19243 W KINZIE ST 91324
Certificate Information: 19243 W KINZIE ST 91324
- Application / Permit
- 21010-20000-02834
- Plan Check / Job No.
- B21VN07268
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW (27'-0"x 29'-0") IRR SHAPE DETACHED ACCESSORY DWELLING UNIT PER GCS 65852.2 (e) (1) (B) and LAMC 12.22 A.33 (c) (d) and (g). WORK PER LA STD WFPP.
- Permit Issued
- Issued on 1/24/2022
- Issuing Office
- Current Status
- CofO Issued on 9/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/8/2021 | TROY DEGUZMAN |
| Corrections Issued | 7/12/2021 | TROY DEGUZMAN |
| Building Plans Picked Up | 7/27/2021 | APPLICANT |
| Quality Review Completed | 8/26/2021 | OMID HEDAYAT |
| Applicant returned to address corrections | 8/26/2021 | TROY DEGUZMAN |
| Plan Check Approved | 1/24/2022 | TROY DEGUZMAN |
| Issued | 1/24/2022 | APPLICANT |
| CofO in Progress | 9/18/2023 | DAVID SCANTLIN |
| CofO Issued | 9/18/2023 | JOHN JANSON |
| Permit Finaled | 9/18/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 9/9/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 9/9/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 9/9/2021 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 10/29/2021 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 12/2/2021 | DAGOVERTO GUERRERO |
| Hydrant and Access approval | Cleared | 1/10/2022 | KURT CORRAL |
| Green Code | Cleared | 1/13/2022 | TROY DEGUZMAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/8/2022 | Corrections Issued | JEFFREY PARD |
| PLUMBING-Rough | 4/13/2022 | Partial Approval | JEFFREY PARD |
| Excavation/Setback/Form/Re-Bar | 5/3/2022 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 11/3/2022 | Not Ready for Inspection | DAVID SCANTLIN |
| ELECTRICAL-Rough | 11/3/2022 | Approved | DAVID SCANTLIN |
| Gas Test | 11/3/2022 | Approved | DAVID SCANTLIN |
| Green Building Rough | 11/3/2022 | Not Ready for Inspection | DAVID SCANTLIN |
| HVAC-Rough | 11/3/2022 | Approved | DAVID SCANTLIN |
| PLUMBING-Rough | 11/3/2022 | Approved | DAVID SCANTLIN |
| Sewer | 11/3/2022 | Approved | DAVID SCANTLIN |
| Verify Sprinkler Sign Off | 11/3/2022 | Not Ready for Inspection | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 11/23/2022 | Approved | JOHN KIDWELL |
| Green Building Rough | 11/23/2022 | Approved | JOHN KIDWELL |
| Special/Order Compliance | 11/23/2022 | Approved | JON MCHUGH |
| Verify Sprinkler Sign Off | 11/23/2022 | Approved | JOHN KIDWELL |
| Insulation | 12/16/2022 | Approved | JOHN KIDWELL |
| Drywall Nailing | 1/27/2023 | Approved | DAVID SCANTLIN |
| Shower Pan | 3/1/2023 | Approved | JUSTIN HAWLEY |
| Special/Order Compliance | 3/1/2023 | Approved | DAVID SANDOVAL |
| Final | 6/29/2023 | Corrections Issued | JOHN KIDWELL |
| Footing/Foundation/Slab | 6/29/2023 | Approved | JOHN KIDWELL |
| Green Building Final | 6/29/2023 | Not Ready for Inspection | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 6/29/2023 | SGSOV Not Required | JOHN KIDWELL |
| Service/Power Release | 6/29/2023 | Not Required | JOHN KIDWELL |
| Smoke Detectors | 6/29/2023 | Approved | JOHN KIDWELL |
| Final | 7/13/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Green Building Final | 7/13/2023 | Approved | DAVID SCANTLIN |
| Final | 9/7/2023 | Not Ready for Inspection | JOHN KIDWELL |
| Final | 9/18/2023 | OK to Issue CofO | DAVID SCANTLIN |