impact Development | Cleared | 10/5/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 10/14/2021 | SAUL GARCIA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/17/2022 | Partial Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 3/23/2022 | Approved | BOBBY KEY |
| Deputy Reinf. Concrete | 3/25/2022 | Conditional Approval | BOBBY KEY |
| ELECTRICAL-Rough | 5/27/2022 | Approved | CLAYTON GRAHAM |
| PLUMBING-Rough | 5/27/2022 | Approved | CLAYTON GRAHAM |
| PLUMBING-Rough | 5/31/2022 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 6/1/2022 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 6/17/2022 | Conditional Approval | STEPHANIE SWANSON |
| Underground Mechanical | 7/5/2022 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 9/19/2022 | Partial Approval | HERBERT GIRON |
| Insulation | 10/14/2022 | Corrections Issued | HERBERT GIRON |
| Insulation | 10/27/2022 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 11/3/2022 | Partial Approval | JESUS RODRIGUEZ |
| Drywall Nailing | 11/3/2022 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 11/3/2022 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 11/3/2022 | Approved | JESUS RODRIGUEZ |
| Verify Sprinkler Sign Off | 11/3/2022 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 6/13/2023 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 6/20/2023 | Approved | EVAN COOPER |
| PLUMBING-Final | 6/20/2023 | Approved | EVAN COOPER |
| HVAC-Final | 6/23/2023 | Corrections Issued | HERBERT GIRON |
| BUILDING-Rough-Frame | 7/11/2023 | Approved | HERBERT GIRON |
| Final | 7/11/2023 | OK to Issue CofO | HERBERT GIRON |
| Green Building Final | 7/11/2023 | Approved | HERBERT GIRON |
| HVAC-Final | 7/11/2023 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 7/11/2023 | SGSOV Approved | HERBERT GIRON |
| Service/Power Release | 7/11/2023 | Approved | HERBERT GIRON |
| Smoke Detectors | 7/11/2023 | Approved | HERBERT GIRON |