16745 W MORRISON ST 91436
Certificate Information: 16745 W MORRISON ST 91436
- Application / Permit
- 21010-20000-02851
- Plan Check / Job No.
- B21VN07312
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 21' X 28' ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)¹, (d)¹, and (g)
- Permit Issued
- Issued on 2/11/2022
- Issuing Office
- Current Status
- CofO Issued on 3/20/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/24/2021 | SELLA BENYAMIN |
| Corrections Issued | 6/29/2021 | SELLA BENYAMIN |
| Quality Review Completed | 7/2/2021 | STEVEN KIM |
| Building Plans Picked Up | 7/7/2021 | APPLICANT |
| Applicant returned to address corrections | 1/27/2022 | SELLA BENYAMIN |
| Plan Check Approved | 2/10/2022 | SELLA BENYAMIN |
| Issued | 2/11/2022 | APPLICANT |
| CofO in Progress | 3/9/2023 | VINCENT HANLEY |
| Permit Finaled | 3/20/2023 | JOHN JANSON |
| CofO Issued | 3/20/2023 | JOHN JANSON |
| Permit Finaled | 3/20/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 7/27/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 7/30/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 7/30/2021 | DAGOVERTO GUERRERO |
| Hydrant and Access approval | Cleared | 9/18/2021 | RUEL COLE |
| Low Impact Development | Cleared | 11/4/2021 | TA ANH |
| Roof/Waste drainage to street | Cleared | 11/4/2021 | DAGOVERTO GUERRERO |
| Construction near power lines | Cleared | 1/14/2022 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/14/2022 | Partial Approval | DAVID SANDOVAL |
| Underground Mechanical | 3/14/2022 | Approved | DAVID SANDOVAL |
| Footing/Foundation/Slab | 3/22/2022 | Approved | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 5/4/2022 | Partial Approval | DAVID SANDOVAL |
| Deputy Wood Construction | 5/16/2022 | Conditional Approval | DAVID SANDOVAL |
| ELECTRICAL-Rough | 6/16/2022 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/16/2022 | Approved | VINCENT HANLEY |
| HVAC-Rough | 6/16/2022 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 6/16/2022 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 6/30/2022 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2022 | Approved | VINCENT HANLEY |
| Green Building Rough | 6/30/2022 | Approved | VINCENT HANLEY |
| Shower Pan | 6/30/2022 | Not Ready for Inspection | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 6/30/2022 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 7/6/2022 | Partial Approval | MORRIS JACKSON |
| Shower Pan | 7/6/2022 | Approved | MORRIS JACKSON |
| Wood Frame | 7/6/2022 | No Access for Inspection | MORRIS JACKSON |
| Drywall Nailing | 7/18/2022 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 7/18/2022 | Approved | VINCENT HANLEY |
| Gas Test | 10/13/2022 | Approved | VINCENT HANLEY |
| Underground Mechanical | 10/13/2022 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 3/8/2023 | Approved | VINCENT HANLEY |
| Final | 3/8/2023 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 3/8/2023 | Approved | VINCENT HANLEY |
| HVAC-Final | 3/8/2023 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 3/8/2023 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 3/8/2023 | SGSOV Approved | VINCENT HANLEY |
| Service/Power Release | 3/8/2023 | Approved | VINCENT HANLEY |
| Smoke Detectors | 3/8/2023 | Approved | VINCENT HANLEY |
| Final | 3/9/2023 | OK to Issue CofO | VINCENT HANLEY |