16745 W MORRISON ST 91436

Certificate Information: 16745 W MORRISON ST 91436

Application / Permit
21010-20000-02851
Plan Check / Job No.
B21VN07312
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 21' X 28' ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)¹, (d)¹, and (g)
Permit Issued
Issued on 2/11/2022
Issuing Office
Current Status
CofO Issued on 3/20/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/14/2021 APPLICANT
Assigned to Plan Check Engineer 6/24/2021 SELLA BENYAMIN
Corrections Issued 6/29/2021 SELLA BENYAMIN
Quality Review Completed 7/2/2021 STEVEN KIM
Building Plans Picked Up 7/7/2021 APPLICANT
Applicant returned to address corrections 1/27/2022 SELLA BENYAMIN
Plan Check Approved 2/10/2022 SELLA BENYAMIN
Issued 2/11/2022 APPLICANT
CofO in Progress 3/9/2023 VINCENT HANLEY
Permit Finaled 3/20/2023 JOHN JANSON
CofO Issued 3/20/2023 JOHN JANSON
Permit Finaled 3/20/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 7/27/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 7/30/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 7/30/2021 DAGOVERTO GUERRERO
Hydrant and Access approval Cleared 9/18/2021 RUEL COLE
Low Impact Development Cleared 11/4/2021 TA ANH
Roof/Waste drainage to street Cleared 11/4/2021 DAGOVERTO GUERRERO
Construction near power lines Cleared 1/14/2022 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/14/2022 Partial Approval DAVID SANDOVAL
Underground Mechanical 3/14/2022 Approved DAVID SANDOVAL
Footing/Foundation/Slab 3/22/2022 Approved DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 5/4/2022 Partial Approval DAVID SANDOVAL
Deputy Wood Construction 5/16/2022 Conditional Approval DAVID SANDOVAL
ELECTRICAL-Rough 6/16/2022 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 6/16/2022 Approved VINCENT HANLEY
HVAC-Rough 6/16/2022 Approved VINCENT HANLEY
PLUMBING-Rough 6/16/2022 Approved VINCENT HANLEY
BUILDING-Rough-Frame 6/30/2022 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 6/30/2022 Approved VINCENT HANLEY
Green Building Rough 6/30/2022 Approved VINCENT HANLEY
Shower Pan 6/30/2022 Not Ready for Inspection VINCENT HANLEY
Verify Sprinkler Sign Off 6/30/2022 Approved VINCENT HANLEY
Interior/Exterior Lathing 7/6/2022 Partial Approval MORRIS JACKSON
Shower Pan 7/6/2022 Approved MORRIS JACKSON
Wood Frame 7/6/2022 No Access for Inspection MORRIS JACKSON
Drywall Nailing 7/18/2022 Approved VINCENT HANLEY
Interior/Exterior Lathing 7/18/2022 Approved VINCENT HANLEY
Gas Test 10/13/2022 Approved VINCENT HANLEY
Underground Mechanical 10/13/2022 Approved VINCENT HANLEY
ELECTRICAL-Final 3/8/2023 Approved VINCENT HANLEY
Final 3/8/2023 Corrections Issued VINCENT HANLEY
Green Building Final 3/8/2023 Approved VINCENT HANLEY
HVAC-Final 3/8/2023 Approved VINCENT HANLEY
PLUMBING-Final 3/8/2023 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 3/8/2023 SGSOV Approved VINCENT HANLEY
Service/Power Release 3/8/2023 Approved VINCENT HANLEY
Smoke Detectors 3/8/2023 Approved VINCENT HANLEY
Final 3/9/2023 OK to Issue CofO VINCENT HANLEY