1554 N TONAWANDA AVE 90041

Certificate Information: 1554 N TONAWANDA AVE 90041

Application / Permit
21010-20000-02846
Plan Check / Job No.
B21VN07309
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED (20'-0"x32'-0"), 1185 SQFT TWO STORY ADU W/FRONT AND REAR PORCH (79 SQFT) PER LAMC 12.22 A.33(c)(d)
Permit Issued
Issued on 2/1/2022
Issuing Office
Current Status
CofO Issued on 4/20/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/10/2021 APPLICANT
Assigned to Plan Check Engineer 7/8/2021 PETER MOSESIAN
Corrections Issued 7/14/2021 PETER MOSESIAN
Quality Review Completed 7/19/2021 OMID HEDAYAT
Building Plans Picked Up 7/21/2021 APPLICANT
Plan Check Approved 2/1/2022 PETER MOSESIAN
Issued 2/1/2022 APPLICANT
CofO in Progress 4/17/2023 CRAIG VAUGHAN
CofO Issued 4/20/2023 DEROLD HAUFF
Permit Finaled 4/20/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/29/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 7/30/2021 CECILIO NAVARRO
Sewer availability Cleared 7/30/2021 CECILIO NAVARRO
Hydrant and Access approval Cleared 9/11/2021 MATTHEW CRAIG
Low Impact Development Cleared 9/15/2021 LONDY ALVARADO
Roof/Waste drainage to street Cleared 9/30/2021 CECILIO NAVARRO
Construction near power lines Cleared 12/13/2021 RIDWAN HARDY
Grading Pre-Inspection Cleared 2/1/2022 PETER MOSESIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Zelada,, Mynor Anibal; Lic. No.: C48666 14545 VICTORY BLVD 405      VAN NUYS, CA 91411

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/7/2022 Corrections Issued CRAIG VAUGHAN
Footing/Foundation/Slab 2/14/2022 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 2/28/2022 Partial Approval CRAIG VAUGHAN
Green Building Rough 2/28/2022 Not Ready for Inspection CRAIG VAUGHAN
Verify Sprinkler Sign Off 2/28/2022 Approved CRAIG VAUGHAN
PLUMBING-Rough 3/11/2022 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 3/21/2022 Partial Approval CRAIG VAUGHAN
Green Building Rough 3/21/2022 Not Ready for Inspection CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 4/21/2022 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 5/6/2022 Approved CRAIG VAUGHAN
HVAC-Rough 5/6/2022 Approved CRAIG VAUGHAN
PLUMBING-Rough 5/6/2022 Approved CRAIG VAUGHAN
Wood Frame 5/6/2022 Not Ready for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 5/17/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 5/17/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Green Building Rough 5/17/2022 Not Ready for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 5/23/2022 Corrections Issued ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 5/23/2022 Corrections Issued ALIZAH MAYAGOITIA
Green Building Rough 5/23/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Deputy Wood Construction 5/26/2022 Conditional Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 6/1/2022 Approved CRAIG VAUGHAN
Green Building Rough 6/1/2022 Approved CRAIG VAUGHAN
Insulation 6/1/2022 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 6/1/2022 Partial Approval CRAIG VAUGHAN
Drywall Nailing 6/6/2022 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 6/6/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
Underground Mechanical 6/6/2022 Corrections Issued KATHRYN BUTTERWORTH
Underground Mechanical 6/10/2022 Approved CRAIG VAUGHAN
Gas Test 8/18/2022 Approved CRAIG VAUGHAN
Final 10/19/2022 Corrections Issued CRAIG VAUGHAN
Green Building Final 10/19/2022 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 10/19/2022 SGSOV Not Ready CRAIG VAUGHAN
Service/Power Release 10/19/2022 Not Ready for Inspection CRAIG VAUGHAN
Smoke Detectors 10/19/2022 Corrections Issued CRAIG VAUGHAN
Final 11/28/2022 Corrections Issued CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 11/28/2022 SGSOV Approved CRAIG VAUGHAN
Service/Power Release 11/28/2022 Not Ready for Inspection CRAIG VAUGHAN
Smoke Detectors 11/28/2022 Approved CRAIG VAUGHAN
Final 12/7/2022 Corrections Issued CRAIG VAUGHAN
Service/Power Release 12/7/2022 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Final 12/20/2022 Approved BRIAN SULLIVAN
Final 12/20/2022 Not Ready for Inspection BRIAN SULLIVAN
Service/Power Release 12/20/2022 Not Ready for Inspection BRIAN SULLIVAN
Final 1/20/2023 Not Ready for Inspection CRAIG VAUGHAN
Service/Power Release 1/20/2023 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Final 4/14/2023 Approved CRAIG VAUGHAN
Final 4/14/2023 OK to Issue CofO CRAIG VAUGHAN
Service/Power Release 4/14/2023 Approved CRAIG VAUGHAN