12557 N SILVER SPUR CT 91326

Certificate Information: 12557 N SILVER SPUR CT 91326

Application / Permit
21010-20000-02867
Plan Check / Job No.
B21VN07316
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 1-STORY SFD W/ ATTACHED GARAGE PER LA CITY STD PLAN #654 (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 1/3/2022
Issuing Office
Current Status
CofO Issued on 5/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/14/2021 APPLICANT
Assigned to Plan Check Engineer 7/15/2021 NILOOFAR MEHRAIN
Plans on Hold 7/19/2021 RARES BODEA
Hold Released 8/4/2021 NILOOFAR MEHRAIN
Corrections Issued 8/5/2021 NILOOFAR MEHRAIN
Quality Review Completed 8/11/2021 STEVEN KIM
Building Plans Picked Up 8/17/2021 APPLICANT
Plan Check Approved 1/3/2022 JON BLAINE
Issued 1/3/2022 APPLICANT
CofO in Progress 5/12/2023 JEFFREY PARD
Permit Finaled 5/15/2023 MICHAEL SMITH
CofO Issued 5/15/2023 MICHAEL SMITH
Permit Finaled 5/15/2023 MICHAEL SMITH

Permit Application Clearance Information

"T" removal Cleared 11/1/2021 DANG NGUYEN
CPC Cleared 11/1/2021 DANG NGUYEN
Specific Plan Cleared 11/1/2021 DANG NGUYEN
Tract Map conditions Cleared 11/1/2021 DANG NGUYEN
Tract Map conditions Cleared 11/1/2021 DANG NGUYEN
ZA Case Cleared 11/1/2021 DANG NGUYEN
ZA Case Cleared 11/1/2021 DANG NGUYEN
ZI Cleared 11/1/2021 DANG NGUYEN
Address approval Cleared 11/2/2021 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 11/2/2021 LEE GUILBEAUX
Permit Cleared 11/2/2021 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 11/2/2021 LEE GUILBEAUX
Sewer availability Cleared 11/2/2021 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 11/2/2021 LEE GUILBEAUX
Hydrant and Access approval Cleared 12/7/2021 ROBERT DUFF
Low Impact Development Cleared 12/16/2021 AMMAR ELTAWIL
GPI Written Notices Cleared 12/28/2021 NILOOFAR MEHRAIN
Grading Pre-Inspection Cleared 12/28/2021 NILOOFAR MEHRAIN

Contact Information

Contractor Shapell Homes Inc; Lic. No.: 1001034-B 1140 VIRGINIA DR ATTN: TOLL   BROTHERS - TAGGERT/LEGAL    FORT WASHINGTON, PA 19034

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/22/2022 Partial Approval HENRY KIM
Deputy Pre-Stress Concrete 9/22/2022 Approved JEFFREY PARD
Footing/Foundation/Slab 9/23/2022 Approved JEFFREY PARD
Deputy Reinf. Concrete 9/26/2022 Approved JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 10/18/2022 Approved JEFFREY PARD
Sewer 10/26/2022 Approved JEFFREY PARD
Service/Power Release 10/31/2022 Not Ready for Inspection JEFFREY PARD
Underground Mechanical 11/3/2022 Approved JEFFREY PARD
Deputy Drilled-In Anchors 11/4/2022 Conditional Approval HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 11/15/2022 Corrections Issued JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 11/17/2022 Approved JEFFREY PARD
ELECTRICAL-Rough 11/30/2022 Not Ready for Inspection JEFFREY PARD
HVAC-Rough 11/30/2022 Approved JEFFREY PARD
Interior/Exterior Lathing 11/30/2022 Approved JEFFREY PARD
PLUMBING-Rough 11/30/2022 Approved JEFFREY PARD
BUILDING-Rough-Frame 12/2/2022 Not Ready for Inspection JEFFREY PARD
Green Building Rough 12/2/2022 Not Ready for Inspection JEFFREY PARD
Shower Pan 12/2/2022 Not Ready for Inspection JEFFREY PARD
Verify Sprinkler Sign Off 12/2/2022 Not Ready for Inspection JEFFREY PARD
ELECTRICAL-Rough 12/5/2022 Approved JEFFREY PARD
Insulation 12/8/2022 Approved JEFFREY PARD
Drywall Nailing 12/14/2022 Approved HENRY KIM
Interior/Exterior Lathing 12/14/2022 Partial Approval HENRY KIM
Drywall Nailing 1/10/2023 Corrections Issued HENRY KIM
Interior/Exterior Lathing 1/10/2023 Approved HENRY KIM
Gas Test 1/23/2023 Corrections Issued HENRY KIM
Gas Test 1/26/2023 Approved JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 1/30/2023 SGSOV Not Ready JEFFREY PARD
Gas Test 2/1/2023 Approved JEFFREY PARD
Service/Power Release 2/27/2023 Not Ready for Inspection JEFFREY PARD
Service/Power Release 3/2/2023 Approved JEFFREY PARD
ELECTRICAL-Final 4/18/2023 Corrections Issued JEFFREY PARD
HVAC-Final 4/18/2023 Approved JEFFREY PARD
PLUMBING-Final 4/18/2023 Approved JEFFREY PARD
ELECTRICAL-Final 4/21/2023 Approved JEFFREY PARD
BUILDING-Rough-Frame 5/11/2023 Approved JEFFREY PARD
Final 5/11/2023 OK to Issue CofO JEFFREY PARD
Green Building Final 5/11/2023 Approved JEFFREY PARD
Green Building Rough 5/11/2023 Approved JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 5/11/2023 SGSOV Approved JEFFREY PARD
Smoke Detectors 5/11/2023 Approved JEFFREY PARD
Verify Sprinkler Sign Off 5/11/2023 Approved JEFFREY PARD